Title: Supplier Introduction
1Supplier Introduction Tutorial 26 February
2008David MichaudSupplier SSC LT Chair
2First Time Mtg Attendees
- Introduce yourself, tell us
- Your Name
- Company Name
- What commodity(ies) will be audited
3Orientation Agenda
- Introduction to Nadcap
- Basic Tools and Advice
- How to Prepare for your Audit
- What to Expect During the Audit
- Important Post Audit Information
- Additional Information
4Welcome to Nadcap
- The leading, worldwide cooperative program of
major companies designed to manage a cost
effective consensus approach to special processes
and products and provide continual improvement
within the aerospace industry. - Nadcap is an industry managed program.
5(No Transcript)
6(No Transcript)
7(No Transcript)
8Industry Managed
Audit Checklist
Process Evaluation/ Improvement
Auditor Qualification Selection
Corrective Actions As Required
Industry experts manage all key steps
Audits Conducted
Audit Results
9PRI/Nadcap Organizational Structure
- Executive leaders
- Legal entity
- Fiduciary responsibility
- Set policy
- Provide the Vision
- Senior Quality Leaders
- Reviews Nadcap resources in Europe
- Promotes Nadcap in Europe
- Monitors affordability issues as they relate to
Nadcap in Europe.
European Regional Advisory Board (EURAB)
Nadcap Management Council (NMC)
Task Groups Special Processes Chemical
Processing Coatings Heat Treating Materials
Testing Nonconventional Machining Surface
Enhancement Nondestructive Testing Welding Systems
Products AQS (AC7004) Composites Distributors E
lectronics Fasteners Fluid Distribution
Systems Sealants, Elastomer Seals
- Senior quality leaders managers
- Oversee operation of Nadcap
- Establish implement policy procedures
- Task group coordination development
- Identify, develop and deploy improvement
- Technical Experts
- Determine requirements
- Develop documents
- Accept corrective action
- Final decision on accreditation
10Industry-Managed Active Customer Audits/Certs
11Nadcap eAuditNet Process
Suppliers
PRI Audit Scheduled
Auditor Assigned
Request Audit
Task Group Approval
Audit Completed
PRI Technical Staff Review
Issue Cert
12Orientation AgendaSection II
- Introduction to Nadcap
- Basic Tools and Advice
- How to Prepare for your Audit
- What to Expect During the Audit
- Important Post Audit Information
- Additional Information
13Primary Documents
- The two most important documents you need are
the - Audit checklist
- Audit handbook (if available)
- You will be audited to the checklist AC7XXX as
developed by the Task Group. Secure both from
www.eauditnet.com in advance of the audit
14eAuditNet PRI Website
- www.eAuditNet.com
- Public Documents
- eAuditNet Supplier Guide Pre Post-Audit
Tutorials - Audit Handbooks
- Miscellaneous documents (Auditor training,
Pyrometry, etc.) - User Documents
- Checklists
- www.pri-network.org
- Nadcap, Supplier Info
- SSC page contact details, mentoring and more
- PRI/Nadcap from a Supplier Perspective
- Root Cause Corrective Action Tools/Training
materials and dates - Check both sites often updates made frequently
15Nadcap
16Supplier Page
Staff Contacts
eAuditNet
17Checklists
User Documents
Public Documents
18Nadcap Procedure Hierarchy
Roles and responsibilities for Nadcap Auditors,
and technical/administrative clarifications to
facilities.
Detail the procedures by which PRI/Nadcap Staff
operate.
Describe the scope and general procedures for
each specific PRI/Nadcap commodity program.
Procedures by which the Nadcap program operates.
Quality policy describing the quality system of
organization.
Aerospace Standard - requirements for
implementing Nadcap industry consensus-based
accreditation programs.
