Title: VENTILATION FOR SINKING VERTICAL, SUB-VERTICAL AND DECLINE SHAFTS
1VENTILATION FOR SINKING VERTICAL,SUB-VERTICAL
AND DECLINE SHAFTS
Derek Walters Turgis Consulting
2Virtually every shaft or decline sunk is
unique in some way
3Major differences being
- Location
- Size and Depth
- Capacity
- Infrastructure
- Amount of development required from shaft or
decline
4Regulatory requirements
- No longer prescribed
- (formerly 0.15 m³/s/m² face area).
- Based on risk assessment and occupational
exposure limits.
5Occupational Exposure Limits (OEL)
- OEL Time weighted average 8 hour day 40 hours
a week. - OEL C Instantaneous value which must never
be exceeded. - OEL-STEL Maximum exposure for 15 minute TWA
and not more than 4 times per day.
6OEL AND STEL AFTER BLASTING OEL AND STEL AFTER BLASTING OEL AND STEL AFTER BLASTING OEL AND STEL AFTER BLASTING OEL AND STEL AFTER BLASTING
Substance OEL OEL OEL-C / STEL OEL-C / STEL
ppm mg/m³ ppm mg/m³
Carbon Monoxide (CO) 30 35 100 115
Carbon Dioxide (CO2) 5000 9000 30000 54000
Nitric Oxide 25 30 35 45
Nitrous Oxide 50 90 - -
Nitrogen Monoxide 25 30 35 45
Nitrogen Dioxide 3 5 5 9
Silica dust (respirable) - 0.1 - -
Coal dust (respirable) - 2 - -
Particles not otherwise classified
Inhalable particulates - 10 - -
Respirable particulates - 3 - -
7Operating outside South Africa
- Comply with local regulations.
- Or
- In the absence of local regulations use South
African regulations. - These comply with internationally accepted norms
and are thus defensible.
8The purpose of ventilation is to dilute and
remove pollutants.
- Always assume that flammable gas may occur.
- SA Limit 1.4 flammable gas in atmosphere.
- Define Atmosphere as 150 mm away from the
source in any direction. - Design must be robust enough to cater for
abnormal but reasonably anticipated events.
9Vertical shafts
- Determine requirement for ventilating the
- shaft barrel.
- Determine work that is to be done
- concurrently or in conjunction with sinking.
- Including
- Station and other development
- Raise Boring
- Holing with other excavations
10Determining basic air requirements
- Ordinary sinking
- Air volume providing minimum of 0.5 m/s in shaft
is good practice. - Example
- An 8.0 m shaft would require 50.3 m² x 0.5 25.2
m³/s
11Determining re-entry times
- Shaft diameter 8 m diameter (50.3 m²)
- Required re-entry time 15 minutes
- Number of air changes 8 between face stage
- Distance from the face to the stage when raised
for blasting 50 m - Air quantity (Q) (Air changes x Volume) /
Time - Q ( 8 x 50.3 x 50) / 15 x 60 22.3 m³/s
- In this case the minimum air quantity required is
22.3 m³/s
12Force system
13Exhaust overlap system
14Force exhaust system
15Airflow reversal
16Ventilation of development from the shaft
- Unique design for each shaft.
- Designed as an integral part of the sinking shaft
17Common problems
- Inadequate air for development activities.
- Column leakage due to improper installation and
damage.
18Recommended
- 2 or 3 mm thick Corten columns
- They are
- Robust
- Can easily be refurbished and re-used
19Decline development
- Single decline using conventional force system
with flexible ducting (world norm). - Twin declines.
20Occupational exposure limits - Diesel Equipment Occupational exposure limits - Diesel Equipment Occupational exposure limits - Diesel Equipment
Carbon dioxide CO2 5000 ppm
Carbon monoxide CO 30 ppm
Nitric oxide NO 25 ppm
Nitrogen dioxide NO2 3 ppm
Sulphur dioxide SO2 2 ppm
Diesel particulate matter DPM Not specified Suggested 400 µg/m³
21Determining air requirements
- Currently no legislated minimum air quantity in
SA - Many other countries have regulations in place.
- These minimum air quantities vary considerably
from country to country. - Suggested volume is 0.075m³/s/kW rated power
- A 150 kW LHD would require (150 x 0.075)
- 11.3 m³/s
22Multiple vehicles used in series
Equipment kW m³/s/kW Factor m³/s
20 t Truck 240 0.075 1 18.0
LHD 185 0.075 0.75 10.4
Utility vehicle 80 0.075 0.5 3.0
Drill rig 40 0.075 0.5 1.5
Total air required Total air required Total air required Total air required 32.9
23Sizing of ventilation columns
- Identical 1.0 m Ø columns, 1500 m long, 15
leakage.
Air quantity 15 m³/s 20 m³/s
Fan Pressure 4147 Pa 7295 Pa
Face quantity 12.9 m³/s 17.2 m³/s
Fan input kW _at_ 75 efficiency 82.9 kW 194.5 kW
24Heat loads
- These are site specific and are affected by
- Ambient conditions
- Depth
- Rock geothermal gradient
- Rock thermal characteristics
- Area of rock exposed
- Diesel equipment
- Other mechanical and electrical heat loads
- Ground water inflow rate
25- To determine the need for cooling a heat
- balance must be done.
- There are a number of computer
- programs to calculate this and to predict
- The working conditions in the decline
- being sunk.
26Conclusions
- The ventilation system should be uniquely
- designed to cater for sinking and any
- additional development that may be
- required.
- Avoid the one size fits all approach.