Title: Connecticut
1Connecticuts Output-Based Emissions Standards
for DG,A Survey of Rates for Customers with
On-Site Generation,and Vermonts New RPS Law
- Frederick Weston
- 17 June 2005
2Connecticuts DGEmissions Rule
- Section 22a-174-42 of the Regulations of
Connecticut State Agencies (RCSA) went into
effect January 1, 2005 - Mirrors the RAP Model Rule in the three key
provisions - Emissions standards
- Manufacturer certification
- Credits for CHP
3Mechanism and Applicability
- Permit-by-Rule Compliance with the Connecticut
rule provides a standardized exemption from the
duty to obtain an individual permit pursuant to
RCSA Section 22a-174-3a for the owners and
operators of distributed generators. - The rule is an optional compliance mechanism
traditional new source review is available for
owners and operators who do not choose to operate
under the rule. - The rule applies to existing (installed prior to
1/1/05), new (installed after 1/1/05), or
modified non-emergency generators with the
following characteristics - A nameplate capacity of less than 15 MW
- A potential to emit 15 tons/yr of any air
pollutant (as defined in RCSA 22a-174-1) - Not a new major stationary source and
- Not operated more than a number of hours as
determined by a specified formula.
4What Emissions Are Regulated and How?
- For NOx, PM, CO, CO2
- Output-based standards pounds per MWh
- For SO2
- Ultra-low sulfur fuel requirements
- For liquid fuels, following EPA on-road
requirements - For gaseous fossil fuels other than natural gas,
no more than 10 grains of sulfur per 100 dry
standard cubic feet - Credits for flared fuels and CHP
- Also, on approval of the DEP, for on-site
renewables and end-use efficiency - Dual-fuel generators standards apply to
gas-fired operations liquid-fuel ops limited to
30 days/year
5Emissions Standards
- The Connecticut rule applies the Model Rules
Phase One Attainment emissions limits to existing
non-emergency generators - The rule applies the Model Rules non-attainment,
three-phase standards to new non-emergency
generators - Compliance Manufacturer certification or
performance testing
6Emissions StandardsExisting Generators
Oxides of Nitrogen (lbs/MWh) Particulate Matter (lbs/MWh) Carbon Monoxide (lbs/MWh) Carbon Dioxide (lbs/MWh)
4.0 0.7 10 1900
7Emissions StandardsNew Generators
Date of First Operation Oxides of Nitrogen (lbs/MWh) Particulate Matter (lbs/MWh) Carbon Monoxide (lbs/MWh) Carbon Dioxide (lbs/MWh)
On or after January 1, 2005 0.6 0.7 10 1900
On or after May 1, 2008 0.3 0.07 2 1900
On or after May 1, 2012 0.15 0.03 1 1650
8Other State Actions
- Massachusetts Draft rule with technology-differen
tiated standards, no CHP credit. - New York Draft rule with RACT approach but
output-based. CHP credit uncertain. New and
existing units. - Delaware Draft rule based on the model currently
under consideration. - New Jersey Draft rule recently released for
comment. - Rhode Island Has begun a pre-rulemaking
stakeholder process, using Model Rule as the
basis for discussions. - Maine Rule adopted 1 August 2004, subjecting
non-mobile generators gt 50 kW (unless subject to
new source review) to the model rules attainment
standards.
9Some Stated Objectives of Pricing for Customers
with On-Site Generation
- To provide the services that DG customers want
and need - To give price signals that reflect the system
costs and benefits of DG - To cover the costs imposed on the system by such
customers - Charges should accurately reflect the temporal
and geographic properties of cost causation - To reflect the benefits bestowed on the system by
such customers - Reliability, diversity, avoided G, T, and D
- To encourage (discourage) DG deployment
- Clean DG?