19NIP 7-04 Accreditation Term
- Your term of accreditation begins in conjunction
with your audit date, not the issue date of your
certificate. - Accreditation terms are tied to the Nadcap
quarterly cycles. - Reference NIP 7-04 on www.eauditnet.com under
User Documents
20NIP 7-07 Export Controlled Materials and
Information Jan 16, 2008
- The US government has determined that certain
products, processes and technical information
must be controlled. - The documents which control this are
- ITAR International Traffic in Arms Regulation
- EAR Export Administration Regulations
- Exports can occur by seeing or discussing
controlled material in addition to obtaining
copies of the material
Throughout this presentation when we refer to
Export Control (EC) we are referring to ITAR/EAR
21NIP 7-07 Export Controlled Materials Information
- The Nadcap process uses both Unrestricted and
Restricted personnel (auditors and Staff
Engineers) on Nadcap audits. - Unrestricted personnel are US citizens green
card holders are allowed access to Export
Controlled materials. - Restricted personnel are non US citizens or green
card holders are not allowed access to Export
Controlled materials. - Suppliers must know the status of the PRI
personnel keep any Export Controlled material
away from Restricted personnel - Auditor status can be found in eAuditNet next to
auditors name for assigned audit - Best way to determine the rest of PRI Staff
status is to ask them
22 Supplier Responsibilities
- Determine whether you have material which is
protected under ITAR/EAR. - Contact your customers to be certain.
- If you have product, information or any other
material(s) protected under ITAR/EAR, you must
indicate such by answering YES to the ITAR/EAR
question after accepting the supplier agreement
when the audit is scheduled. - This alerts PRI Scheduling as to whether ITAR/EAR
controlled work exists and guides the
assignment of the auditor.
23Supplier Responsibilities (Cont)
- Work with PRI Scheduling - if you have ITAR
controlled material they will attempt to schedule
an unrestricted auditor (one who can look at ITAR
controlled material). - If an unrestricted auditor cannot be scheduled, a
Restricted auditor may be assigned. Scheduling
Staff will contact the supplier to determine if
sufficient non-Export Controlled work will be
available. If it is, a Restricted auditor can be
assigned. - The supplier must ensure that only non ITAR work
is presented to the Restricted auditor for the
audit. - Screen all documents for ITAR controlled
requirement before presenting to auditor NOTE
if ITAR/EAR information is sent to an
Unrestricted auditors as part of the pre-audit
paperwork, it must be recovered by the supplier
after the audit.
24Supplier Responsibilities (Cont)
- General information on Export Control can be
found in eAuditNet (Public Documents) and on the
Supplier page of the Nadcap website
(www.pri-network.org) - Suppliers cannot post or reveal any technical
details on EC parts in response to any findings
in eAuditNet. - At Nadcap meetings ensure that no information is
discussed or presented to anyone which is Export
Controlled. - Contact your prime customer if you have any
question about the status of information as to
Export Control.
25Supplier Merit (NOP-008)
- Accreditation term for initial audits is 12
months. - Suppliers with superior performance will be
eligible for longer terms 18 months or 24
months - Merit is based on performance in two consecutive
audits for most task groups. - Eligibility is contingent on no Product Impact
findings and no adverse Supplier Advisories - Each Task Group has specific criteria. Refer to
the NTGOP Appendices, available on
www.eAuditNet.com under User Documents
26Failure Policy (NOP-011)
- Suppliers can fail an audit for
- Supplier stops the audit
- Excessive number of findings
- Severity of findings
- Too many corrective action response review cycles
to close - Nonresponsiveness
- The above criteria are not automatic failure
points the Task Group votes and makes the final
decision - Only 4 of all audits conducted in 2007 resulted
in failure the majority were due to
Nonresponsiveness - Specific criteria determined by Task Group
refer to - NOP-011,User Documents, www.eauditnet.com
27Orientation AgendaSection III
- Introduction to Nadcap
- Basic Tools and Advice
- How to Prepare for your Audit
- What to Expect During the Audit
- Important Post Audit Information
- Additional Information
28Initial Steps
- Register in eAuditNet.com
- Contact PRI Scheduling
- Complete a preliminary questionnaire and return
to Scheduling - Obtain length of audit and cost
- Obtain access to Nadcap checklists
- Schedule Audit
- Pre-Audit Preparation participate in NCSI!
