Defense Environmental Restoration Program DERP Planning Meeting - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Defense Environmental Restoration Program DERP Planning Meeting

Description:

13 Nov 03 1 of 14. Assistant Secretary of the Army for Installations and Environment ... Directed by ASA(I&E) ... Monthly status reporting to the ASA(I&E) DASA(ESOH) ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 15
Provided by: acs55
Category:

less

Transcript and Presenter's Notes

Title: Defense Environmental Restoration Program DERP Planning Meeting


1
Defense Environmental Restoration Program
(DERP)Planning Meeting
November 13, 2003 Office of the
Deputy Assistant Secretary of the Army
(Environment, Safety and Occupational Health)

2
Topics
  • Army Environmental Cleanup Strategy
  • DASA (ESOH) Top Five
  • Current Issues
  • Military Munitions Response Program
  • Perchlorate Policy
  • Land Use Controls

3
Army Environmental Cleanup Strategy
  • Directed by ASA(IE)
  • Developed by ESOH and OACSIM with participation
    from Program Managers and principals
  • Not just DERP
  • Includes Overseas, Compliance-Related Cleanup,
    FUDS, and Special (unique funding) installations
  • For first time, one Strategy for all program
    areas

4
DASA(ESOH)Top Five
  • Top five initiatives identified by each DASA
  • Monthly status reporting to the ASA(IE)
  • DASA(ESOH)
  • Cleanup - Site accomplishment of RIP/RC for FY 04
    05
  • Integrated Natural Resource Management Plans
    (INRMP) at 80 of installations by FY 04
  • Safety - Reduce accident rates by 50 in two
    years
  • Technology - Validate 5 new technologies for
    field testing
  • Environmental vulnerability - Achieve Low Risk
    category
  • 75 of Army installations by end of 04
  • 80 of Army installations by end of 05

5
DASA(ESOH)Top Five (Cont)
  • DASA(ESOH) Cleanup Achieve RIP/RC for Active
    and BRAC Programs
  • FY 04 207 Active Sites
  • 44 BRAC Sites
  • FY 05 141 Active Sites
  • 27 BRAC Sites
  • Installation Status Reporting Requirements
  • Semi Annual AEDB-R updates
  • Quarterly out of cycle updates for affected
    installations

6
Current Issues
  • Military Munitions Response Program
  • Perchlorate Policy
  • Land Use Controls

7
Current Issues Military Munitions Response Program
  • Munitions Response Directive (DoDD 4715.XX)
  • Provides response policy for all locations other
    than operational ranges
  • Policy guidance expected to be signed by Jan 04
  • MMRP Site Prioritization Protocol
  • OSD has published in Federal Register
  • Public comment period ends November 20, 2003
  • OSD working group is developing metrics
  • Expect DOD to finalize the metrics for cleanup at
    MMRP sites in FY2004
  • Karen Wilson is Army POC

8
Current Issues Perchlorate Policy and Guidance
  • ASCIM Guidance of June 27, 2003
  • Comply with applicable laws
  • Sampling response authorized where
  • release is known or suspected
  • human exposure pathway exists
  • prior approval by HQDA
  • requires development of sampling plan

9
Current Issues Perchlorate Policy and Guidance
(Cont)
  • OSD PDUSD(IE) Interim Policy of September
    29, 2003 directs sampling and establishment of
    database
  • Safe Drinking Water/Unregulated Contaminant
    Monitoring Rule and Clean Water Act
  • Environmental Restoration
  • Reasonable basis to suspect release
  • Human exposure completed pathway is likely
  • Reports to DOD by 31 January 2004
  • Funding Restoration and Compliance accounts
  • Army developing implementing guidance

10
Current Issues Land Use Controls
  • Land Use Controls
  • DoD has approved Navy/EPA Principles
  • Army has endorsed
  • Principles
  • NPL RODs should be lean LUCs will become part of
    a remedy
  • Specific details on LUC management will be placed
    in post-ROD documents
  • Remedial Design
  • Remedial Action Work Plan

11
Current Issues Land Use Controls (cont)
  • Issues Relating to RD Documents
  • As primary document, RD should outline LUC
    performance objectives
  • Should not list all LUC details
  • Augmenting the RD is appropriate
  • Compile a comprehensive site-wide LUC management
    plan
  • LUC Modification Obtain EPA concurrence
  • Existing LUC MOAs and LUCIPs We do not plan to
    revisit
  • Field should transition to documentation approach
    outlined above

12
Current Issues Land Use Controls (cont)
  • LUC Enforcement
  • Prefer cooperative approach to LUC enforcement
  • Work with EPA, States and relevant parties to
    prevent LUC violations
  • Site Closeout
  • May negotiate/finalize Closeout Documents(COD)
  • Avoid using the term Remedial Action Closure
    Report (RACR)
  • DoD will define Land Use Control
  • Will provide to field for incorporation into
    current FFAs without further discussion

13
Current Issues Land Use Controls (cont)
  • DoD InterService Review
  • No 72-hour review required if follow principles
  • Remain silent on issue of whether EPA approves
    5-Year reports
  • Installations may outline basic 5-year review
    commitments in their post-ROD documents
  • Do not agree to any new post-ROD primary
    documents
  • OSD will discuss with EPA in the future

14
Summary
  • DASA(ESOH) continues to have keen interest in
    oversight and advocacy for the Armys
    Installation Restoration Program
  • Good data and consistent story from year-to-year
    is key to program CREDIBILITY and support for
    continued funding