10From 30,000 FeetSome Recurring Themes
- DG reduces consumer demand for grid-supplied
energy and can reduce demand for grid-supplied
generation capacity, but the extent to which it
will depends upon customer loads and the
operational characteristics of the on-site
generation - DG can defer or avoid transmission and
distribution investments, but again the extent to
which it will depends upon customer loads, the
characteristics of the on-site generation, and
the characteristics of the distribution system - On-site generation cannot avoid distribution
investments that serve only the individual
customer (can possibly affect sizing, however) - The grid, and the reliability it provides, has
value for which all customers should pay their
fair share - Reliable analyses of the costs and benefits of
on-site generation have not been performed
11General Features of Utility Rates for DG Customers
- Users with on-site generation are often referred
to as partial requirements customers - Typical services provided
- Stand-by
- Grid power during an unscheduled outage of the
on-site generation - Scheduled maintenance
- Grid power, without penalty or reservation
charges, while the on-site generation is being
serviced - Supplemental (or baseline) Service
- Grid power in excess of that supplied by the
on-site generation, often supplied at the
applicable full-requirements tariff - Economic replacement
- Low-cost (usually interruptible) grid power to
displace on-site generation at times of utility
surplus
12Rate Components
- Distribution
- Fixed recurring customer charges for billing,
metering, administration, etc. (daily or monthly) - Demand charge components
- Charges for distribution facilities dedicated
wholly to the customer (local or dedicated
facilities - Charges for the portion of shared distribution
and transmission facilities attributed to the
customer - Generation
- Demand charges
- Reservation fees, to cover the costs of
generation capacity that will be needed to
provide stand-by service, or - Fees for contingency reserves, the amount of
spinning and supplemental reserves that must be
available to meet the load otherwise served by
the on-site generator - Energy
- Unscheduled, at market prices
- Scheduled, at tariffed or otherwise specified
prices - Risk and other cost adjustments (e.g., system
usage fee)
13Typical Tariff Features
- Customer size, as measured in MW
- Minimum amounts of contract demand
- Indiana (AEP) 500 kW, increments of 100 kW
- Exemptions if below a specified size
- Minnesota 60 kW
- Oregon 1 MW
- Texas for on-site renewables that dont export
(considered energy efficiency) - Note TX does not have stand-by service for
partial requirements customers service is taken
under regular tariffs - New York 50 kW (contract demand) or if the DG
serves no more than 15 of the on-site load - Massachusetts (NSTAR) 250 kW and aggregations
between 251 kW and 1 MW that serve no more than
30 of the on-site load
14Typical Tariff Features
- Technology
- Exemptions for renewables
- MA (NSTAR) Renewables as defined in other state
policies, except fuel cells - NY Designated technologies including CHP
- RI Eligible renewable energy resources up to
an aggregate statewide cap of 3 MW - Seasonal Cost Differences
- MA, NY, CA, AZ
- Time of Use
- Peak, off-peak AZ, CA, NY
15PGE Schedule 83Full Requirements
Schedule 83, Standard Offer Service, Large Non-Residential Schedule 83, Standard Offer Service, Large Non-Residential Schedule 83, Standard Offer Service, Large Non-Residential Schedule 83, Standard Offer Service, Large Non-Residential
Delivery Voltage Delivery Voltage Delivery Voltage
Secondary Primary Subtransmission
Basic Monthly Charge
Single-Phase Service 20.00
Three-Phase Service 25.00 150.00 500.00
Transmission Related Services
Per kW of monthly Demand 0.78 0.78 0.78
Distribution Charges
The sum of the following, per month
Per kW of Facility Capacity 2.27 1.65 0.32
Per kW of monthly Demand
First 30 kW 0.56 1.89 1.05
Over 30 kW 1.89 1.89 1.05
Energy Charge
Cost of Service Option, per kWh
1,000 kW Facility Capacity 0.04239 0.04083
gt 1,000 kW Facility Capacity
On-Peak Period 0.04507 0.04326 0.04254
Off-Peak Period 0.03743 0.03593 0.03534
System Usage Charge
Per kWh 0.00485 0.00354 0.00257
1 Costs for contingency reserves are bundled in
the energy charges. PGE also offers a variety of
market-based energy options not described here.
