SKDP NClass JackUp Unit - PowerPoint PPT Presentation

1 / 60
About This Presentation
Title:

SKDP NClass JackUp Unit

Description:

Self-Elevating Drilling Unit (KFELS Class N) Harsh Environment North Sea and Canadian waters ... Drillers Cabin elevated 2 m with 2 chairs and Cyberbase ... – PowerPoint PPT presentation

Number of Views:708
Avg rating:3.0/5.0
Slides: 61
Provided by: dage4
Category:

less

Transcript and Presenter's Notes

Title: SKDP NClass JackUp Unit


1
N-Class Harsh Environment Jack-up
Drilling/Production
SKDP N-Class Jack-Up Unit Drilling/Production
2
SKDP CLASS-N JACK-UP UNIT TABLE OF CONTENT
  • Company Background
  • Rig Concept and Design
  • Operations Management
  • QHSE

1
2
3
4
3
COMPANY BACKGROUNDSKEIE DRILLING PRODUCTION ASA
  • Skeie Drilling Production ASA KDP (SKDP)
    established September 2006 and located in
    Kristiansand
  • 49 Owned by Skeie Group and 5 by Keppel
    Offshore Ltd, 46 external investors
  • Administrative services will be hired from Skeie
    Group AS
  • Operational Management Agreement with ProCorp
    Offshore Management Services
  • Signed contract for design and construction of
    three (3) KFELS Class N Jack-up Unit with
    delivery March, August and December 2010.
  • OTC listed in Oslo

4
COMPANY BACKGROUND COMPANY SET-UP
  • Board of Directors
  • Chairman, Bjarne Skeie
  • Board member Anne Breive
  • Board member Edmund Mah (KFELS)
  • Management
  • Birger Skeie, CEO
  • Willy Tørhaug, COO
  • Dag Eggan, QHSE Director
  • Stein Eggan, VP Business Develpoment
  • Svein Anton Bjørnholmen,CFO

5
COMPANY BACKGROUND PROJECT SCHEDULE RIG 1
1) Delivery of unit 2 August 2010 2)
Delivery of unit 3 December 2010
6
COMPANY BACKGROUND KEY COMPANY STRUCTURE
Skeie Drilling Production ASA (Kristiansand,
Norway)
SKDP Project Management/Project Supervision
Group (Kristiansand, Norway KFELS Shipyard,
Singapore Sub-Contractor Manufacturer Yards)
SKDP Operations Management Group
(Onshore) (Trondheim, Norway Local Base Office)
KFELS Shipyard Singapore (Engineering /
Construction)
Rig Offshore Organisation
Sub-Contractor Manufacturer Yards (Engineering /
Construction)
7
COMPANY BACKGROUND SKDP PROJECT ORGANISATION
8
SKDP CLASS-N JACK-UP UNIT TABLE OF CONTENT
  • Company Background
  • Rig Concept and Design
  • Operations Management
  • QHSE

1
2
3
4
9
RIG CONCEPT AND DESIGN SPECIFICATIONS FOR
DRILLING AND PRODUCTION OPERATIONS
  • Self-Elevating Drilling Unit (KFELS Class N)
  • Harsh Environment North Sea and Canadian waters
  • High pressure/high temperature deep well GoM
  • Extended reach and transverse skidding of Drill
    Floor
  • Combined drilling production facilities
  • 10 wells tie back or sub sea completion with
    production module installed
  • Subsea well completion with HP riser and dry BOP
    over large subsea template 75 ft long x 66 ft
    wide
  • Large Subsea X-mas tree (45 mt) handling through
    Cantilever hatch 5x6m
  • Operations in 122 meters water depths. Optional
    132 meters with 10m leg extension.
  • Drilling depth up to 35,000ft (10,667M) Set
    Back.
  • Derrick 1000 tons.
  • Triangular hull with three (3) triangular truss
    legs each fitted with a spud can with tip at its
    lower end. The modified triangular hull is 264
    ft. (80.46M) long, 289 ft. (88.09M) wide, and 35
    ft. (10.67M) deep at the side.

