Title: Slide 1 of 11


1
PDS FM STATUS REPORT
Carlo Gavazzi Space M.Olivier, S.Alia,
A.Assenza, P.Ruzza, A.Albertin, A.DellAcqua,
G.Magistrati, A.Bursi
  • PROCUREMENT STATUS COMPLETE
  • MANUFACTURING AND INSPECTION PRE OPEN BOX
    COMPLETE
  • TEST EQUIPMENT FOR ACCEPTANCE TEST CAMPAIGN
    COMPLETE
  • OPEN BOX TEST AND INTEGRATION STATUS
  • PDS EM MAGNETIC TEST RESULTS
  • ACCEPTANCE TEST CAMPAIGN PLANNING
  • PDS SCHEDULE

2
PDS FM OPEN BOX TEST STATUS
  • PDS FM OPEN BOX TESTING WITH COMPLETE SECTION A
    AND B.
  • OPEN BOX TEST STEPS COMPLETED SINCE LAST TIM
  • OPEN BOX COMMUNICATION AND POWER TESTING OF BOTH
    SECTIONS COMPLETE
  • CANBUS CROSS COMMUNICATION CHECK IS COMPLETE
  • ALL BOARDS TELEMENTRIES TRIMMING IS COMPLETE
  • SHORT CIRCUIT PROTECTION VERIFICATION ( NOMINAL
    LOAD CONFIGURATION) COMPLETE
  • OPEN BOX TESTS IN PROGRESS
  • CAN BUS SW INVESTIGATION IN PROGRESS (WORKING
    MEETING HELD ON 20-21/01/09 IN CGS WITH THE KIND
    SUPPORT OF MR. LEBEDEV AND MR. KOUTSENKO)
  • OPEN BOX TEST MAJOR NCRs OPEN (2)
  • See next slide for details

3
PDS FM OPEN BOX TEST STATUS
  • NCR-CGS-PDS-C-128 CPU RST BUTTON
  • NC ITEM Can Bus I/F Board Assy
  • NON CONFORMANCE Detected During Open box test
  • Suspected cause of NC SW
  • CLASS Major (AFE related)
  • STATUS Open
  • Using CPU RST command unwanted switch off of
    second CAN BUS happens.
  • AMS and CGS verified that this issue is present
    on all AMS USCM boards.
  • New SW version has been provided by AMS
    collaboration to CGS and tested on PDS CAN BUS.
  • Results showing resolution of the issue have been
    discussed with AMS collaboration during CGS
    working meeting of 20-21/01/09 with the kind
    support of Mr. Lebedev and Mr. Koutsenko.
  • Issue is considered tecnically solved. CGS to
    call NRB with ASI and AMS for NCR closure.

4
PDS FM OPEN BOX TEST STATUS
  • NCR-CGS-PDS-C-129 CAN-BUS UNESPECTED SWITCH OFF
  • NC ITEM Can Bus I/F Board Assy
  • NON CONFORMANCE Detected During Open box test
  • Suspected cause of NC SW, design
  • CLASS Major (AFE related)
  • STATUS Open
  • CAN BUS board reset is caused by external noise
    (ie monitors or power supplies switch on)
  • AMS and CGS verified that this issue is present
    on all AMS USCM boards.
  • New SW version has been provided by AMS
    collaboration to CGS and tested on PDS CAN BUS
    together with AMS collaboration during CGS
    working meeting of 20-21/01/09.
  • NCR is open and further unit testing activities
    need to be adressed at NRB with AMS and ASI.

5
PDS FM OPEN BOX TEST STATUS
  • OPEN ISSUES RAISED DURING CGS WORKING MEETING OF
    20-21/01/09.
  • The following items are considered not critical
    for PDS performance but are under joint CGS-AMS
    investigation being common to all AMS USCM design
    and having possible relation with previously
    mentioned NCR issues.
  • Activation Of The Signal S_Off During Power Down
    Of The Board
  • This issue is common to all USCM boards. Not
    critical for PDS but need to be adressed at
    system level.
  • Activation Of The Crow_Bar Circuit During Power
    On Phase
  • This issue is common to all USCM EM boards and
    PDS CAN BUS FM , that is based on the PDS EM
    design. Item is currently under discussion.
  • NOP CPU command inserted in SW
  • This issue is related to NCR-CGS-PDS-C-120 that
    is considered closed. AMS request further
    investigation on this topic. Item is currently
    under discussion.

6
PDS FM INTEGRATION STATUS
  • PDS FM IS UNDEGOING CAN BUS INVETIGATION TESTING.
    UNIT IS 90 INTEGRATED, FINAL BOARDS CLOSURE AND
    UNIT FINAL INTEGRATION AND CLOSURE SHALL BE
    COMPLETED ONCE CAN BUS INVESTIGATION SHALL BE
    COMPLETE AND CAN-BUS SW SHALL BE FINALLY LOADED
    ON EPROMS.