16PGE Schedule 75Partial Requirements
Schedule 75, Partial Requirements Service Schedule 75, Partial Requirements Service Schedule 75, Partial Requirements Service Schedule 75, Partial Requirements Service
Delivery Voltage Delivery Voltage Delivery Voltage
Secondary Primary Subtransmission
Basic Monthly Charge
Single-Phase Service 20.00
Three-Phase Service 25.00 150.00 500.00
Transmission Related Services
Per kW of monthly Demand 0.78 0.78 0.78
Distribution Charges
The sum of the following, per month
Per kW of Facility Capacity 2.27 1.65 0.32
Per kW of monthly Demand
First 30 kW 0.56 1.90 1.06
Over 30 kW 1.90 1.90 1.06
Generation Contingency Reserves
Spinning Reserves
Per kW of Reserved Capacity gt 1,000 kW 0.234 0.234 0.234
Supplemental Reserves
Per kW of Reserved Capacity gt 1,000 kW 0.234 0.234 0.234
System Usage Charge
Per kWh 0.00485 0.00354 0.00257
Energy Charge
Baseline Energy Per Schedule 83 Per Schedule 83 Per Schedule 83
Scheduled Maintenance, max 744 hrs/ calendar year Daily or Monthly Fixed, per Schedule 83 Daily or Monthly Fixed, per Schedule 83 Daily or Monthly Fixed, per Schedule 83
Unscheduled Dow Jones Mid-Columbia Hourly Firm Electricity Price Index, plus wheeling charges and a 0.003/kWh recovery charge, and adjusted for losses Dow Jones Mid-Columbia Hourly Firm Electricity Price Index, plus wheeling charges and a 0.003/kWh recovery charge, and adjusted for losses Dow Jones Mid-Columbia Hourly Firm Electricity Price Index, plus wheeling charges and a 0.003/kWh recovery charge, and adjusted for losses
17NSTAR G-3 Rate
NSTAR Rate G-3 NSTAR Rate G-3 NSTAR Rate G-3
Customer Charge, per month 237.07 237.07
October May June September
Distribution Charge, per kW/month 5.58 11.66
Transition, per kW/month 2.46 7.70
Transition, per kWh
Peak hours usage 0.01954 0.03119
Off-peak hours usage 0.00704 0.01044
Transmission, per kW/month 2.37 2.37
Supplier Services (Optional)
Default or Standard Offer As in effect per tariff As in effect per tariff
18NSTAR Stand-By Delivery Rate
NSTAR Rate SB-3 NSTAR Rate SB-3 NSTAR Rate SB-3
Customer Charge, per month As per applicable rate schedule As per applicable rate schedule
Monthly Distribution Charge, per kW October May June September
Contract Demand lt 1,000 kW 3.58 6.65
Contract Demand gt 1,000 kW 5.02 9.33
Transmission No charge No charge
Transition No charge No charge
19Comparison
- Annual costs for stand-by service, customer and
distribution charges only, for a customer with a
contract demand of 1,000 kW, at primary voltage - PGE 53,760.00
- NSTAR 80,324.84
- Caveat This implies no judgment as to the cost
bases of the rates or the cost characteristics of
the two utilities.
20Issues and Ideas
- Demand charges
- As-used Monthly, daily
- Ratchets
- Distribution planning and the sizing of the wires
- Ability of planning methods to properly value DG
- Incentives for DG incentives for utilities
- Impacts on utility profitability regulatory
fixes - Policy leadership assuring consistency among
state agencies, utilities - What technical issues are consistent across
systems? - When does a policy overlay make sense (beyond
technical and economic issues)? - Cost-shifting (revenue responsibility) vs. future
cost avoidance - How can rates for DG customers be structured to
promote environmental policy objectives? Should
they be?
