Underground - PowerPoint PPT Presentation

About This Presentation
Title:

Underground

Description:

Underground – PowerPoint PPT presentation

Number of Views:407
Avg rating:3.0/5.0
Slides: 36
Provided by: edwardc59
Category:
Tags: dce | underground

less

Transcript and Presenter's Notes

Title: Underground


1
Underground
National Energy Supergrid Workshop November 7,
2002 Palo Alto
Edward J. Cording University of Illinois at
Urbana-Champaign
2
Underground
National Energy Supergrid Workshop November 7,
2002 Palo Alto
Edward J. Cording University of Illinois at
Urbana-Champaign
3
Scale 6 inches to 200 feet
  • Rock Chambers 60 to 100 ft wide
  • Rock tunnel boring machines (TBMs) with disk
    cutters
  • 8 to 40 ft diameter
  • Most economic 10 to 15 ft diameter, gt 5000 ft
    length
  • Soil tunnel shields with pressurized chambers to
    support face
  • Micro Tunneling jacking a pipe, removing muck
    by slurry line
  • less than 3 ft dia is no-entry, larger diameters
    can be entered.
  • Length determined by jacking forces tunnel
    lengths greater than 1000 can be driven using
    intermediate jacking stations inserted in the
    pipe string.
  • Horizontal Directional Drilling
  • typical 300 to 1500 ft long, 6 to 24 in.
    diameter
  • up to 48 and 3000 length, up to 24 and 6000
    length.
  • Open Excavation
  • Large braced excavations and shafts
  • Trenching
  • Trenchers and Excavators
  • Rock chain driven cutters with rock picks, rock
    wheels, blasting.
  • Plowing reeled conduit, field drains

NATIONAL CONTRACTORS
4
Order of magnitude
  • Fiber optic conduit trenching 50-100/ft
  • Conduit pipe jacking,
  • directional drilling 200/ft
  • Larger 2- to 4-ft-dia micro tunnel 500/ft
  • Optimum-sized TBM tunnel 1500/ft
  • Larger TBM tunnels 3000/ft

5
Large Excavations for Support Facilities, Nuclear
Reactors
SHAFTS CHAMBERS
  • Take advantage of underground
  • Build arches, not beams
  • Shielding provided by rock
  • Avoid difficult ground, soil/rock contacts
  • in the rock chambers
  • Groundwater control essential
  • Pro-active planning/design team
  • Investigation and assessment of environmental
    impacts
  • Establishment of better management and
    contracting practices
  • Community relations
  • Licensing
  • QA/QC programs
  • Dont try to force-fit above-ground criteria to
    underground construction
  • Learn lessons from previous DOE underground
    projects.

SOIL
ROCK
6
Experience with Large Excavations
  • Subway stations, NORAD,
  • underground powerhouses in rock

    60 to 100 ft wide
  • Deep access shafts extending into rock
  • through 200 - 300 of water-bearing sands
  • using concrete diaphragm walls, freezing,
  • 200-ft-diameter circular shafts constructed in
    clay
  • DOE Underground Projects large interaction halls
  • NUMI at Fermi-lab in limestone
  • 200 ft deep open excavations designed for Texas
    SSC in shale.
  • DOE Underground projects tunnels
  • Exploratory TBM tunnel (25) for site
    suitability, Yucca Mountain
  • TBM tunnels for SSC ring, Texas
  • Shotcreted tunnels for SLAC, Palo Alto

SHAFTS CHAMBERS
SOIL
ROCK
7
Mainline of Supergrid tunnel scale?
  • Rock tunnel boring machines (TBMs) with disk
    cutters
  • Most economic
  • 10- to 15-ft-dia (depending on tunnel length
  • gt 5000 ft drives
  • Soil tunnel shields, pressurized face
  • Bentonite slurry or conditioned muck (Earth
    Pressure Balance, EPB) to support face
  • Install one pass (final) segmented lining in
    shield as shield advances
  • Soil TBMs can be fitted with disk cutters to cut
    rock and boulders, but driving tunnels on
    contacts between rock and soil should be avoided.