10
RIG CONCEPT AND DESIGN COMBINED DRILLING AND
PRODUCTION OPERATIONS
Limits Area 12,918 sq ft (1,200M2)
Height 52.5ft (16M)
The Cantilever and Drill Floor can be
repositioned 26ft (7.92M) to the Port side of the
Vessel, to allow space for installation of a
future production process module.
11
RIG CONCEPT AND DESIGN N-CLASS COMBINED DRILLING
/ PRODUCTION UNIT WITH STORAGE TANK
12
RIG CONCEPT AND DESIGN SPECIFICATIONS FOR
DRILLING AND PRODUCTION OPERATIONS
  • Drill Floor located on the substructure above the
    cantilever.
  • Cantilever capable of being skidded fore and aft
    with center line (primary Cantilever position) of
    rotary up to 75 ft (22.86m) aft of sternIt can
    be relocated 26 (7,92m) ft to port (secondary
    Cantilever position)
  • The Drill Floor can be skidded 20 ft (6.1m) port
    and starboard of the Cantilever centerline both
    in primary position and in secondary position
  • Max operation envelop over a pre-installed
    Jacket/Wellhead Platform75 ft aft of Transom,
    20 ft to starboard of hull centerline and 46 ft
    to port of hull centerline.

13
RIG CONCEPT AND DESIGN SPECIFICATIONS FOR
DRILLING AND PRODUCTION OPERATIONS
  • The Cantilever and Drill Floor can be
    repositioned 26ft (7.92M) to the Port side of
    the Vessel, to allow space for installation of a
    future Production Process Module. 12,918ft2
    (1,200m2) in area and 52.5ft (16m) maximum in
    height.
  • With the cantilever/drill floor in offset
    position with 10 wells tie back (1500 ton
    tension)
  • Row no. 1 - 5 wells 12 ft aft of transom
  • Row no. 2 - 5 wells 20 ft aft of transom
  • With cantilever in secondary position and no
    production module installed a total of 12,918
    square ft (1200 square m) free main deck area is
    available in one common space. (Page 16)

14
RIG CONCEPT AND DESIGN CANTILEVER FOOTPRINTS
15
RIG CONCEPT AND DESIGN CANTILEVER FOOTPRINTS
16
RIG CONCEPT AND DESIGN CANTILEVER FOOTPRINTS
17
RIG CONCEPT AND DESIGN DESIGN OPERATING
CONDITIONS STANDARD DRILLING MODE
Design Operating Conditions Design Storm
Survival Conditions
18
RIG CONCEPT AND DESIGN TECHNICAL COMPARISON WITH
PEERS
1) Enhanced version of the existing CJ-70 design
with increased drilling depth, increased variable
deck load and 1000 t top drive.
Source Company, ODS Petrodata
19
RIG CONCEPT AND DESIGN OPTIMISED DRILLING
EQUIPMENT
  • Derrick model SSBN 1100-40X40X180
  • Crown block/Traveling block 1100 sh. Tons 72
    diameter 2 groves.
  • Top Drive Model HPS 1000-2E-AC-KT Torque 78450
    ft. Lbs. continious
  • Retractable Dolly for Top Drive
  • Drawworks 1100 sh. Ton 16 lines 4XAC GE motors
    with regenerative braking disc brakes for
    parking and emergency brake
  • 1000 sh Ton Rotary support table 49 ½, Max 15
    rpm / 45000 ft.Lbs. at 5 rpm.

20
RIG CONCEPT AND DESIGN OPTIMISED DRILLING
EQUIPMENT
  • Dead line anchor 160 kip. Floor mounted Rotary
    slip
  • Dual Hydraulic catheads with commen control panel
  • PipeRacker 10 ton lifting capacity. Parallel
    racking of 90 ft stand. Off line Stand building
    capability for DP, DC and Casing.
  • Fingerboard 35.000 ft racking capacity. DP- 286
    st. of 5 7/8 and 108 st. of 6 5/8, 10 st. of 9
    ½ DC, 22 st. of Casing 9 5/8 or 14 st. of
    Casing 13 3/8
  • Belly Board for 199 stands locking latch for each
    pipe slot.
  • Stabbing basket/work basket 250kg swl.