21Issues and Ideas
- Best efforts or Non-Firm Stand-by Service
- A customer would not be creating any requirement
for the utility to invest in any generation or
transmission plant or equipment to provide
standby service. This could justify no demand
charge at all. - Low Demand, High Energy
- Demand charges based on a fraction of nameplate
capacity, high energy charge - Reflects low probability of DG outages coincident
with peak - Strong incentive to maintain and operate DG
- Similar to RI settlement where customers are not
charged TD for back-up, only for supplemental
(reflects diversity)
22Renewables underVermont S.52
- RPS beginning 7/1/13, equal to all incremental
sales growth between 11/05 and 1/1/12, not to
exceed 10 of 2005 sales - Satisfied through contracts, RECs, or payments to
a renewables fund or for end-use efficiency - Sustainably Priced Energy Enterprise Program
(SPEED) in lieu of RPS - Supports long-term utility contracting for
renewables (qualifying resources) and CHP
(non-qualifying) between 2006 and 2012. If
output from qualifying resources meets or exceeds
the RPS requirement, then the RPS will not go
into effect - Passed House and Senate this month. Governor
expected to sign.
23Appendix A
- Connecticuts DG emissions rule in greater detail
24Connecticuts Rule
- Section 22a-174-42 of the Regulations of
Connecticut State Agencies (RCSA) went into
effect January 1, 2005 - Mirrors the RAP Model Rule in the three key
provisions - Emissions standards
- Manufacturer certification
- Credits for CHP
25RAP Model Rule for DG Emissions
- Developed by a public/private stakeholder group
over a two-year period - Funded by DOE/NREL
- Available at www.raponline.org
- Model Regulations for the Output of Specified Air
Emissions from Smaller-Scale Electric Generation
Resources, 31 October 2002 Review Draft
26Optional Compliance Mechanism
- Permit-by-Rule Compliance with the Connecticut
rule provides a standardized exemption from the
duty to obtain an individual permit pursuant to
RCSA Section 22a-174-3a for the owners and
operators of distributed generators. - RCSA 22a-174-3a contains the states new source
review permit program. - Actual emissions are limited to less than 15
tons/yr of any individual air pollutant (the new
source review permitting threshold). - The rule is an optional compliance mechanism
traditional new source review is available for
owners and operators who do not choose to operate
under the rule.
27Applicability
- The rule applies to existing (installed prior to
1/1/05), new (installed after 1/1/05), or
modified non-emergency generators with the
following characteristics - A nameplate capacity of less than 15 MW
- A potential to emit 15 tons/yr of any air
pollutant (as defined in RCSA 22a-174-1) - Not a new major stationary source and
- Not operated more than a number of hours as
determined by a specified formula. - Intent of the formula is to limit emissions of
generators eligible for the permit-by-rule to
under 15 tons per year of any air pollutant. If
a generator cannot meet the requirements of the
rule (e.g., the limits or the operating-hour
limitation), the operator would seek an
individual permit under new source review.
28Exemptions
- The rule does not apply to
- Generators or engines subject to 40 CFR 52.21,
89, 90, 91, or 92 - Generators powered by fuel cells, wind, or solar
energy. - Emergency generators, which are regulated under
RCSA 22a-174-22(a) (defines emergency). - In Connecticut, an emergency generator is not
considered a distributed generator and therefore
cannot operate under the rule.
29What Emissions Are Regulated and How?