8
Requirements for construction shafts, access,
junctions, chambers, booster stations
Shafts
SOIL ROCK
SOIL ROCK
  • Spacing along tunnel line
  • Depth
  • Size

10 to 15 ft

9
Multiple use corridors large tunnels
  • Rail
  • Freight, double stack
  • Passenger, twin tunnels 20-ft-dia
    limited additional space
  • Passenger, single tunnels 35-ft-dia
  • Fire Life Safety concerns
  • High speed corridors likely to require high
    population density
  • Portion of tunnel cost supported by supergrid ?

?
10
Drill and Blast
11
Chattahoochie Tunnel, AtlantaTwo 20-ft-dia.
tunnel boring machines 47,000 ft
CUTTERHEAD
OPEN SHIELD
12
Cutter head Back-loading (recessed) disk
cutterscutting tracks approx. 4 in. apart
13
GRIPPERS AGAINST ROCK.
THRUST CYLINDERS SHOVE CUTTERHEAD FORWARD
(Photo shows machine being assembled in drill and
blast section)
14
MINIMUM ROCK SUPPORT ROCK BOLTS
VENTILATION LINE
CONVEYOR BELT FOR MUCK
15
DISK CUTTERS Penetration rate - - in
proportion to Thrust/cutter rpm
Thrust 1960 soft rock 1980 30,000 lb/
cutter 2000 70,000 lb /cutter the result of
improved tool hardness, bearing design
metallurgy.
Advance Rate Pen. rate x
Utilization ( of workday machine is
penetrating)
16
  • Pressurized face tunnel boring machines
  • now the standard tunneling method for soils
    that would otherwise flow or run into the tunnel
    face. Allows tunneling through water-bearing
    soils without dewatering.
  • SLURRY SHIELD (Common for micro-tunnels)
  • Chamber at front of shield is filled with a
    bentonite slurry mixed with excavated muck to
    provide a pressure against the face. Slurried
    muck is removed from chamber and pumped out of
    the tunnel through a return slurry pipe.
  • EARTH PRESSURE BALANCED (EPB) SHIELD
    (Common for large tunnels in soil)
  • Chamber at front of shield is filled with
    excavated muck mixed with additives to provide a
    pressure against the face. Muck is removed from
    chamber with a screw conveyor.

17
  • Earth Pressure Balanced Shield

Muck pressurized muck in chamber supports face
Screws remove muck and provide back pressure
2
1
Segmental Lining is installed in tail end of the
shield. Shield is advanced by pushing against
the installed lining
18
Soap foam, polymer is injected to reduce friction
and fluidize muck so that face pressure can be
developed
19
Disk cutters to cut boulders, rock
Grizzlies to limit size of boulders passing
through the head
20
Small Scale Conduit
  • Micro Tunneling pipe jacking
  • Diameters from 2 ft to 10 ft.
  • Less than 3-ft-diameter no entry
  • Horizontal Directional Drilling
  • 6 to 48 in. diameter
  • Short runs (200 1000 6000)
  • Open Excavation
  • Plowing cable reels
  • Trenching
  • Trenchers, Excavators
  • Rock chain driven cutters with rock picks, rock
    wheels, blasting. Preferred excavation method is
    not just what can be done but what is efficient.

10
21
  • MICRO TUNNEL SLURRY SHIELD
  • Rotating cutterhead, bentonite slurry supports
    face
  • Slurry is circulated out of tunnel to remove
    excavated muck
  • After muck is separated, slurry is recirculated
    to tunnel face

22
Total Jacking Force
PIPE SECTIONS ARE ADDED IN JACKING SHAFT. Micro
TBM IS PROPELLED BY JACKING THE STRING OF PIPE
FORWARD
23
JACKING PIT START OF MICRO TUNNEL
24
  • JACKING FRAME IN STARTING PIT
  • Place 10 to 12-ft-long pipe, with slurry lines
    attached
  • 30 minutes to install pipe section
  • Jack pipe string to advance the shield

25
LOWERING PIPE SECTION INTO PIT
FOR JACKING
26
HORIZONTAL DIRECTIONAL DRILLING (HDD)
27
  • HDD CAPABILITIES TO DATE
  • Maximum distance 6000 ft at 24 in. dia.
  • Maximum diameter 48 in. over distance of 3000 ft
  • Excavation and Steering
  • EM signal transmitted to surface or through
    single hard wire line in casing inclination
    and magnetic azimuth
  • Circulating fluid pumped to mud motor or jets to
    excavate ground. Steering controlled by small
    rotations of pipe to adjust attack angle of the
    motors or cutting tool.