29Pre-Assessment Audit
- You can schedule a pre-assessment audit using a
Nadcap auditor BEFORE your actual Nadcap audit. - Three types procedural review, complete
documentation review, full scope audit. - All the data from the audit will be left with
you. No need to close out findings with Nadcap. - If there is a finding which clearly may affect or
has affected product, it will be sent to the
Primes. - Contact PRI Scheduling and refer to NIP 7-06 for
more information.
30A Nadcap Audit is . . .
- The most thorough and comprehensive audit you
probably have ever had. - Conducted by experts in the field with technical
special process knowledge and background.
The more you prepare the greater success you
will have.
31Quality System Approval
- Before you can receive a Nadcap special process
accreditation, your quality system must be
approved - Nadcap recognized quality systems approvals
- AS9003 and AS/EN/JISQ 9100 quality system
approvals performed by approved registrars -
listed in the IAQG Oasis database.
(www.iaqg.org/oasis). Product groups require
AS9100. -
- ISO/IEC 17025 for testing laboratories (AC7101),
must cover the Nadcap scope of accreditation and
be from an approved NACLA/ILAC accreditation
body. -
- If you have neither of these, you will need a
Nadcap AQS audit to AC7004 or AC7006 (labs) to
support the special process accreditation. - Refer to NOP-002 in www.eAuditNet.com.
32Quality System Approval (Contd)
- Suppliers scheduling an initial Nadcap audit
shall provide PRI a recognized quality system
certification prior to the time the audit is
entered into eAuditNet or an AC7004 assessment
audit shall be scheduled, unless TG requires more
than AC7004. - For reaccreditation audits, where no existing
recognized quality system approval exists,
Suppliers shall have two options - a minimum of 90 days prior to the audit start
date schedule an assessment to AC7004, unless TG
requires more than AC7004 - provide PRI a valid Quality System accreditation
certificate no later than 60 days following the
end of the Nadcap audit - Suppliers who fail to provide a valid quality
system accreditation certificate to PRI by this
date shall have the process audit automatically
failed without further notice.
33Self Audit
- Perform a thorough and complete self-audit using
the Nadcap checklist. - Record for each question, where in your system
you meet the requirement - Record for each question, where you have
objective evidence of compliance - If you can not list where in your system you have
documentation and what you will show the auditor
the answer is No! - Fix all Nos with complete root cause
corrective action prior to audit.
34Additional tools
- Use the tools on www.eauditnet.com
- Tutorials
- Audit Handbooks
- Checklists
- Contact your customers to verify your audit scope
- Read the preparation instructions for your
commodity. You must send certain documents
(quality manual, procedures, etc.) to your
auditor AT LEAST 30 days prior to your audit. - Familiarize yourself with www.pri-network.org and
the tools available. - Courses such as NCSI, RCCA, etc.
- Nadcap meetings information
- Keep your management informed
- Time spent on preparation will save even more
time after the audit.
Do your Own Job Audits
35Job Audit
- Job Audits a key part of the Nadcap audit is
the job audit. - A job audit is a step by step review of all
processing on actual hardware evaluating how you
meet your customer requirements. - Each special process family has a numbers of job
audits that will be conducted with the special
process checklist.
36Job Audit (Contd)
- Schedule the Nadcap audit when you can perform as
many of the job audits as possible. - Work with PRI scheduling and your internal
(company) scheduling to ensure you will have jobs
for the audit. - Example
- Try to schedule the audit on days of the week
you may have more work (Tuesday through Friday
vs. Monday through Thursday) - If possible, avoid scheduling audits when your
larger customers are shut down. - You should have available a REAL part from a
Nadcap aerospace Prime - NOTE
- Each Task Group has specific requirements. You
MUST review the Audit Checklist for - specific details and speak to the Staff Engineer
if you will not have a part from a - Nadcap aerospace Prime at the time of your audit.