- For NOx, PM, CO, CO2
- Output-based standards pounds per MWh
- For SO2
- Ultra-low sulfur fuel requirements
- For liquid fuels, following EPA on-road
requirements - For gaseous fossil fuels other than natural gas,
no more than 10 grains of sulfur per 100 dry
standard cubic feet - Credits for flared fuels and CHP
- Also, on approval of the DEP, for on-site
renewables and end-use efficiency - Dual-fuel generators standards apply to
gas-fired operations liquid-fuel ops limited to
30 days/year
30Emissions Standards
- The Connecticut rule applies the Model Rules
Phase One Attainment emissions limits to existing
non-emergency generators - The rule applies the Model Rules non-attainment,
three-phase standards to new non-emergency
generators
31Emissions StandardsExisting Generators
Oxides of Nitrogen (lbs/MWh) Particulate Matter (lbs/MWh) Carbon Monoxide (lbs/MWh) Carbon Dioxide (lbs/MWh)
4.0 0.7 10 1900
32Emissions StandardsNew Generators
Date of First Operation Oxides of Nitrogen (lbs/MWh) Particulate Matter (lbs/MWh) Carbon Monoxide (lbs/MWh) Carbon Dioxide (lbs/MWh)
On or after January 1, 2005 0.6 0.7 10 1900
On or after May 1, 2008 0.3 0.07 2 1900
On or after May 1, 2012 0.15 0.03 1 1650
33Emissions Standards Compliance
- Options Certification or performance testing
- Certification
- Demonstrated certification by CARB
- Certification by manufacturer testing
- Generator will meet standards for the lesser of
15,000 hours or three years of operation in
effect, a warranty - Testing methods applicable EPA Reference
Methods, CARB methods, or equivalent - Liquid fuel reciprocating engines ISO Method
8178
34Emissions StandardsCompliance
- Performance testing
- Existing generators within 180 days of the
rules effective date - New or modified generators within 180 days of
installation or modification (if modification
increases emissions output) - Testing methods applicable EPA Reference
Methods, CARB methods, or equivalent - Liquid fuel reciprocating engines ISO Method
8178 - If unable to comply, operation must cease
immediately - The DEP may conduct field audits at its discretion
35Credit forConcurrent Emissions
ReductionsFlared Fuels
- If a generator uses fuel that would otherwise be
flared, the owner or operator may deduct the
emissions that were or would have been produced
through the fuel flaring from the actual
emissions of the generator on a per-pollutant
basis, for the purposes of calculating compliance
with the requirements of this rule. - Credit may be based on either the actual
emissions offset (if able to be documented) or on
default values specified in the rule.
36Credit forConcurrent Emissions ReductionsCHP
- The owner or operator of a CHP system may receive
a compliance credit against its actual emissions
on a per-pollutant basis, as follows - The power-to-heat ratio must be between 4.0 and
0.15, and - The design system efficiency must be at least 55
percent.
37Credit forConcurrent Emissions ReductionsCHP
(continued)
- CHP Credit, mathematically
- Credit lbs/MWhemissions
- (thermal system lbs/MMBtu)/(thermal system
efficiency) 3.412/(power-to-heat ratio) - Note Offset boiler emissions are capped at (a),
for new installations, the standards for new
gas-fired boilers as set out in 40 CFR 60,
Subparts Da, Db, and Dc, or (b), for existing
boilers, maximums specified in the rule. This
latter provision strikes a balance between
rewarding owners for removing an older, dirtier
boiler and perpetuating those old boiler
emissions with a CHP system that is dirtier than
it needs to be. The efficiency of the displaced
system is (a) a default of 80, (b) its actual
design efficiency, or (c), in the case of
retrofits, its historic efficiency, if it can be
documented.
38Other State Actions
- Massachusetts Draft rule with technology-differen
tiated standards, no CHP credit. - New York Draft rule with RACT approach but
output-based. CHP credit uncertain. New and
existing units. - Delaware Draft rule based on the model currently
under consideration. - New Jersey Draft rule recently released for
comment. - Rhode Island Has begun a pre-rulemaking
stakeholder process, using Model Rule as the
basis for discussions. - Maine Rule adopted 1 August 2004, subjecting
non-mobile generators gt 50 kW (unless subject to
new source review) to the model rules attainment
standards.
39Appendix B
- Synapse-RAP stand-by rates survey report in
greater detail
40Rates for Customers with On-Site DGThe Project
- Under a contract with the California Energy
Commission (through the National Renewable Energy
Laboratory), Synapse Energy Economics and RAP are
surveying state policy on stand-by rates for
customer-sited DG/CHP systems. - The purpose is to identify the suite of
innovative ratemaking policies that will best
support the deployment of clean DG systems.
