Template - PowerPoint PPT Presentation

About This Presentation
Title:

Template

Description:

Demonstrate viability of Nb3Sn ... TQ (Technology Quads, 2005-07) D = 90 mm, L = 1 m, Gnom 200 T/m ... Disassemble TQC01 coil and test in TQS01 structure ... – PowerPoint PPT presentation

Number of Views:16
Avg rating:3.0/5.0
Slides: 13
Provided by: JimSt61
Category:

less

Transcript and Presenter's Notes

Title: Template


1
BNL - FNAL - LBNL - SLAC
Model Magnet RD (WBS 2.2) LARP Collaboration
Meeting October 5-6, 2005 Gian Luca Sabbi
2
LARP Magnet Program Goals
FY09 Milestone Demonstrate viability of
Nb3Sn technology for Quad-first option
1. Capability to deliver predictable,
reproducible performance TQ (Technology Quads,
2005-07) D 90 mm, L 1 m, Gnom gt 200
T/m 2. Capability to scale-up the magnet
length LQ (Long Quadrupoles, 2008-09) D
90 mm, L 4 m, Gnom gt 200 T/m 3. Capability to
reach high gradient (pole tip field) in large
aperture HQ (High Gradient Quads, 2008-09) D
90 mm, L 1 m, Gnom gt 250 T/m
  • Fabrication of the first two TQ quads (TQS01 and
    TQC01) has started
  • TQS01 test in February/March 2006 TQC01 test in
    April/May 2006

3
Technology Quads (TQ)
  • Objective contribute to developing the
    technology base for LQ HQ
  • evaluate conductor and cable performance
    stability, stress limits
  • develop and select coil fabrication procedures
  • select the mechanical design concept and support
    structure
  • demonstrate predictable and reproducible
    performance
  • Implementation two series, same coil design,
    different structures
  • TQS models shell-based structure
  • TQC models collar-based structure
  • Magnet parameters
  • 1 m length, 90 mm aperture, 11-13 T coil peak
    field
  • Nominal gradient 200 T/m maximum gradient
    215-265 T/m

4
TQS01 Shell-based Structure
  • Concept
  • Aluminum shell over yoke and pads
  • Assembly based on bladders and keys
  • Advantages
  • Can deliver very high pre-stress
  • Large pre-stress increase at cool-down
  • Easy assembly/disassembly/reassembly
  • RD issues
  • Coil alignment, field quality
  • Long vs. segmented shells

TQS01 task leader S. Caspi - Test planned for
February/March 2006
5
TQC01 Collar-based Structure
  • Concept
  • Support by thick SS collars
  • Assembly w/external press
  • Advantages
  • Proven coil positioning
  • Proven length scale-up
  • RD issues
  • Deliver required pre-stress
  • Pre-stress overshoot
  • Flexibility for RD

TQC01 task leader R. Bossert - Test planned for
April/May 2006
6
TQ Coil Winding Status
  • 6 unit lengths of practice cable and 10 UL of
    cable fabricated at LBNL
  • 8 insulated UL available for production coils, 2
    additional UL to follow
  • 4 practice coils wound and cured at FNAL
  • Various improvement were included based on
    practice winding/curing
  • 2 production coils for TQS01 were fabricated at
    FNAL

7
TQ Coil Reaction and Impregnation
  • The first set of practice coils were reacted and
    impregnated at FNAL
  • Good results on the first set of impregnated
    coils
  • The second pair of practice coils is being
    reacted at LBNL
  • Strand cable samples are being reacted with
    the practice coils
  • Reaction of first pair of production coils
    starts in 3 weeks

8
TQ mechanical models
  • Mechanical models using dummy coils
  • TQS01 (2004) TQC01 (underway)
  • Mechanical models using the practice coils will
    be performed in the next 3 months in preparation
    for magnet assembly

9
TQ Schedule (Rev. 10/5/2005)
Q3-05 Q4 2005 Q1 2006 Q2 2006
Q3 2006
10
TQ Program following TQS01-TQC01
  • 1. Additional tests using the same coil design
  • TQS02 reconfigure/optimize based on TQS01
    results
  • Increase preload? (e.g. 4.2 K to 1.9 K) Modify
    structure? (as for HD1)
  • Replace quadrant with spare? (if localized
    quenches observed)
  • TQC02 new coils (w/RRP conductor) in
    collar-based structure
  • Feedback from TQC01 can be incorporated at
    assembly
  • Coils might be redirected to TQS depending on
    test results
  • TQE01 coil-structure exchange
  • Disassemble TQC01 coil and test in TQS01
    structure
  • Some technical issues to be addressed decision
    after TQS01/TQC01 tests
  • 2. Coil iteration and fabrication of TQS03
    TQC03 coils

11
TQ plan after S01-C01 (Rev. 10/5/05)
12
Model Magnet Tasks Budget Summary
Write a Comment
User Comments (0)
About PowerShow.com