21
RIG CONCEPT AND DESIGN OPTIMISED DRILLING
EQUIPMENT
  • Drillers Cabin elevated 2 m with 2 chairs and
    Cyberbase operation stations.
  • Catwalk machine with remote control from DCR or
    Drillfloor and tail in /out arm for transport of
    DP, DC and Casing up to 36 OD to rotary,
    separate pull back winch on Catwalk structure
  • Drillfloor Manipulator Arm with remote control
    from DCR or Drillfloor for DF handling and tail
    in operations of large tubular
  • Pipe handling crane Working radius 25 m. SWL 5.5
    Mt.
  • 3 x 5t utility winches with remote control,
    installed in Derrick level at level 4
  • 1 x Derrick Man rider winch with remote control,
    installed in Derrick level at level 4
  • Iron Roughneck type Wellquip

22
RIG CONCEPT AND DESIGN WELL CONTROL EQUIPMENT
  • Surface 18 ¾ BOP Shaffer 18-15M
  • - 1ea spherical 10 K
  • - 1 ea pipe Ram 15 K
  • - 1ea. Shear Ram 15 K with Booster for max
    shearing capacity
  • - 2ea. Pipe Ram 15 K
  • - 2ea.3 1/16 15 M type DB valve Hydraulic
    operated
  • - 2ea 3 15 M type B valve manually operated
  • Koomy Hydraulic Power Unit
  • - Remote control of HPU functions from Drillers
    panel and Tool Pushers panel
  • - Emergency remote operating panel located in
    central control room
  • - 3000 psi. working pressure
  • - Accumulator capacity to meet API 16D and PSA
    requirements

23
RIG CONCEPT AND DESIGN WELL CONTROL EQUIPMENT
24
RIG CONCEPT AND DESIGN WELL CONTROL EQUIPMENT
  • Choke Kill Manifold 15 K
  • - 2ea Remote operated chokes from Drillers
    Cabin
  • - 2ea. Manual operated choke
  • 1ea. Poor boy degasser 12 went line a bow top of
    derrick
  • 2ea. Swaco CD 1400 degasser with blower
  • Vetco KFDJ-500 49 ½ diverter System 16 diverter
    lines

25
RIG CONCEPT AND DESIGN EQUIPMENT IN CANTILEVER
  • BOP Overhead Crane with 2x75 T SWL The two hoist
    beams are split to operate 75 T of each side of
    the well centre. For lifting of the BOP or sub
    sea X-mas Tree, the 2 hoists beams run
    simultaneously.
  • 2 x120 t BOP skid to handle BOP or X-Mas tree
    from landing area to BOP Crane working area, or
    onto BOP 130 t trolley
  • 1 x Cellar deck opening 130 t BOP trolley
  • 1 x Cellar deck transverse moving and telescopic
    work basket
  • 1 x Cellar deck Man rider winch with remote
    control, installed in cantilever
  • 2 x 5 t utility winches local control in Cellar
    deck
  • Conductor Tensioning System 700K capacity fold
    down conductor tensioning platform (centre 20
    feet aft of hull)
  • Riser Tensioning System 700K capacity 4
    cylinders installed below Drillfloor

26
RIG CONCEPT AND DESIGN MUD CIRCULATING SYSTEM
  • 3 x Mud HP pumps 7500 psi. Model NO 14-P-120.
    2200 HP/2 GE AC motors and Centrifugal pumps
    arranged for charging.
  • 5 x VSM 300 dual deck Shale Shakers.
  • 2 x centrifugal mixing pumps arranged with
    manifold for simultaneous mixing in active pits
    and reserve pits
  • Power and piping provided to delegated place for
    Centrifuge.

27
RIG CONCEPT AND DESIGN MUD PIT CAPACITIES
28
RIG CONCEPT AND DESIGN BULK TANKS (P TANKS)
  • Five (5) mud tanks each of 1875 cu ft (50 m3) and
    four (4) cement tanks each of 1875 cu ft, (50
    m3).
  • Operating pressure of 60 psi and bulk material
    specific gravity 2.163.
  • Mud additive system with skid mounted sack
    cutting unit, big bag unit, liquid additive skid,
    high rate mixer, HP mud share unit, density
    control unit and caustic mixing unit.