41The Project
- Three parts
- Survey of a representative sample of states
- Arizona, California, Indiana, Massachusetts,
Minnesota, New York, Oregon, Rhode Island, Texas,
and Vermont - Interviews with regulators, utility officials,
consumers, manufacturers, developers, etc. - Final report with policy recommendations
- First two parts are (largely) completed final
report due in June. - This presentation is a summary of what weve
learned from the surveys and interviews, and of
issues for recommendations
42Some Stated Objectives of Pricing for Customers
with On-Site Generation
- To provide the services that DG customers want
and need - To give price signals that reflect the system
costs and benefits of DG - To cover the costs imposed on the system by such
customers - Charges should accurately reflect the temporal
and geographic properties of cost causation - To reflect the benefits bestowed on the system by
such customers - Reliability, diversity, avoided G, T, and D
- To encourage (discourage) DG deployment
- Clean DG?
43From 30,000 FeetSome Recurring Themes
- DG reduces consumer demand for grid-supplied
energy and can reduce demand for grid-supplied
generation capacity, but the extent to which it
will depends upon customer loads and the
operational characteristics of the on-site
generation - DG can defer or avoid transmission and
distribution investments, but again the extent to
which it will depends upon customer loads, the
characteristics of the on-site generation, and
the characteristics of the distribution system - On-site generation cannot avoid distribution
investments that serve only the individual
customer (can possibly affect sizing, however) - The grid, and the reliability it provides, has
value for which all customers must pay their fair
share - Reliable analyses of the costs and benefits of
on-site generation have not been performed
44General Features of Utility Rates for DG Customers
- Users with on-site generation are often referred
to as partial requirements customers - Typical services provided
- Stand-by
- Grid power during an unscheduled outage of the
on-site generation - Scheduled maintenance
- Grid power, without penalty or reservation
charges, while the on-site generation is being
serviced - Supplemental (or baseline) Service
- Grid power in excess of that supplied by the
on-site generation, often supplied at the
applicable full-requirements tariff - Economic replacement
- Low-cost (usually interruptible) grid power to
displace on-site generation at times of utility
surplus
45Rate Components
- Stand-by and related rates are typically
structured along conventional lines - Customer charges
- Demand charges for capacity (per kW)
- Distribution, transmission, generation
- Bundled or un-
- Energy charges (per kWh)
46Rate Components
- Distribution
- Fixed recurring customer charges for billing,
metering, administration, etc. (daily or monthly) - Demand charge components
- Charges for distribution facilities dedicated
wholly to the customer (local or dedicated
facilities) - Some of which may be included in the fixed
customer charges - Assessed against either customer non-coincident
peak demand, maximum potential demand, or
negotiated contract demand - Charges for the portion of shared distribution
and transmission facilities attributed to the
customer - The rates are typically multiplied by a
customers non-coincident peak, maximum potential
demand, or contract demand, but they are intended
to cover the cost of the customers contribution
to coincident peak on the shared facilities (the
rates, in effect, reflect the relationship
between the average customers coincident and
non-coincident demand).