28
Management and Contracting Practices
  • 1970s Excessive litigation on tunnel projects
    desire to avoid adversarial relations that
    affected project cost, schedule, quality.
  • As a result, tunneling industry became the leader
    in the development of better contracting
    practices and dispute resolution processes.
  • Three- person, independent Disputes Review
    Boards non binding arbitration real time
    resolution of issues on the job
  • Geotechnical baseline reports data from borings
    alone do not adequately describe site conditions
    owner defines anticipated ground conditions to
    aid bidding and reduce disputes.
  • Recognize that Differing Site Conditions clause,
    which is standard to Federal contracts, means
    that the ground is the owners, and risks
    associated with the ground conditions must be
    assumed by the owner.
  • Design and manage the project first, to avoid
    risk, then to equitably assign risk, and clearly
    define responsibility for risks.
  • Use of owner-provided contingency funds for low
    probability, high risk events that are difficult
    for contractor to estimate and bid.
  • Provide unit prices for items that contractor
    does not control.
  • Some tunneling projects are considering use of
    design-build, and other contracting forms that
    combine technical and cost proposals

29
  • 1970s
  • DOT-sponsored RD and demonstrations.
  • Washington Metro start-up 100-mile subway
    construction
  • SSC Project
  • 16-ft-diameter tunnels 50 miles under
    construction.
  • 200-ft-deep interaction halls.
  • Design and construction coped with swelling shale
    formation not anticipated in Texas proposal.
  • PBMK Team Underground construction on schedule
    and under budget.
  • Yucca Mountain exploratory tunnel for site
    suitability
  • 25-ft diameter tunnel worlds largest
    exploratory tunnel.
  • QA/QC for nuclear facilities often
    inappropriately applied to tunnel construction.
  • cost plus construction, large bureaucracy
  • coordination between science (site suitability
    investigations) and tunneling
  • Tunneling revealed conditions unknown from other
    exploration, provided platform for experimental
    work.
  • Fermi Lab NUMI.
  • SLAC, Fermilab Next Linear Collider

30
The industry does not have organizations that
invest significantly in long term R D
  • Engineering firms small (No Mitsubishis)
  • Contractors focus on each contract, high risk
    limits innovation.
  • Trenching and trenchless (micro-tunnel,
    directional drilling) contractors innovations
    have been made, but most are small operators.
  • Equipment manufacturers utilize available
    technology
  • Exploration, instrumentation borrow tools from
    oil industry
  • Owners Washington Metro supported field research
    in early phases of project, most owners do not.
  • U.S. DOT supported demonstration projects and
    applied research in tunneling in the early 1970s
  • 2002 Amsterdam Metro an owner committed to major
    applied research and development program in order
    to control settlement of soft clays and silts
    below water table and limit damage to historic
    structures by
  • designing tunneling machine shield, working with
    machine manufacturers to minimize ground loss
    during tunneling.
  • conducting full scale tests of grouting
    procedures to compensate for ground movements
  • developing methods for analyzing and estimating
    settlements and controlling the tunneling process
  • investigating contracting practices to manage
    risks, and distribute them between owner and
    contractor

31
  • Curvature
  • Diameter
  • Moisture/water control
  • Access, Maintenance
  • Shafts, booster/mechanical stations, junctions

32
Supergrid Opportunities
  • Long-term project
  • Large capital costs for installation
  • Special requirements for installing the grid
    tunnel size, lengths of runs, ranges of ground
    conditions to be encountered.
  • Trend with time less space and more difficult
    access for installing utlities. Less public
    tolerance for disturbance
  • Increasing use of tunneling and trenchless
    technologies rather than trenching and open
    excavation.
  • Focus for improving tunneling technology for
    supergrid
  • Contracting practices mitigation and assignment
    of risk
  • Joint efforts with research groups, engineering
    firms, contractors, and machine manufactures to
    develop and demonstrate excavation and tunneling
    systems that will fit the requirements of the
    project
  • Link directional drilling, micro-tunneling and
    larger tunnel boring machine technologies.
  • Support demonstration projects using advanced
    technologies for driving tunnels.

33
Hole through
34
(No Transcript)
35
(No Transcript)
36
ROCK GROUP
  • Better Contracting Practices
Write a Comment
User Comments (0)
About PowerShow.com