7
PDS EM MAGNETIC FIELD TEST _at_ CERN
  • MAGNETIC FIELD TEST ON PDS EM (NOV 2008)
  • PDS UNIT HAS BEEN TESTED _at_ CERN ON GOLIATH TEST
    MAGNET TO ASSESS UNIT CAPABILITY TO WITHSTAND THE
    FORESEEN FLIGHT FIELD
  • TEST FIELD IS A STRAIGHT ONE, WHILE THE FLIGHT
    FIELD IS A COMPLEX SHAPED ONE (PICTURE OF UNIT
    DURING Y AXIS TEST SHOWED)

8
PDS EM MAGNETIC FIELD TEST _at_ CERN
  • MAGNETIC FIELD TEST RESULTS EVALUATION
  • SINGLE AXIS TEST LEVELS CONSERVATIVE TARGET HAVE
    BEEN DEFINED AS THE MAXIMUM COMPONENT MAGNITUDE
    (164 GAUSS) TO GUARANTE MARGINS AND AVOID COMPLEX
    EVALUATION COMPONENT BY COMPONENT.
  • OBTAINED STABILITY LIMITS ARE ALWAYS HIGHER THAN
    THE SINGLE WORST CASE COMPONENT FOR ALL THE
    ELECTRONIC PARTS BUT ONLY FOR X DIR, THEY ARE
    ALSO HIGHER THAN THE WORST MAGNITUDE.
  • NEXT TABLE SHOW STABILITY LIMITS VERIFIED BY TEST
    WITH RESPECT TO THE FLIGHT WORST CASE (VALUES ARE
    GAUSS)

9
PDS EM MAGNETIC FIELD TEST _at_ CERN
  • PDS MAGNETIC ANALYSIS IN PROGRESS
  • ANALYTICAL SIMULATIONS ARE IN PROGRESS TO CONFIRM
    PDS COMPLIANCE TO THE FLIGHT FIELD, BASED ON THE
    CORRELATION WITH GOLIATH MAGNET TEST OF PDS EM

SINGLE PDS SECTION MODELLED BY FEM
10
PDS FM ACCEPTANCE TEST CAMPAIGN AND PLAN
  • THE ACCEPTANCE TEST PLAN IS CONFIRMED FROM LAST
    TIM
  • TEST READINESS REVIEW (AT BOX CLOSURE) _at_ CGS
  • FULL FUNCTIONAL TEST (FFT) _at_ CGS
  • REDUCED FUNCTIONAL TEST AFTER PDS SHIPMENT TO
    SERMS _at_SERMS
  • RANDOM VIBRATION TEST (3 AXES) _at_SERMS
  • REDUCED FUNCTIONAL TEST AFTER RVT _at_SERMS
  • TVT TEST (WITH REDUCED FUNCTIONAL TEST DURING
    CYCLING) _at_SERMS
  • REDUCED FUNCTIONAL TEST AFTER TVT _at_SERMS
  • EMC TEST _at_SERMS (TBC)
  • FULL FUNCTIONAL TEST (FFT) _at_SERMS (TBC)
  • TEST REVIEW BOARD _at_ SERMS (TBC)

11
PDS FM SCHEDULE
  • SCHEDULE BASED ON THE FOLLOWING ASSUMPTIONS
  • AMS authorize within 06/02/09 usage of the
    current SW version to prosecute PDS CAN BUS
    verification activities and to complete open box
    testing and boards closure.
  • Discussion on open issues raised during CGS
    working meeting of 20-21/01/09 do not result in
    HW or SW modification.
  • NEXT MILESTONES
  • PDS TRR 27/03/2009
  • PDS PFM Test Review Board (TRB) on 12/06/2009
  • PDS PFM _at_ CERN on 16/06/2009

12
CONCLUSIONS AND COMMENTS
  • ACTIVITIES IN PROGRESS
  • PDS FM magnetic analysis in progress after PDS EM
    test
  • PDS FM can bus investigation in progress
  • NEXT STEPS
  • PDS FM final verications and integration before
    box closure 27/03/2009 (TRR)
  • PDS PFM acceptance campaign _at_ SERMS from
    16/04/2008 to 12/06/2009
  • PDS FM Test Review Board (TRB) and shipment to
    CERN on 12/06/2009
  • CRITICALITIES
  • CAN BUS SW investigation is currently requiring
    extensive testing for monitoring of can bus
    signals using different sw versions.
  • THANKYOU FOR YOUR KIND ATTENTION