29
RIG CONCEPT AND DESIGN TANK CAPACITY
Tank Capacity Total capacity Fuel oil (3
tanks) 880 m3 Base oil tank 330
m3 Brine oil (2 tanks) 782 m3 Mud
pit 1050 m3 Mud contaminated tank
10 m3 Drillwater (28 tanks) 6094
m3 Fresh water (2 tanks) 831 m3
30
RIG CONCEPT AND DESIGN DECK LOAD PLAN
  • Canteliver Pipe Rack (800 kips) 363 ton 2637
    kg/m2
  • Total setback area (1200 kips) 544 ton
  • Drillfloor working area 1953 kg/m2
  • Drawworks house top 459 kg/m2
  • Main deck (outside pipe rack) 2075 kg/m2
  • Pipe rack (Main Deck) 2637 kg/m2
  • IWO Production module 3330 kg/m2
  • Quarters deck plan 459 kg/m2
  • Loading platform 1318 kg/m2
  • Emergency Generator room 459 kg/m2
  • Helideck is to be designed for Sikorsky S61 and
    S92 Helicopters in accordance with CAP 437   

31
RIG CONCEPT AND DESIGN RIG CRANES
  • 1 ea. Electro hydraulic driven Deck crane
    starboard aft.Certified for Zone 1, compliance
    with PSA/NMD regulation. SWL 50 Mt _at_ 36 m SWL
    38,1 Mt. _at_ 46m
  • 2 ea. Diesel engines driven Deck cranes port side
    and starboardCompliance with PSA/NMD
    regulations.1 off SWL 50 Mt _at_ 36 m / SWL 38,1 Mt
    _at_ 46m1 off SWL 50 Mt _at_ 20 m / SWL 14,5 Mt _at_ 46m

32
RIG CONCEPT AND DESIGN WELL TESTING PROVISIONS
AND AREAS
  • Well Testing Area assigned starboard aft between
    aft leg and cantilever (area approx 7,5 x 9,0
    meters)
  • Two burner booms will be installed on each side
  • Piping System
  • 3" line, 600 psi(102.9bar), HP Gas
  • 3" line, 600psi (102.9ar), Main oil
  • 2" line, 150psi(10bar). Diesel oil
  • 4" line, 150psi (10bar), Gas vent.
  • 4" line, 150psi (10bar), Compressed air
  • 4" line, 150psi (10bar), Sea water (Water curtain
    from seawater ring line)
  • 3/4" line, 150 psi (10bar), Butane
  • 4 connections for temporary air compressors
    feeding the test plant.

33
SKDP CLASS-N JACK-UP UNIT TABLE OF CONTENT
  • Company Background
  • Rig Concept and Design
  • Operations Management
  • QHSE

1
2
3
4
34
OPERATIONS MANAGEMENTOPERATIONS MANAGEMENT
STRUCTURE
Skeie Drilling Production ASA
Prod Jack 3 Ltd
Prod Jack 2 Ltd
Prod Jack 1 Ltd
ProCorp Offshore Management Services AS
Offshore Production Services AS (100 owned by
Skeie Technology AS)
Management Agreement
35
OPERATIONS MANAGEMENTOPERATIONAL MANAGEMENT
RESPONSIBILITY
  • Development and implementation of total
    integrated QHSE Management System
  • Emergency Preparedness management
  • Budget and Cost management / reporting
  • Execution of Drilling Contract including
    operational/ admin. interface with Client

OPERATIONAL MANAGEMENTSERVICES
  • Unit insurance management
  • Contract Management
  • Personnel management including recruitment,
    training, salary, taxation etc.
  • Regulatory Compliance/Class-, Flag State- and
    Coastal Authority management