37Supplier Mentoring
- SSC has established a mentoring program for
suppliers - The program matches suppliers who need assistance
with experienced suppliers who can help them
succeed in the Nadcap process - Goal educate supplier base reduce cycle time
- Go to www.pri-network.org SSC page for more
information. - To request a mentor, send an email to
NadcapSSC_at_sae.org
38PRI Staff Engineer
- The PRI Task Group Staff Engineer has commodity
specific knowledge and expertise. - The Staff Engineers review and approve all
specified audits. - Staff Engineers have years of audit review
experience use their expertise before and after
your audit
39Staff Engineer Advice
- Do not rely on your customer to have found
everything in the specification. - It is your responsibility to ensure that you meet
all requirements. - The auditor will check for complete compliance
and ensure compliance flows throughout your
documents.
40More Staff Engineer Advice
- If there is a conflict between the checklist and
your customer requirement, pick the most
stringent. - Multiple customer requirements require a more
robust system. - The specification is the requirement. Procedures
must meet all requirements in the specification. - All process requirements must
- Be Documented
- Be Complied with
- Have objective evidence of compliance.
41Still More Staff Engineer Advice
- Ask questions early regarding interpretations.
- Typical problem areas
- NDT Exams (Level III)
- HT - Pyrometry
- CP Periodic testing
42Orientation AgendaSection IV
- Introduction to Nadcap
- Basic Tools and Advice
- How to Prepare for your Audit
- What to Expect During the Audit
- Important Post Audit Information
- Additional Information
43Scope Verification
- Audit In-briefing Sets the stage for the audit.
Supplier auditor will verify the scope of the
audit. - This requires access to the internet for auditor
to conduct a sign-off process in eAuditNet. - Any changes or corrections to the scope must be
made before the audit starts. - After the audit is conducted, no changes can be
made to the scope of your accreditation.
44Daily Briefings
- At the end of each audit day, the auditor will
conduct a daily briefing. - Meeting is designed to review any findings from
that day and to ensure all findings are
understood. - Make certain that you have proper supplier
personnel attend this meeting. - Raise any issues or problems that arose during
the audit.
45NCR Classifications
- Major Nonconformance
- The absence of, or systemic breakdown of, the
Process Control and/or Quality Management system.
Or - Any non-conformance where the effect impacts or
has the potential to impact the integrity of the
product. - Minor Nonconformance
- Any single system failure or lapse in conformance
with the - applicable standard or audit criteria.
- Refer to PRI Quality Manual available in the User
Documents - section of www.eauditnet.com.
-
46Outbriefing Meeting
- Schedule top management to attend.
- Make certain that you understand all NCRs as
written ask questions if you do not understand
make sure the finding will be clear to the
Staff Engineer and Task Group. - Review the process requirements and expectations
before the auditor leaves.
47Orientation AgendaSection V
- Introduction to Nadcap
- Basic Tools and Advice
- How to Prepare for your Audit
- What to Expect During the Audit
- Important Post Audit Information
- Additional Information
48After the Auditor Leaves
- We value your feedback Nadcap is a cooperative
program - When you submit your NCR responses you will be
prompted to complete an online questionnaire - If you require a response, or have a complaint,
please submit it in writing, separately from the
questionnaire - There is an appeals process for NCRs, Staff
Engineer decisions, and Task Group decisions - Contact the Staff Engineer for more information
49Corrective Action Response Submittals
- Reply to your Non-conformances in the Supplier
Discussion for each NCR. - Immediate Corrective Action Taken (Containment
Actions) - Root Cause of Nonconformance
- Impact of all Identified Causes and the Root
Cause - Action Taken to Prevent Recurrence
- Objective Evidence Attached
- Must be included for ALL findings for Initial
audits AND Reaccreditation audits. - You may submit evidence by uploading attachments
or via U-fax, refer to the eAuditNet Supplier
Guide for help. - IMPORTANT if a procedure is changed, clearly
specify what the change was. Change or create a
procedure, implement a new system or method,
perform training / awareness, propose audits, new
checklists, etc? SHOW IT.