47Rate Components
- Generation
- Demand charges
- Reservation fees, to cover the costs of
generation capacity that will be needed to
provide stand-by service, or - Fees for contingency reserves, the amount of
spinning and supplemental reserves that must be
available to meet the load otherwise served by
the on-site generator - Energy
- Unscheduled, at market prices
- Scheduled, at tariffed or otherwise specified
prices - Risk and other cost adjustments (e.g., system
usage fee)
48Typical Tariff Features
- Customer size, as measured in MW
- Minimum amounts of contract demand
- Indiana (AEP) 500 kW, increments of 100 kW
- Exemptions if below a specified size
- Minnesota 60 kW
- Oregon 1 MW
- Texas for on-site renewables that dont export
(considered energy efficiency) - Note TX does not have stand-by service for
partial requirements customers service is taken
under regular tariffs - New York 50 kW (contract demand) or if the DG
serves no more than 15 of the on-site load - Massachusetts (NSTAR) 250 kW and aggregations
between 251 kW and 1 MW that serve no more than
30 of the on-site load
49Typical Tariff Features
- Technology
- Exemptions for renewables
- MA (NSTAR) Renewables as defined in other state
policies, except fuel cells - NY Designated technologies including CHP
- RI Eligible renewable energy resources up to
an aggregate statewide cap of 3 MW - Seasonal Cost Differences
- MA, NY, CA, AZ
- Time of Use
- Peak, off-peak AZ, CA, NY
50Typical Tariff Features
- Billing Demand or Reservation Capacity
- Most tariffs tie a customers billing demand to
usage coincident with system peak or peak periods
of usage (e.g., Rhode Island, Texas, Minnesota,
and Oregon). - Contract demand, as agreed on by the customer and
stand-by service provider not necessarily
related to the size of the on-site generation - Physical Assurance Customer guarantee that, if
its generator trips, the customers demand for
grid power will not exceed a specified level
(often involves instantaneous load shedding) - Billing demand will be used to calculate total
charges for shared facilities and generation
capacity
51Arizona
- Tucson Electric Powers Partial Requirements
Usage Percentage (PRUP) - Determines whether a customer takes service under
the standby tariff or the supplemental. - Effectively caps the number of hours per billing
period during which a customer can rely on
back-up power. - The PRUP is the ratio of Backup Energy Purchased
to the product of Billing Demand for standby
service and hours in the billing period. If the
PRUP exceeds five percent in a period, the
customers Energy Charge is converted to the
Supplemental Service energy charge for all
kilowatt-hours in excess of the five percent. - Arizona Public Service
- Minimum number of stand-by hours/month
allocation of hours determined by customer
penalties for violations - Must maintain a 75 capacity factor over rolling
18 months - Discounts for achieving higher CFs
52Minnesota
- Customers are eligible for PUC-approved credits
for - Avoided distribution costs and avoided line
losses - If renewable DG, avoided purchases of green power
- Avoided purchases of SO2 allowances
- To receive the credits, customer must fund a
utility study to determine whether the customers
load and generation profiles justify them
53New York
- Contract demand charges for local facilities
costs - Based on a customers potential maximum electric
load, determined by the utility, and set yearly - On-peak, daily as-used demand charge for shared
facilities costs - Assessed during daytime (e.g., from 8am to 10pm)
and for the daily amount of standby service
demand (kW) a customer uses - No differentiation between distribution prices
for scheduled and unscheduled outages - On the grounds that the costs of the wires do not
differ according to the portion of the customers
load served by DG or whether an outage is
scheduled or not
54Oregon (PGE)
- Full requirements rates for local and shared
facilities - Times the average of the two highest months in
previous 12-month period - Will reflect the impacts (in kW) of an outage of
on-site generation if replaced by Unscheduled
Energy - Rates for Contingency Reserves
- DG subject to same requirement of other
generators they must have or buy spinning and
supplemental reserves which together equal to 7
of their nameplate capacity - Rates for the two contingency reserves are equal
to 7 of the cost of reserve capacity (adjustable
by agreed-on, instantaneous load reductions) - 0.468 per kilowatt per month (2,808/yr for a
500-kW reserved capacity) - Multiplied by reserved capacity in excess of 1 MW
- Supplemental service at full requirements tariffs
- Scheduled maintenance
- Unscheduled Energy
55PGE Schedule 83Full Requirements
Schedule 83, Standard Offer Service, Large Non-Residential Schedule 83, Standard Offer Service, Large Non-Residential Schedule 83, Standard Offer Service, Large Non-Residential Schedule 83, Standard Offer Service, Large Non-Residential
Delivery Voltage Delivery Voltage Delivery Voltage
Secondary Primary Subtransmission
Basic Monthly Charge
Single-Phase Service 20.00
Three-Phase Service 25.00 150.00 500.00
Transmission Related Services
Per kW of monthly Demand 0.78 0.78 0.78
Distribution Charges
The sum of the following, per month
Per kW of Facility Capacity 2.27 1.65 0.32
Per kW of monthly Demand
First 30 kW 0.56 1.89 1.05
Over 30 kW 1.89 1.89 1.05
Energy Charge
Cost of Service Option, per kWh
1,000 kW Facility Capacity 0.04239 0.04083
gt 1,000 kW Facility Capacity
On-Peak Period 0.04507 0.04326 0.04254
Off-Peak Period 0.03743 0.03593 0.03534
System Usage Charge
Per kWh 0.00485 0.00354 0.00257
1 Costs for contingency reserves are bundled in
the energy charges. PGE also offers a variety of
market-based energy options not described here.