36
OPERATIONS MANAGEMENT MAIN ORGANISATION(PROCORP
OFFSHORE MANAGEMENT SERVICES AS)
CEO/Managing DirectorStein Eggan
Finance/Accounting Mng.Heidi Fornes
Office Administration Mng.Hilde Traaseth
Human Resources Mng.Geir Bjørsvik
Marketing(CEO/Managing Director)
QHSE DirectorDag Eggan
Operations DirectorWilly Tørhaug
QHSE ManagerJonny Mourad
Drilling Eq. Specialist Kristian Skagemo
Contract/Project Base Organisation
37
OPERATIONS MANAGEMENT RIG BASIS ORGANISATION
UNIT 1, 2 3
Unit Owner
Operations DirectorWilly Tørhaug
Operations Manager(SKDP Units)
Administration/Document Control
Wages/SalaryCoordinator
Personnel Co-Ordinator
Rig Accounting
Operational/Technical Support Manager
Supply/PurchasingManager
QHSE Manager
Technical/Maintenance Manager
EI Manager
This function may support several units
depending on the area of Operations This
function shall interface with/be assigned to the
Project Organisation/Construction Management
group during the Design and Construction Phases.
Rig ManagerRig Base Organisation (Ref. next
chart)
Drilling Manager
Marine Manager
Process Manager(as applicable)
38
OPERATIONS MANAGEMENT RIG BASE ORGANISATION (PER
UNIT)
Operations Manager(SKDP Units)
Rig Manager
QHSE Advisor
Technical Superintendent
Supply/Purchasing
Rig Accountant
Personnel Co.ord.
This function may be same as for Basis
Organisation depending of the area of Operations
(i.e. Norway)
Rig OrganizationOIM
39
OPERATIONS MANAGEMENT UNIT OFFSHORE ORGANISATION
Permanent Crew Onboard - 25
Drilling Mode Crew 14
Offshore Installation Manager (OIM)
Production Mode Crew - 7
Pending Activity Crew 6
Admin.
Camp Boss
Total Crew No. Drilling/Production Mode - 52
Medic
Safety Officer
Rig OperationsSuperintendent
1(1) x Storekeeper
ProcessSection Leader
Marine / StabilitySection Leader
Technical Section Leader
Drilling Section Leader(Toolpusher)
Electrical Section Leader
Stability S.L. II
2 x Process CCR Op.
Tourpusher
2 x Electricians
Ass. Tech. Sect. Leader
4 x Process Operator
1 x Electronics
2 x Crane Operators
1(1) x Driller
Engine Room Op.
3(3) x Roustabouts
2 x Assistant Driller
Motorman
2 x Derrickman
Hydraulic Engineer
2 x Pumpman
Rig Mechanic
Welder
6 x Roughneck
Number in brackets () indicates additional
number for full Drilling or combined
Drilling/Production mode activity.
40
OPERATIONS MANAGEMENT MANNING SCHEDULE (as per
February 2008)
41
SKDP CLASS-N JACK-UP UNIT TABLE OF CONTENT
  • Company Background
  • Rig Concept and Design
  • Operations Management
  • QHSE

1
2
3
4
42
QHSESKDP QHSE POLICY
43
QHSEREGULATORY FRAMEWORK / CERTIFICATION
  • Designed, constructed, installed, operated and
    maintained in compliance with relevant and latest
    Norwegian Continental Shelf requirements as
    defined by the Petroleum Safety Authority Norway
    (PSA)
  • Compliance based on DNV class requirements, the
    requirements of the Norwegian Maritime
    Directorate (as applicable) and additional PSA
    requirements and will generally follow the
    recommendations as outlined in Handbook for
    Application for Acknowledgement of Compliance.
  • For Working Environment, NORSOK standard S-002
    specifically applies as design specification.
  • Above Norwegian Coastal State requirements
    selected as basis to achieve equivalent or higher
    regulatory framework for world-wide operations
    including North Sea, Canada and US waters.

44
QHSEREGULATORY FRAMEWORK / CERTIFICATION
  • Det Norske Veritas (DNV) Classification with the
    following class notations
  • 1A1 Self Elevating Drilling Unit (N)
  • Drill (N)
  • HELDK-SH
  • CRANE
  • Designed in accordance with the following DNV
    specifications
  • OSS-101 Rules for Classification of Offshore
    Drilling and Support Units
  • OSS-201 Verification of Compliance with Norwegian
    Shelf Regulations

