Title: COST ALLOCATION


1
COST ALLOCATION
  • A reference to help with cost allocation.

2
Course Objective
  • Learn how to correctly apply your cost allocation
    plan to your center.
  • Learn how to implement your cost allocation plan
    and document costs based on your plan.

3
Allocating Costs
  • If an organization has only one activity that is
    funded by one funding source and if all costs
    associated with the organization are for that
    activity, no allocation is needed.
  • If an organization has multiple activities, and
    one or more funding sources, a cost allocation is
    needed.

4
Direct Costs
  • Direct costs are those which are clearly and
    easily attributable to a specific program.
  • Examples of direct cost are
  • Employee time devoted to one or more activity.
  • Materials purchased for one or more activity.
  • Equipment bought for a specific activity.

5
Indirect Cost
  • Indirect costs are those which are not easily
    identifiable with a specific program, but which
    are, nonetheless, necessary to the operation of
    the program.
  • These costs are shared among programs and, in
    some cases, among functions (program, management
    and general, and fundraising).

6
Indirect Cost Examples
  • Executive Directors salary
  • Chief Financial Officers salary
  • Single Audit report costs
  • Shared office costs, such as rent and utilities

7
Why Allocate Indirect Costs to the Programs?
  • The full cost of a program rightfully includes a
    share of the overall costs of the organization.
  • Knowing the full cost of a program sets a basis
    for financial analysis of the program, and for
    requesting reimbursement from funders for the
    full costs of providing services.

8
What Are the Methods for Allocating Indirect
Costs?
  • There are several methods for allocating indirect
    costs . The most common are
  • case-by-case allocation,
  • developing an indirect cost rate, and
  • Full Time Equivalents (FTEs)

9
Case-by-Case Allocation
  • One method of allocating indirect costs is to
    determine a rate of actual usage for each
    program. For example
  • You may decide to keep track of long distance
    telephone calls and charge them to the
    appropriate program when you pay the phone bill
    each month.
  • Some organizations use a counter or log to track
    copying expenses for each program and/or
    function.
  • Time sheets may form the basis for allocation of
    salaries for the executive director, accountant,
    and staff whose work benefits more than one
    program or activity.

10
Case-by-Case Allocation (cont)
  • The advantage of this method is that it seems to
    make sense.
  • A major disadvantage, however, is that it often
    requires a great deal of time consuming record
    keeping.

11
Case-by-Case Allocation (cont)
  • Even if you keep the records needed to precisely
    allocate shared expenses among programs, not all
    expenses will be covered.
  • If, for example
  • The rent is allocated by square feet, how should
    you allocate the hallway and rest rooms?
  • What about local phone calls which can not be
    tracked using a code?

12
Developing an Indirect Cost Rate
  • The first step in determining an indirect cost
    rate is to separate all costs into two groups
    direct and indirect costs.
  • The indirect costs are aggregated into an
    indirect cost pool and then allocated to the
    programs based on a set proportion or rate.

13
Developing an Indirect Cost Rate (cont)
  • There are several measures used to determine the
    proportion of indirect costs to allocate (apply)
    to each program.
  • The following simple example illustrates an
    indirect cost rate based on the relationship
    between total indirect costs and total direct
    costs.

14
Crisis Center
  • The Crisis Center has a total budget of 3,300.
    The budget is distributed as follows
  • Program A has direct costs of 1,000.
  • Program B has direct costs of 2,000.
  • Indirect costs to run the programs is budgeted at
    300.
  • Total costs are 3,300.

15
Crisis Center (cont)
  • Since Program As direct costs are one-third of
    the total direct cost of the shelter center
    (1,000 out of 3,000), it should bear one-third
    of the indirect costs. Similarly, since Program B
    incurs two-thirds of the total direct costs of
    the shelter center, it should bear two-thirds of
    the indirect costs, as well.
  • An indirect cost rate (using direct costs as a
    base) is established by dividing the total
    indirect costs by the total direct cost.
  • Total Indirect costs divided by Total Direct
    Costs 300/3,00010 percent of total costs

16
Full Time Equivalents (FTEs)
  • Training/Conferences/Seminars- Allocated to the
    program benefiting from the training, conferences
    or seminars. The following example shows how
    costs that benefit two or more specific programs,
    but not all programs.

Expense Amount 5,000
17
OMB Circular A-122 and UGMS
  • Pass-through recipients from the HHSC Family
    Violence Program funding, are required to
    reference the OMB Budget Circular A-122 and UGMS
    using these same principles.
  • However, even within these guidelines, indirect
    cost rates for the same organization may vary
    from federal agency to federal agency.

18
Direct vs. Indirect Allocation
  • Contrary to popular belief, indirect costs are
    not an easy measure of an organizations
    efficiency. Imagine a multi-service agency where
    each program has its own bookkeeper, purchases
    its own supplies, and has all its own equipment.
  • Such an organization would have no indirect
    costs at all, but would be clearly less efficient
    than if the programs shared bookkeeping costs,
    supplies and equipment.

19
Final Comments
  • Because the presentation of financial information
    influences the way we access a providers
    finances, the selection of indirect costing
    methods and accounting procedures has an
    important impact on decision-making.
  • Several urgent and perhaps conflicting demands
    are made of the indirect costing process
  • to attribute indirect costs in the fairest way
    possible,
  • to attribute the most indirect costs to the
    programs that can best afford them,
  • to eliminate as many indirect costs as possible
    by having each program buy its own supplies, etc.
  • Finding a balance among these demands that
    clears confusion and informs decision-makers is a
    responsibility of all participants in the
    nonprofit sector.

20
HHSC Family Violence Program
  • Humphrey Matthews, Contract Manager
  • 512-206-5123
  • Humphrey.matthews_at_hhsc.state.tx.us
  • Helen Oh, Contract Manager
  • 512-206-5565
  • Helen.oh_at_hhsc.state.tx.us
  • Sandra Steward, Program Specialist
  • 512-206-5125
  • Sandra.steward_at_hhsc.state.tx.us
  • Katie Ray-Jones, Program Manager
  • 512-206-5143
  • Katie.ray-jones_at_hhsc.state.tx.us
  • Judy Forbes, Program Specialist
  • 512-206-5040
  • Judy.forbes_at_hhsc.state.tx.us
  • Robyn Mobley, Contract Specialist
  • 512-206-5137
  • Robyn.mobley_at_hhsc.state.tx.us
  • Susie Roberts, Contract Manager
  • 512-206-5517
  • Susie.roberts_at_hhsc.state.tx.us

21
Budget Revisions
  • The HHSC Family Violence Program allows each
    provider to submit a budget revision to ensure
    your grant monies are fully expended.
  • According to the HHSC FVP contract, Article 13,
    Section 13.06 (j), a budget revision should be
    submitted
  • only for allowable expenses,
  • does not contradict other rules or policies, or
  • indicate a change in the scope of the contract.
  • All budget revisions must be submitted using HHSC
    FVP Budget Revision forms (included in the Excel
    Budget Workbook).

22
Budget Revisions (cont)
  • If the total amount of the budget revision is
  • less than 5.0 of the contract amount or 5,000,
    (or a prorated portion if the contract term is
    less than one year, whichever is lower), the
    budget revision must be submitted within 30 days
    of implementation.
  • More than 5.0 of the contract amount or 5,000,
    (or a prorated portion if the contract term is
    less than one year, whichever is lower), the
    budget revision must be submitted prior to
    implementation and approved by the Commission.
  • Retroactive budget revisions will not be accepted
    by HHSC.