Title: MMF%20Introduction,%20Schedule,%20Budget%20%20Robert%20Ruland
1MMF Introduction, Schedule, Budget Robert Ruland
- Design Driving Requirements
- Magnetic Measurements Facility (MMF) Capabilities
- Magnetic Measurements
- Fiducialization
- Storage
- Magnetic Measurements Facility
- Location, Construction Schedule
- Implementation
- Schedule
- Manpower
- Summary
2MM Test Bench Design Driving Requirements
- Magnetic Measurements / Tuning
- The measured values for Keff shall be within
0.0005 (i.e., 0.015) of the design
values(LCLS Undulator Requirements PRD 1.4
001) - Alignment / Fiducialization -Undulators-
- Relative alignment of undulator to BBA quadrupole
driven by sensitivity of K to position,1.510-4
is correlated to 70µm in Y, to achieve this
requires finding the magnetic CLund to 20µm and
the CLquad to 10µm
3MMF Design Driving Requirements Undulator to
Quad Relative Alignment
- Quadrupoles are aligned to straight line using
BBA - Undulators need to follow quadrupole position
- Critical relative alignment tolerance of 70 µm in
Y - Extremely difficult to achieve in tunnel
environment with conventional alignment methods - Solution Undulator and Quad integrated on common
support, relative alignment performed in
laboratory using CMM - Design requirement accurate magnetic CL
determination for quad, undulator as well as CMM
for control of relative alignment
4Required MMF Tasks
- Tune
- Implement magnetic measurements equipment to
measure and tune Keff to within 0.0005 - Determine magnetic CL
- Implement magnetic measurements equipment to
determine magnetic centerline for quadrupole and
undulator to within 10 µm and 20 µm,
respectively. - Mechanical Fiducialization
- Correlate magnetic axis to fiducials for
quadrupole and undulator - Alignment Control
- Perform control of relative alignment quadrupole
to undulator - Assembly
- Implement assembly capability to integrate
components on common support
5MMF Set-up
- Assembly
- Cradle Assembly Bench
- Vacuum Chamber Alignment BenchGranite table with
Height Gauge - Undulator Segment / Cradle Storage
- At least 2 Und. Segments in MM lab (0.1º C)
- At least 2 Und. Segments in FA lab (1º C)
- 8 Cradles, quads, BPMs, Vacuum chamber and misc.
supports in FA lab (1º C) - About 20 undulator segments / cradles in storage
area (2.5º C)
- Magnetic Measurements
- Undulator Test Bench 1 (7 m)final gap setting,
final tuning - Undulator Test Bench 2 (4 m)
existingprototyping procedures, software
development, initial gap setting - Hall Probe Calibration SystemTest magnet and NMR
system - Quad Integrated Field Strength BenchStretched
Wire - Quadrupole Fiducialization PlatformVibrating
Wire - Pointed-Magnet Fixture Calibration Bench
- Fiducialization Assembly
- Fiducialization CMM 4.2 m
- Quadrupole Fiducialization PlatformVibrating
Wire mounted on CMM - BPM, Diagnostics Fiducialization
Magnetic Measurements Facility Requirements, PRD
1.4 - 002
6Layout
- Floor plan divided into three functional areas
- Magnetic Measurements ( 0.1º C)
- Fiducialization and Assembly ( 1º C)
- Storage ( 2.5º C)
- Test stand lay-out is driven by requirement to
match the Earth Magnetic Field conditions in lab
to Undulator Hall, i.e. azimuth and gap
orientation need to be identical
7Undulator Test Bench
- 8m Test Bench Implementation Schedule
- First article undulators will arrive at SLAC
around March 2006 - Production undulator delivery commences in summer
06 - BO MMF estimated Febr. 06
- Not enough time to complete integration, software
development, testing and commissioning before
first undulators arrive - Upgrade 4m bench obtained from APS with
equivalent hardware as 8m bench to serve as test
bed for software development and procedure
testing. - Will be using second bench for preliminary gap
setting will help production schedule
8Undulator Fiducialization
- Proposed Method Pointed Magnet Fixture
- Step 1 measure offset between undulator axis
and pointed-magnet reference fixture on MM Bench - Step 2 Measure pointed-magnet reference fixture
wrt undulator fiducials on CMM
9Quadrupole Fiducialization
- Finding the axis
- Based on Vibrating Wire or Pulsed Wire
- Have Pulsed Wire prototype setup. Routinely
achieve repeatabilities even in environment with
wide temperature swings of better than 5 µm - Also have Vibrating Wire prototype set-up. It
promises better yaw and pitch resolution.