45
QHSEREGULATORY FRAMEWORK / CERTIFICATION
  • The vessel shall be registered in the Panama
    Ship Register and comply with the latest and
    relevant International Rules and Regulations for
    world-wide operations including
  • Governing maritime regulations for the country
    the Unit is to be flagged to.
  • The International Maritime Organizations (IMO)
    Code for the Construction of Mobile Offshore
    Drilling Unit, 1989 Resolution A.649(16)
    (generally known as the 1989 IMO MODU Code)
  • The International Convention for the Safety of
    Life at Sea (SOLAS) 1974, 1978 Protocol and later
    amendments where being referred by the IMO MODU
    Code only.
  • The International Convention for the Prevention
    of Marine Pollution from Ships 1973, 1978
    Protocol and later amendments (MARPOL 73/78).
  • The International Convention on Load Lines 1966,
    1988 Protocol.
  • The International Convention of Tonnage
    Measurement of Ships 1969.
  • International Convention for the Prevention of
    Collision at Sea.
  • International Telecommunication Union ( ITU)
    Radio Regulations (1982)
  • ILO 92 and ILO 133
  • SNAME TR Bulletin 5-5A Site Specific Assessment
    of Mobile Jackup Units, May 1944/1977 is only for
    Site Specific Assessment and not applicable for
    the current assessment. When applicable, the
    Unit will have to be re-assessed base on the
    Specific Site environmental and soil conditions.

46
QHSEREGULATORY FRAMEWORK / CERTIFICATION
  • Handbook For Application For Acknowledgement of
    Compliance (AoC) as published by the Norwegian
    Shipowners Association Revision 03 dated July 1,
    2006
  • Norwegian Helicopter Deck regulation BSL D-51
    issued by the Norwegian Civil Aviation Authority
    (equal to Regulation of 22 December 1993 No. 1240
    concerning helicopter decks on mobile offshore
    units (NMD)) and CAP 437 issued by UK Civil
    Aviation Authority. Where discrepancies are
    identified between BSL D-51 and CAP 437, BSL D-51
    shall apply.
  • Regulation and guidelines for potable water
    system and potable water supply on offshore unit
    issued by Norwegian Institute for Public Health
    (NIPH) including
  • NIPH Guidelines for Sufficient, Safe and Good
    Potable Water Offshore dated 19 December 2005.
  • Regulation of 4 September 1987 No 860 concerning
    potable water system and potable water supply on
    mobile offshore units
  • Electrical standards
  • IEC standards and other relevant standards as
    defined within the AoC Handbook.
  • The Offshore Deck Cranes shall be designed,
    installed and tested in accordance with the
    specific requirements for Offshore Cranes as
    defined directly by the PSA regulations (not NMD)
    effective at time of signing of this Contract.

47
QHSECONCEPT RISK AND WORKING ENVIRONMENT STUDIES
  • Concept Risk and Working Environment Studies
    performed (Workshop) in co-operation with DNV
    iaw. principles outlined in NORSOK Z-013
    including
  • Pre-screening Hazard Review
  • Detailed Hazard Review
  • Evacuation Review
  • Working Environment Review (LQ and Working Areas)
  • Environmental System design specification review
    (Zero Discharge)
  • Performed prior to Contract Agreement for
    construction, to verify feasibility of concept
    both against prevailing Regulatory Framework
    (Norwegian Continental Shelf), ALARP principle
    for Risk Mitigation and to identify any key cost
    drivers for the design, construction and
    operations of the unit.

48
QHSECONCEPT RISK AND WORKING ENVIRONMENT STUDIES
  • Initial concept analysis summarized in Concept
    Analysis Report with specific actions for further
    follow-up both during the detailed design phase
    and throughout the phases of construction and
    into Operations, to ensure risk ALARP and meeting
    the intention of the specified Regulatory
    Framework.
  • Concept Analysis further concluded with
    assistance from DNV in separate reports for
    reference during the detailed design phases
  • Concept Working Environment Review report
  • Concept Evacuation Study Report
  • Concept Risk Analysis Report
  • Concept Emergency Preparedness Review report
  • Environmental Design Specification (included in
    Technical Design Specification)