50NCR Responses
- Responses are due 21 calendar days from the close
of the audit - Submit in eAuditNet
- Submit in accordance with Requirements for
Corrective Action Response Requirements
(eAuditNet Supplier Guide and www.pri-network.org)
- For completeness of the audit report, additional
information or clarifications may be requested by
the Staff Engineer. Responses must be submitted
through the Observation Forum on
www.eauditnet.com
51Response Due Dates
- Initial responses are due in 21 days, subsequent
responses are due in 7 days. Any responses sent
outside of these requirements will be considered
late. - No extensions can be granted.
- Suppliers are given 45 days of cumulative
lateness. If you must be late, you can use up to
45 days to respond. - This is not to be considered extra time, this is
late time that suppliers can use for issues that
prevent them from responding according to the
requirements (plant shutdowns, holidays, etc.) - The total number of days past due will be visible
in eAuditNet and reminders will be sent when the
audit is 15 and 30 days past due - At 45 days past due, the audit will be balloted
for failure.
52RCCA help
- Help available
- www.eauditnet.com
- A link to Response Requirements is attached to
the - NCRs
- Also www.pri-network.org
- -Nadcap page
- -Supplier Info Post Audit Assistance
- -Supplier Training additional tools
53(No Transcript)
54(No Transcript)
55Supplier Advisory/Early Review
- If a potential product impact or failure issue is
identified all User members will receive an early
review notice to look at the audit results. - If deemed necessary, a Supplier Advisory will be
issued. - An advisory is a formal way of communicating
concerns regarding documented possible product
impact, changes in key personnel, quality
systems, equipment, etc. to Nadcap Subscribing
Prime Members. - Four levels Preliminary, Potential Product
Impact, Safety Alert, Audit Failure, plus one
informational.
56Supplier Advisory/Early Review (Contd)
- Suppliers are encouraged to provide their own
comments as part of the advisory (within 5
working days). - Before closing the advisory, all other
accreditations will be reviewed to determine if
the identified issue is systemic and affects
other accreditations/ registrations. - If the issue is widespread, revocation of current
accreditation (if one exists) and other
commodity/quality certificates could occur. - Refer to NOP-006 for more information.
57NCR Review
- NCR responses may be sent back
- By the Staff Engineer
- Based on history and experience with Task Group
- History with similar findings/responses
- By the Task Group
- Each Request for additional information
- Delays your Accreditation
- Adds to cycle time
58If Your Response is Not Accepted
- You have 7 days to respond to the Staff Engineer
- If the Staff Engineer details specific requests
- Review and comply with the entire request. Your
response will not be accepted until all items are
addressed. - In the event of a generic rejection, i.e.,
Readdress Root Cause - Review the Requirements for Submittal of
Corrective Action Responses and comply - NOTE use e-mail/phone to work out an acceptable
response do not ask questions in eAuditNet -
each reply counts as an additional cycle
59Common Findings
- Job Audits
- Customer flowdown
- Lack of shop discipline inform your personnel!
- Lack of documentation/Objective evidence
- Data transfers
- Processes requiring approvals not approved (i.e.,
NDT Techniques or other frozen process) - Specification compliance (i.e., frozen process
doesnt meet specification, AMS 2750 compliance,
etc.) - Parts cleaning not in accordance with
requirements - Testing including periodic
60Automatic Scheduling
- When the Task Group has granted your Nadcap
accreditation, eAuditNet will be updated and your
accreditation will be listed on the online
Qualified Manufacturers List (QML). - At this same time, your next Nadcap audit for the
same commodity will be automatically scheduled by
eAuditNet. Some can not be auto-scheduled 85
are! - Please verify the dates and contact the
Scheduling Department within 21 days of any
changes. IMPORTANT, a reminder will NOT be
sent.
