Review - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Review

Description:

9:00 am - 9:15 am Thermal panel design (Martin Nordby) ... Disassemble dust tent from around LAT and remove from chamber. Systems Integration 17 ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 22
Provided by: Martin437
Category:

less

Transcript and Presenter's Notes

Title: Review


1
LAT Environmental Test Planning Meeting 14-16
March 2005 Thermal-Vacuum Testing
Martin Nordby Jack Goodman
2
Agenda
  • 830 am - 900 am      Thermal panel design (Jack
    Goodman)
  • Thermal design concepts
  • 900 am - 915 am      Thermal panel design
    (Martin Nordby)
  • Heating/cooling electrical and gas schematics
  • Power and feedthrough tally
  • 915 am - 945 am      EGSE cabling (Rich
    Bielawski)
  • Cabling schematic, feedthrough pin-outs
  • Thermal sensor cabling
  • Routing and wrapping
  • 945 am - 1015 am    MGSE (Martin Nordby)
  • Chamber configuration
  • Support stand design concept
  • Cable routing and support
  • 1015 am - 1030 am    Thermal data acquisition
    (Jack Goodman, Mike Van Herpe)
  • Data flow
  • Communication between chamber DAQ and LAT EGSE
  • 1030 am - 1115 am    Thermal-Vacuum test
    sequence walk-through (Martin Nordby)
  • 1115 am - 1200 pm    Action Item List Status
    (Martin Nordby)

3
Thermal Panel Design
4
Thermal Panel Cooling Schematic
  • Cooling circuits use boil-off LN2 system
  • Radiator Y/-Y circuits need to be sized for
    transient testing
  • Fast cool-down to simulate eclipse

Cooling Zones
5
Thermal Panel Electrical Heating Schematic
  • Each zone shown is computer controlled
  • Radiator Y and Y zones are independently
    controlled, and need 4-5 kW total power per
    Radiator to provide transient test heat-up
    capability

Heater Zones
6
Heater Power Requirements and Feedthroughs
7
EGSE Cabling and Feedthroughs
8
Thermal-Vacuum Test Test Configuration
Port plate for LAT elec, gas feedthroughs
LAT rolls into chamber on floor
LAT on Test StandOriented Horizontally
9
Thermal-Vacuum Test Test Configuration
Chamber Plan View (PDF file)
SIIS, thermal sensor cable routing
Front View with Chamber Cut Away
View from Inside Chamber
10
Thermal-Vacuum Test MGSE Concept
Upper extension beams are used for lifting LAT
into place, then removed
Radiators mounted to Test Stand in vertical
orientation
Extension beams double as support legs
LAT on Test Stand(Horizontal Configuration)
11
Thermal-Vacuum Test MGSE Concept (cont.)
ACD Sink Plates on an independent support frame
Possible hydraulic assist for rotating detaches
for T-Vac
LAT on Test Stand(Horizontal Configuration)
12
Thermal-Vacuum Test Mechanical Issues
  • Known issues to be worked
  • Trapped air volumes contamination issue
  • Thermal stability of support how level will it
    keep the LAT and what is requirement
  • Sink panel design and support 5 ACD, 3 SC, 2
    Rad
  • Requirements list
  • Leveling what is accuracy and precision needed
    for heat pipes any stability reqs?
  • Test Stand allowed temps temperature range that
    Test Stand may see
  • Allowed parasitic conduction and radiation
    to/from Test Stand and other MGSE

13
Thermal-Vacuum Test MGSE Action Item Status
  • T102, T114 clearances in and around T-Vac
    chamber and chamber dimensions
  • Chamber model delivered to SLAC and incorporated
  • Clearance evaluations are in the works
  • T110, T130, T137, T138 define leveling
    requirements for heat pipes, any muon surveys
    inclinometers needed?
  • No progress
  • T118 MGSE temperature requirements
  • Agreed to keep Test Stand in a -1020 degC
    range
  • Still working details of heating/cooling/isolation
    needed
  • T126 agree to structural supports of LAT in
    T-Vac
  • Test Stand provides flight-like structural and
    thermal interface for LAT
  • Eliminated all options using GPR
  • T127 develop T-Vac STE list
  • Started list of MGSE, but not complete