49
QHSEDESIGN/CONSTRUCTION RISK AND WORKING
ENVIRONMENT STUDIES (As per principles outlined
in NORSOK Z-013)
50
QHSEDESIGN/CONSTRUCTION RISK AND WORKING
ENVIRONMENT STUDIES (As per principles outlined
in NORSOK Z-013)
51
QHSEDESIGN/CONSTRUCTION RISK AND WORKING
ENVIRONMENT STUDIES (As per principles outlined
in NORSOK Z-013)
52
QHSEDESIGN/CONSTRUCTION RISK AND WORKING
ENVIRONMENT STUDIES (As per principles outlined
in NORSOK Z-013)
53
RISK WORKING ENVIRONMENT ASSESSMENTS Norwegian
PSA Requirements (NORSOK Standard Z-013) UK HSE
Safety Case Regs PFEER Regulations
Coarse Concept Safety Evaluation
Concept Noise Vibration Lighting Evaluations
Concept Working Environment Evaluation
Concept Environmental Evaluation(Zero Discharge
Compliance)
Noise Prediction Design Study
Working Environment Area Charts(Design standard
requirements)
HAZID Review Layout Review
Zero Discharge Assessment
Lighting Prediction Design Study
High Level Risk Assessment(Including Fire
Explosion Risk Analysis)
  • Rig Design w/DALs
  • Risk Acceptance CriteriaQHSE Management System
  • Reliability vulnerability Analysis (FMEA)
  • DP system
  • Emergency power
  • Ballast system
  • Fire water/sprinkler
  • Fire Gas detection
  • Control communication
  • BOP control system

Quantitative Risk Analysis(QRA)
  • Evacuation, Escape Rescue (EER) Analysis
  • Frequency Consequence of
  • Blow-outs
  • HC leaks - mud system well test
  • Ship collision
  • Dropped objects
  • Helicopter crash onboard
  • Fires explosions
  • DP failure
  • Occupational accidents

Working Environment Assessments vs. Working
Environment Area Charts
PFEER /Emergency Preparedness Analysis
UK Safety Case / Norwegian AoC/ Certificate
of Fitness etc.
  • Input to Operations Manuals/Em. Prep. Manual
  • Input to Emergency Prep. Analysis
  • Input to Maintenance Criticality Analysis
  • Verify compliance with regulations
  • Verify compliance with Company Risk Acceptance
    Criteria

Environmental HAZOP Review
Noise Vibration Survey(Sea Trials/Operations)
Ergonomic/MMI Assessment (Sea Trials/Operations)
Lighting Survey (Sea Trials/Operations)
Air Quality Assessment (Sea Trials/Operations)
CONCEPT PHASE DETAILED ENG. PHASE OPERATIONS
ISPS Ship Security Assessment Ship Security
PlanISPS Code Compliance
Final Working Environment Area Charts for rig
54
QHSEPERSONNEL TRAINING AND COMPETENCE SYSTEM
  • Qualification Requirements for all offshore
    positions is being defined and implemented for
    guidance and follow-up during recruitment and
    training process.
  • Draft Training Matrix including both Regulatory
    Training (Certification and Safety), Vendor
    Training and In-House Training has been prepared
    for the new SKDP Jack-up units.
  • Link to SKDP Offshore Training Matrix
  • Specific Competency Development Assurance
    Procedure for the SKDP Jack-up operations being
    prepared by Operations Personnel defining the Rig
    Specific Competency Development Program to be
    effective for the SKDP North Sea Operations. This
    includes development of in-house QHSE Management
    System training packages.
  • Separate Personnel Competency Administration
    system OCS (Onsoft Computer Systems) has been
    installed and implemented, to provide detailed
    planning tool for the training and competency
    development activities and further the actual
    scheduling, execution and documentation of all
    training activities to be performed.

55
QHSE MANAGEMENT SYSTEM INTEGRATED QHSE
MANAGEMENT SYSTEM MODEL
QHSE Management System
Key Management System Elements

56
QHSE MANAGEMENT SYSTEM SUPPORTING CONTROLLING
DOCUMENTATION
Unit Specific Level 1)
Corporate Level

CONTRACT SPECIFIC QUALITY PLANS
CORPORATE VISIONS AND POLICIES
OPERATION MANUALS FOR THE UNIT
COMPANY STANDARDS
EMERGENCY PREPAREDNESS MANUAL
ONSHORE CONTINGENCY MANUAL
SOPEP MANUAL
QHSE MANAGEMENT SYSTEM MANUAL
SHIP SECURITY PLAN
QHSE MANAGEMENT PROCEDURES MANUAL
UNIT SAFETY BOOKLET
COMPANY CORPORATE FORMS
POTABLE WATER MANUAL
UNIT TECHNICAL SPECIFICATION
Above Corporate Documentation will also apply for
local Company Entities including Branch- and Base
Offices with local adjustments as required in the
QHSE Management Procedures Manual and Onshore
Contingency Manual.
US CG LoI / SAFETY CASE / AoC / CoF(including
Key Risk/Working Environment Analysis)
YEARLY HES PROGRAM FOR THE UNIT
1) Unit specific as built documentation,
including PIDs, drawings, design philosophies,
vendor documentation etc., is not included in the
listing of Unit Specific Documentation.
57
QHSE MANAGEMENT SYSTEM SUPPORTING CONTROLLING
DOCUMENTATION
Corporate Level
Summary of Content