61Automatic Scheduling More Details
- When an audit is auto-scheduled, you must still
accept the Supplier Agreement and designate if
there is ITAR work involved. - Log in to eAuditNet, click Accept Agreement. A
list of audits where agreements are not accepted
will appear. - Select the audit for which you wish to accept the
agreement and indicate ITAR status. - This must be done prior to every audit. You will
receive reminders.
62Orientation AgendaSection VI
- Introduction to Nadcap
- Basic Tools and Advice
- How to Prepare for your Audit
- What to Expect During the Audit
- Important Post Audit Information
- Additional Information
63eAuditNet Information
- Keep your email address current to ensure you
receive important emails related to your audit. - If there is a change in your contact information,
inform PRI. - Do not reply to automated emails received from
eAuditNet there are contacts listed in the
email. - For eAuditNet Support, refer to the Public
Documents section for User Guides or contact the
Help Desk at 1 724 772 1616 x8679 or via email
at eauditnetsupport_at_sae.org.
64Supplier Support Committee (SSC)
- SSC Position in Nadcap
- The SSC is an integral part of the Nadcap
process. - Established in NOP 001 just like the Nadcap
Task Groups. - SSC Chair is a voting member on NMC.
- Full support from PRI Staff.
65Supplier Support Committee Mission Statement
- Our goal is to represent the supplier community
and work with the Nadcap Management Council to
enhance the effectiveness and economical value of
the Nadcap system for the mutual benefit of
suppliers and primes.
66SSC Systemic Focus
- Operates independent of the Task Groups.
- SSC Focus is on overall issues common to
suppliers NOT technical or Task Group specific.
67SSC Organization
- SSC LT is comprised of
- SSC Chair
- SSC Vice Chair
- 2 representatives from each Sector
- Secretary
- Standing Committees
- Communications Mentoring
- Metrics
- Survey
- Task Group Reps to SSC
68Supplier Support Committee Leadership Team (SSC
LT)
- David Michaud, Chairperson
- -Fountain Plating Co
- Jim Cummings, Vice Chairperson
- -Metal Finishing Co
- Derek Alty, Europe Sector Rep
- -Bodycote Heat Treatments Ltd
- Bob Custer, Americas Sector Rep
- -AAA Plating Inspection Inc
- Eric Jacklin, Americas Sector Rep
- F. M. Callahan Son
- Yoshiomi Sukesada, Asia Sector Rep
- -Asahi Kinzoku Kogyo Co. Ltd
- Stu Sherman, Secretary
- -Metallurgical Processing Inc
Two Open Positions Asia Sector Rep Europe Sector
Rep
69SSC Activities
- Supplier survey
- Communiqué Flyer participation - newsletter to
Nadcap participants - SSC Metrics
- Mentoring program
70Nadcap Meeting Information
- Available at www.pri-network.org
- Minutes Agendas
- Keep up with Task Group activities
- Participate in Task Group decisions
- Plan to attend Open Meeting Suppliers are
always welcome - Attend the Supplier Support Committee (SSC)
meeting
71Nadcap Meeting Information
72Obtain Agendas and Registration for Upcoming
meetings
73Important Meetings
- Supplier Support Committee Meeting
- Your participation is needed!
- Today 26 February 2008
- 400pm-600pm
- eAuditNet Training for Suppliers
- Today, following this session
74Upcoming Nadcap Meetings
- Meetings in 2008
- Nadcap meetings will now be three times per year.
- 21-25 July 2008 Pittsburgh, PA, US
- 6-10 October 2008 Yokohama, Japan
- Additional details can be found in the Nadcap
Meeting Attendees Guide
75Our Web Addresses
- www.pri-network.org
- www.eauditnet.com
76Questions?