Title: October Shutdown - ICD
1A.White 9/10/01
October Shutdown - ICD
Tasks during shutdown (A) when ECs are
open gt Install remaining 30 electronics
drawers (North End) plus cabling
(HV,LV,pulser) gt ?? Change signal cable
lengths?? (Depends on timing studies) gt
Replace/repair bad drawers gt Install last 1/2
tile module (SE) gt Replace any bad tile
modules gt Check/repair/replace fiber cables gt
Verify operation of ALL channels using elec. and
LED pulsers gt Iterate the above until all
channels are working gt Verify/repair LMB
photodiode connections
.more
2(B) Other tasks (before end of shutdown) gt
Continue ICD timing studies ( Decide on final
signal cable lengths!) gt Install new HV fanouts
(MCH1) gt Create new monitoring tools gt Develop
pulser(s) run procedures PLUS gt Ongoing
calibration studies