Implementation based on setup by Dr. Temnykh from
Cornell - Transfer onto quadrupole fiducials
- Use Wire Finders (developed for VISA) to locate
wire and reference to its tooling balls - Use Coordinate Measurement Machine (CMM) to
transfer information from WF to Quad fiducials. - Vibrating Wire system will be mounted onto
optical table which can be set-up on undulator
fiducialization CMM
10SLAC LCLS Magnet Measurements Facility
- SLAC presently does not have a facility to
perform the magnetic measurements tasks necessary
for LCLS with the required accuracy Need to
build new facility. - Proposed Location Bldg 81, about 0.8 km away
from tunnel - Sufficient power for HVAC test equipment
- Ground motion and vibration measurements did not
indicate potential problems - Manageable space constraints
11Facility Construction Design Goals
- Funding
- Long Lead Procurement Funds, available in FY05
- Building Climate Control K1,400
- Construction Schedule
- T1 Aug 04 (Engineering)
- T2 Dec 04 (Final Construction Drawings)
- T3 May 05 (Construction Start)
- Beneficial Occupancy February 2006 (early finish
11/05) - Design Specifications
- Full set of specs LCLS-TN-04-1 Z. Wolf, R.
Ruland, "Requirements for the Construction of the
LCLS Magnetic Measurements Laboratory. - Magnetic Measurements Lab Temperature stability
of 0.1º C, short term temperature swings of up
to 0.3 ºC with less than 1 hour duration are
acceptable - Fiducialization Lab and Assembly Area
Temperature stability of 1º C - Storage Area Temperature Stability of 2.5º C
12Measurement Equipment
13Test Stand Implementation Schedule
14Test Stand Implementation Schedule
Schedule needs to be adjusted for effect of
Continuing Resolution
15Test Stand Implementation Schedule
Schedule needs to be adjusted for effect of
Continuing Resolution
16Manpower
- We have mostly ramped up the staffing in the
Magnetic Measurements Group to cope with the MMF
work and at the same time to allow our
conventional work to continue. - MMF Development
- 1 Senior Physicists
- 2.5 Engineering Physicists
- 1 add. Eng. Physicist (starts Jan. 1, 2005)
- 1 Metrology Engineer
- 2 Technicians
- 1 add. Technician (starts Jan 1, 2005)
- Conventional Work
- 1 Senior Physicist
- 0.5 Engineering Physicist
- 1 Technician
- 1 Research Assistant
- Will be able to handle Undulator Production
Measurements with existing manpower, supplemented
with help from the Alignment Engineering and
Quality Inspection Groups. There is no other
significant competing work scheduled.
17END of Presentation
18Fiducialization Accuracy Requirement
Required fiducialization accuracy is driven by
error budget for aligning undulator wrt to
beam-based-aligned quad, i.e. in order to stay
within the total error budget of 70µm vertically,
quadrupole fiducialization needs to done to 25µm
and undulator segments need to be done to 40µm
(see PRD1.4-001 General Undulator System
Requirements)
197 m Test Bench Specifications Outline
- Total travel length in Z 7000 mm.
- Make carriage as long as cost wise reasonable to
minimize yaw, at least 1000 mm - Make bench cross-section as large as reasonable,
min 800 mm wide, 500 mm high - Travel length in X as much as bench width
permits, min 300 mm - Travel length in Y 100 mm or more if w/o loss of
accuracy - Granite base straightness in Z and X 10 µm
- Position accuracy at probe tip required Z, X, Y
5 µm, 20 µm, 20 µm, desired 3 µm, 10 µm, 10 µm. - Z-axis drive linear motor with 1 µm positioning
resolution - X, Y axes drive lead-screw with 1 µm positioning
resolution - No stepping motor on any axis
- Z position measurement with incremental encoder
type Heidenhain LIDA, a second encoder on
opposite side of bench could be considered to
monitor yaw rotation of carriage - X, Y axes motion measured with Heidenhain glass
scale encoders - Perpendicularity of X and Y axes to be better
than 0.1 mrad - Probe axis be equipped with rotary stage with
0.01º resolution and 4-axes goniometer - Support bench on foundation separate from
laboratory floor - Support undulator independent from bench on
common foundation - Support cable carrier independent from bench on
common foundation - Equip cable carrier with drive system
synchronized as slave to Z-axis drive