14
Thermal Data Acquisition
15
Thermal-Vacuum Test Sequence Walk-Through
  • Transport to Thermal-Vacuum Chamber
  • Open door of T-Vac chamber and set up temporary
    trolley supports and rails. Roll out trolley
    from inside T-Vac chamber
  • Move LAT on Test Stand in horizontal
    configuration on Cart to T-Vac chamber.
  • Lift LAT on Test Stand and set down on trolley.
    Secure on trolley and break rigging.
  • Move GN2 source and re-route hoses up onto
    trolley.
  • Test Preparation
  • Install EGSE crates and run outside cabling from
    EGSE crates and chamber DAQ to chamber port
    plates. Make connections to outer feedthroughs.
  • Connect internal EGSE cabling from inner
    feedthroughs on port plates.
  • Check end-to-end continuity of all cabling and
    connections through to LAT EGSE crates and
    chamber DAQ.
  • Mount remainder of specialized test equipment
    (STE), including thermal panels.
  • Roll trolley into mouth of T-Vac chamber.
  • Plumb chiller lines from LAT manifolds through
    port plate feedthroughs to external chiller.
    Test. Leave off.

16
Thermal-Vacuum Test Sequence Walk-Through (cont.
1)
  • Test Preparation
  • Connect internal EGSE cabling to LAT.
  • Run LAT Aliveness test.
  • Mount thermal instrumentation to LAT, MGSE, and
    inside of chamber. Connect instrumentation
    cabling to inner chamber port plate feedthroughs
    and check.
  • Mount ACD-XLAT and ACD-Radiator MLI blankets.
  • Wrap MGSE MLI blankets around Test Stand,
    instrumentation cabling, and to patch up blanket
    open regions around Radiator-Grid volume.
  • Run LAT LPT test.
  • Dress internal plumbing and electrical lines in
    preparation for rolling into chamber.
  • Roll LAT on Test Stand into T-Vac chamber.
  • Level Test Stand to ensure that heat pipes are
    within required level.
  • Re-check all plumbing and electrical lines in
    preparation for pump-down.
  • Connect thermal panels to cooling source and
    connect heaters to port plate feedthroughs.
  • Connect chamber test instrumentation to port
    plate connectors on inside of chamber.
  • Check chamber instrumentation and
    heating/cooling.
  • Pre-T-Vac Performance Testing
  • Run LAT CPT test.
  • Run LAT SVAC and Muon Survey tests.
  • Turn off GN2 purge and remove purge lines from
    LAT and Test Stand.
  • Disassemble dust tent from around LAT and remove
    from chamber.

17
Thermal-Vacuum Test Sequence Walk-Through (cont.
2)
  • T-Vac Test
  • Close T-Vac chamber door.
  • Pump down chamber
  • Bake out LAT and ground support equipment (GSE)
    inside chamber.
  • Hot survival Turn-On, Aliveness tests.
  • Thermal-balance hot TCS Perf, LPT tests.
  • Cold-survival Heater Check test, LAT Turn-On,
    LAT Aliveness tests.
  • Thermal-balance cold TCS Perf, LPT tests.
  • Thermal cycle hot (1) CPT test.
  • Thermal cycle cold (1) CPT test.
  • Thermal cycle hot (2) LPT test.
  • Hot plateau Muon survey.
  • Thermal cycle cold (2) LPT test.
  • Cold plateau Muon survey.
  • Thermal cycle hot (3) LPT test.
  • Thermal cycle cold (3) LPT test.
  • Thermal cycle hot (4) CPT test.
  • Thermal cycle cold (4) CPT test.
  • Return to ambient temperature

18
Thermal-Vacuum Test Sequence Walk-Through (cont.
3)
  • Transport from T-Vac Test
  • Re-assemble dust tent around LAT.
  • Re-connect purge lines to LAT and Test Stand.
    Turn on GN2 purge.
  • Drain and disconnect chamber thermal panels from
    chiller lines. Remove panels.
  • Remove ACD-XLAT and ACD-Radiator MLI blankets.
  • Disconnect test instrumentation.
  • Disconnect LAT EGSE cabling from port plate
    feedthroughs.
  • Disconnect fly-away and other thermal
    instrumentation from LAT, Test Stand, and
    Chamber. Remove.
  • Drain and disconnect auxiliary cooling lines from
    Chill Bars and X-LAT Plate.
  • Roll LAT on T-Vac Test Stand out of chamber.
  • Lift LAT on Test Stand off trolley. Set down on
    Cart and secure.
  • Move GN2 source and re-route hoses down onto
    Cart.
  • Move LAT on Test Stand back to High Bay.

19
Action Item List Status
20
(No Transcript)
21
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com