Presented By: Mike James, Technology and Innovation Manager - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Presented By: Mike James, Technology and Innovation Manager

Description:

Nuclear Decommissioning & Major Projects Group 'Acceleration with ... early 1940s to home Royal Ordnance factories producing explosives for World War II. ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 17
Provided by: BNFL7
Category:

less

Transcript and Presenter's Notes

Title: Presented By: Mike James, Technology and Innovation Manager


1
Sellafield The Challenge Ahead
  • Presented By Mike James, Technology and
    Innovation Manager

Nuclear Decommissioning Major Projects Group
Acceleration with Assurance
2
Sellafield History
  • A key part of the UK nuclear industry for more
    than five decades
  • Sellafield represents the most challenging
    nuclear site management programme in the world
  • Originally, established during the early 1940s to
    home Royal Ordnance factories producing
    explosives for World War II. However, the British
    Government sought to develop its own independent
    nuclear capability recognising atomic energy
    could be harnessed for commercial uses
  • During the early 1950s Britain's scientists and
    engineers combined to develop the world's first
    civil nuclear reactor programme

3
Sellafield History
  • In 1953 Prime Minister Winston Churchill ordered
    the building of four reactors and Her Majesty
    Queen Elizabeth II officially opened Calder
    Hall, the first commercial Nuclear Power
    Station in the world in October 1956
  • Today, Sellafield Ltd manage and operate the site
    on behalf of the owners, The Nuclear
    Decommissioning Authority
  • The site is home to the Thorp and Magnox
    reprocessing plants, the Sellafield Mixed Oxide
    Fuel manufacturing plant and a wide range of
    waste management and effluent treatment
    facilities
  • Activities now include remediation,
    decommissioning, accelerated hazard reduction and
    clean-up of the historic legacy

4
Decommissioning Evolution
  • Nuclear Decommissioning and Major Projects Group
    formed November 2006 to manage all of the current
    and future decommissioning work and major build
    projects on the Sellafield Site
  • The Sellafield Nuclear Decommissioning and Major
    Projects programme is the largest and most
    diverse in the world today
  • Total value of 46billion

5
Sellafield Decommissioning Challenges
  • Extremely diverse portfolio of
  • facilities to decommission
  • including
  • Magnox and Pile Fuel Storage Ponds
  • Nuclear Reactors
  • Solid Nuclear Waste Store
  • Sea Discharge Pipelines
  • Legacy Reactor Exhaust Stacks
  • Reprocessed Product Finishing Lines
  • Medical Source Production Plant
  • Research Development Labs
  • Legacy Reprocessing Plants
  • Contaminated Land

6
What is there to Decommission?
  • 170 major nuclear facilities and 2200 other
    buildings dating from 1940 to 2006
  • 1 million m3 of concrete above ground, 1 million
    m3 below ground
  • Some 200,000 Te of steel to be managed
  • 61,200 M3 of conditioned ILW
  • 37km road, 15km railway,120km sewers, 65km water,
    7km pipebridges (21 off), 16km ducts and trenches
    (333 off)
  • Ongoing commercial operations until at least 2015

7
  • Highly diverse range of hazards. Nuclear,
    Conventional, Radiological and Environmental
    Safety are Paramount

8
NDMPG ramp-up
M
9
The Achievements
10
Cell Stabilisation
  • Highly Active North Outer (HANO) Cell used as a
    route for ventilation gases
  • Air was moist, acidic and warm
  • Significant corrosion to the steelwork occurred
  • Man Access to the HANO Cell precluded,
    prohibiting further decommissioning

11
Cell Stabilisation
  • Bespoke laser scanner deployed to generate 3D
    images of the cell inventory
  • This confirmed contents of cell could be
    encapsulated
  • Low density grout was formulated in order to
    secure inventory
  • Trials were undertaken in mock-up facility off
    site
  • Grout pours now ongoing
  • Upon cell stabilisation the grout can be easily
    removed and size reduced, minimising waste
    volumes and disposal costs

12
Major Projects - Underway
  • Major Projects Group established to drive
    project management excellence, Construction
    underway of a number of site critical facilities

13
Future technical focus
  • Condition monitoring of stored waste, waste
    packages, and store buildings
  • Prediction of liquid discharges
  • Characterisation and treatment of ILW and PCM
    wastes, and where possible reclassification to
    LLW
  • Mobile treatment technologies
  • Treatment of pond floor sludges
  • Disposal techniques for pond furniture
  • Innovative encapsulant technology
  • Decontamination methods
  • Remote dismantling
  • Monitoring, treatment and reclassification of
    high volume LLW

14
Key Future Projects
  • Pile Chimney Demolition
  • Separation Area Ventilation
  • Contaminated Land
  • LLWR Separation
  • Ponds and Silos programme
  • Separation Area Management
  • Site critical new builds
  • SPRS, Evap D E, EPS 3

Nuclear Decommissioning Major Projects Group
Acceleration with Assurance
15
Conclusion
  • We will continue to drive innovation in to the
    heart of all our activities
  • In addition to the technical challenges ahead,
    the industry is undergoing a period of change
  • PBO Competition
  • Energy Coast
  • Revitalised Sellafield
  • New Build
  • Safety and the environment will remain our number
    one priority

16
  • This concludes the presentation
  • Thank you for your attention
Write a Comment
User Comments (0)
About PowerShow.com