Title: Value Stream Mapping: August 2005 Current State


1
Value Stream Mapping August 2005 Current State
  • Nancy Terranova
  • October 26, 2006

2
Regulation 1102 Current State(As of August 2005)
  • Construction permit applications
  • Processing time 74.4 hours
  • Lead Time 104.5 days
  • Construction to Operation permits
  • Processing time 15 hours
  • Lead Time 14 days

3
Regulation 1102 Current State(As of August 2005)
  • Less than 1 of incoming applications issued on
    first pass
  • 18 of applications after being determined
    technically complete issued if first pass set at
    technically complete

4
Construction Permit Process
  • Applications sent to Dover and/or New Castle
    Offices
  • Applications sent to New Castle sometimes didnt
    get to Dover in a timely manner
  • About 55 of the applications were
    administratively complete and accurate (The
    forms contained information in the blocks, were
    signed and fees were included)

5
Construction Permit Process
6
Construction Permit Process
  • Applications from new facilities sent to Program
    Manager II for assignment to Eng/Sci
  • Applications sent to Eng/Sci
  • Eng/Sci conducts Technical Review
  • About 10 of the applications were technically
    complete and accurate. (Information in the
    blocks was missing, incomplete, or inaccurate)

7
Construction Permit Process
8
Construction Permit Process
  • Additional information is requested, received,
    and reviewed by Eng/Sci
  • About 85 to 90 of the applications were then
    technically complete
  • This means that 9 to 14 of the applications
    still could not be processed without additional
    technical information
  • Public Notice (ad) prepared by Eng/Sci

9
Construction Permit Process
10
Construction Permit Process
  • Program Manager I reviews the ad
  • 95 of the ads were complete and accurate
  • Public Notice (ad) is placed for 15 day comment
    period
  • Requests for public hearing are not addressed in
    this process
  • Technical Memorandum and Permit prepared by
    Eng/Sci

11
Construction Permit Process
12
Construction Permit Process
13
Construction Permit Process
  • Program Manager I reviews the technical memo and
    permit
  • 20 to 25 of the documents were complete and
    accurate
  • Program Manager II reviews the technical memo and
    permit. If ready, the permit is also signed.
  • 90 to 95 of the documents were complete and
    accurate

14
Construction Permit Process
15
Construction Permit Process
  • Construction permit issued
  • Copied and sorted
  • Mailed to Company
  • Logged in mail log
  • Distributed
  • Logged into DEN

16
Construction Permit Process
17
Operation Permit Process
  • Company contacts Eng/Sci to request a
    Construction to Operation Inspection
  • About 98 of the inspections showed compliance
    with the construction permit. So an operation
    permit could be prepared
  • Note, Regulation 1102, Section 11.4.2, dated June
    6, 2006 states
  • Upon satisfactory demonstration that the
    equipment, facility or air contaminant control
    device complies with all of the terms and
    conditions of the construction permit, the
    Department shall grant approval to operate by
    issuing an operation permit.

18
Operation Permit Process
19
Operation Permit Process
  • Technical Memorandum and Operation Permit
    prepared by Eng/Sci
  • Program Manager I reviews the technical memo and
    Operation Permit
  • 80 of the documents were complete and accurate

20
Operation Permit Process
21
Operation Permit Process
  • Program Manager II reviews the Technical
    Memorandum and Operation Permit. If ready, the
    permit is also signed
  • 95 of the documents were complete and accurate

22
Operation Permit Process
23
Operation Permit Process
  • Operation permit issued
  • Copied and sorted
  • Mailed to Company
  • Logged in mail log
  • Distributed
  • Logged into DEN

24
Operation Permit Process