QHSE MANAGEMENT SYSTEM MANUAL
Overall description of the processes defined
within each element of the integrated QHSE
Management System (ref. previous slide).
Detailed generic procedures defining the
controlled processes established for management
of Administration, Finance Accounting,
Personnel (HR), Marketing, Technical Supervision,
Operations, Logistics/Supply and general QHSE
management.
QHSE MANAGEMENT PROCEDURES MANUAL
ONSHORE CONTINGENCY MANUAL
Detailed description of the companys procedures
for management of Emergency Preparedness and
Response.
58
QHSE MANAGEMENT SYSTEM SUPPORTING CONTROLLING
DOCUMENTATION
Unit Specific Level
Summary of Content

Detailed description of various Bridging
procedures between the Companys established QHSE
Management System and the specific contractual
requirements with the Client.
CONTRACT SPECIFIC QUALITY PLANS
Detailed unit specific instructions and
procedures for the operations of the units
systems and equipment including Marine, Jacking
Operations, Ballast/Stability, Technical/Electrica
l, Anchor Handling and Drilling/Production
Operations (including Well Control).
OPERATION MANUALS FOR THE UNIT
EMERGENCY PREPAREDNESS MANUAL
Detailed procedures and guidelines for the
management of Emergency preparedness and response
onboard the unit, in line with pre-defined
situations of Hazards and Accidents (i.e. DSHA
scenarios)
SOPEP MANUAL
Detailed procedures and guidelines for the
management of oil/chemical discharge emergency
situations onboard the unit (as per IMO and Flag
State requirements.
Detailed procedures and guidelines for the
management of Ship Security (e.g. anti terror
measures) including detailed Ship Security
Assessment as per IMO and Flag State required
ISPS Code.
SHIP SECURITY PLAN
UNIT SAFETY BOOKLET
Detailed introduction handbook for offshore
employees and visitors, including an abbreviated
version of the QHSE Management System and key
procedures.
POTABLE WATER MANUAL
Detailed system description and
procedures/guidelines for the Potable Water
System, including procedures for operations,
maintenance and testing of Potable Water.
UNIT TECHNICAL SPECIFICATION
Detailed technical specification and description
of the key systems and equipment onboard the unit.
Various applications for Regulatory Approval from
relevant Coastal Authorities, including
description of compliance with local rules and
regulations, detailed compliance studies and
risk/emergency preparedness and working
environment related analysis and assessments.
US CG LoI / SAFETY CASE / AoC / CoF(including
Key Risk/Working Environment Analysis)
Annual program defining the overall QHSE goals
and objectives for the operations, and further
detailing QHSE related improvement activities for
the upcoming period.
YEARLY HES PROGRAM FOR THE UNIT
59
QHSE MANAGEMENT SYSTEM RIG OPERATIONS MANUAL
TABLE OF CONTENT

PART 0 GENERAL
PART 1 MARINE OPERATIONS
PART 2 DRILLING OR PRODUCTION OPERATIONS
PART 3 SPECIAL OPERATIONS (e.g. H2S, SimOps,
Complex Wells etc.)
PART 1.1 MARINEOPERATIONS
PART 1.2 TECHNICAL / ELECTRICAL
PART 1.3 STABILITY OPERATIONS
PART 1.4 RIG MOVE OPERATIONS
) Specific manuals containing operational
descriptions, instructions and procedures for the
operations of the units systems and equipment to
be developed and implemented depending on the
type of unit (e.g. drilling and/or production
unit).
60
Contact details Skeie Drilling Production
ASA Tordenskjoldsgate 9 N-4612
Kristiansand Norway Telephone 47 38 04 19
40 Fax 47 38 04 19 41
Write a Comment
User Comments (0)
About PowerShow.com