1TRD Chamber production issues
- General Issues, Planning and Hd Status
2Anode wire quality
Dubna wire TW002
TW 002x2
3Anode wire quality cont.
TW 003 before Meteor (Dubna)
TW 003 after Meteor
4Anode wire Quality cont. 2
Bukarest wire Black spots visible by eye More
information to come after looking at different
rolls
5Anode Wire Quality Summary
- Status
- 3 bad roll in Bukarest (out of 3), dust on
Meteor. - 2 bad rolls in Dubna (out of 14? How many were
examined), dust on Meteor. - Heidelberg Wire OK, sometimes dust on Meteor (3
rolls so far). - GSI no Problem.
- Solutions
- Better wire? Is it available, price?
- Look at every winding feasible? (REM not easily
accessible at Hd and Dubna. - Can bad wire be identified under the light
microscope?
6HV cable
- Manufacturer Low noise is not a feature of this
wire - 300 m delivered in December
- production date 2002
- -gt Perfect (few nA starting at 6kV)
- 700 m delivered in January
- production date 2004
- OK few nA starting at 3-4kV
- New wire will be distributed to Bukarest and
Dubna in next delivery. - Currently every wire is tested at Dubna/Bukarest
- no showstopper
7Problem Chamber Hd
- As reported at last Status meeting
-
- 1 Chamber displayed high anode currents after
glueing Panel starting at 1100V (was OK
previously) independant of anode segment used. - After 1 month in the corner chamber is OK ?!?
- Not understood so far.
8L-profile bending
- Dubna had some bent L-profiles, with residual
bending after gluing frame. - Check in Heidelberg some profiles bent more than
acceptable (250um at each side). - Investigation currently under way probably only
relevant for the first series. - Please check before gluing a frame
9Gas connectors
- Problem 1
- Hole in front profile can be too
- small (due to wear of tools)
- should be larger than 19,00mm
- Problem 2
- Gas connectors (glued into front profiles) are
very sensitive parts - No glue residuals, no scratches allowed.
- For gas tightness grease is probably needed.
- ToDo chamber connection test (gas tightness of 2
or 3 Chambers in a row)
10Anode wire breaking
- Dubna and Heidelberg use Olegs solution (see
picture). - Dubna experiences breaking even after fixing
chambers to table - Heidelberg has problems with copper strip not
gluing to wire ledge.
Dubna solution to prevent removal of copper strip
during soldering
11Material Database
- Still very little use, but it is an undebatable
requirement!!! - Maybe leave out unecessary steps during shipping
(e.g. Padplanes should be sent from Frankfurt to
Dubna etc.) - Serial numbers of Radiator/Chamber, Panel,
Padplanes, wire rolls have to be noted and kept
(also for DCDB)
12Schedule
- Layer 6 scenario
- (decision this weekend)
- finish L6C0 material and include in next Dubna
transport (in 3 weeks) - -gt1st Supermodule Chambers May 1st (transport
from Dubna/Bukarest) - decision in 3 weeks
- additional transport to Dubna,
- -gt1st Supermodule Ch
- July 1st (transport time)
- Layer 0 scenario
- (decision this weekend)
-
- L0C0,L0C1 Material at Hd May 1st
- L0C0 material in Dubna
- June 15th
- -gt1st Supermodule Chambers
- July 1st (transport)
- (unefficient, better have a transport in
Sept./Okt.?) -
- (Assuming no Quality Problems)
-
13Dubna Chamber Transport Dates
Supermodule assembly August
Supermodule assembly November
14Bukarest Schedule
- Unclear (to me)
- Climatic constraints?
- Customs requirements? (fixed export dates)
- Is a large transport more efficient?
15Estimated SM production dates(just from Chamber
point of view)
Transport delays not taken into acount All
estimates based on 1 Chamber/week average
production rate Suggest to use as a base plan
until more detailed rate info is available
16Heidelberg Status
- 9xL1C1 finished
- 2xL1C1 being wired
- 3xL1C0
- 3xL2C0
- 1xL1C0 not usable? (Badly glued Padplane maybe
repair possible)