56PGE Schedule 75Partial Requirements
Schedule 75, Partial Requirements Service Schedule 75, Partial Requirements Service Schedule 75, Partial Requirements Service Schedule 75, Partial Requirements Service
Delivery Voltage Delivery Voltage Delivery Voltage
Secondary Primary Subtransmission
Basic Monthly Charge
Single-Phase Service 20.00
Three-Phase Service 25.00 150.00 500.00
Transmission Related Services
Per KW of monthly Demand 0.78 0.78 0.78
Distribution Charges
The sum of the following, per month
Per kW of Facility Capacity 2.27 1.65 0.32
Per kW of monthly Demand
First 30 kW 0.56 1.90 1.06
Over 30 kW 1.90 1.90 1.06
Generation Contingency Reserves
Spinning Reserves
Per kW of Reserved Capacity gt 1,000 kW 0.234 0.234 0.234
Supplemental Reserves
Per kW of Reserved Capacity gt 1,000 kW 0.234 0.234 0.234
System Usage Charge
Per kWh 0.00485 0.00354 0.00257
Energy Charge
Baseline Energy Per Schedule 83 Per Schedule 83 Per Schedule 83
Scheduled Maintenance, max 744 hrs/ calendar year Daily or Monthly Fixed, per Schedule 83 Daily or Monthly Fixed, per Schedule 83 Daily or Monthly Fixed, per Schedule 83
Unscheduled Dow Jones Mid-Columbia Hourly Firm Electricity Price Index, plus wheeling charges and a 0.003/kWh recovery charge, and adjusted for losses Dow Jones Mid-Columbia Hourly Firm Electricity Price Index, plus wheeling charges and a 0.003/kWh recovery charge, and adjusted for losses Dow Jones Mid-Columbia Hourly Firm Electricity Price Index, plus wheeling charges and a 0.003/kWh recovery charge, and adjusted for losses
57NSTAR G-3 Rate
NSTAR Rate G-3 NSTAR Rate G-3 NSTAR Rate G-3
Customer Charge, per month 237.07 237.07
October May June September
Distribution Charge, per kW/month 5.58 11.66
Transition, per kW/month 2.46 7.70
Transition, per kWh
Peak hours usage 0.01954 0.03119
Off-peak hours usage 0.00704 0.01044
Transmission, per kW/month 2.37 2.37
Supplier Services (Optional)
Default or Standard Offer As in effect per tariff As in effect per tariff
58NSTAR Stand-By Delivery Rate
NSTAR Rate SB-3 NSTAR Rate SB-3 NSTAR Rate SB-3
Customer Charge, per month As per applicable rate schedule As per applicable rate schedule
Monthly Distribution Charge, per kW October May June September
Contract Demand lt 1,000 kW 3.58 6.65
Contract Demand gt 1,000 kW 5.02 9.33
Transmission No charge No charge
Transition No charge No charge
59Comparison
- Annual costs for stand-by service, customer and
distribution charges only, for a customer with a
contract demand of 1,000 kW, at primary voltage - PGE 53,760.00
- NSTAR 80,324.84
- Caveat This implies no judgment as to the cost
basis of the rates or the cost characteristics of
the two utilities.
60Issues and Ideas
- What kinds of service do DG customers really want
and need? - What is the probability that stand-by service
will be needed and how should the various rate
elements be adjusted to reflect it? - Sliding scale of performance-based stand-by
charges? Based on capacity factor or number and
duration of calls for stand-by? - How do rates affect customer capital allocation
decisions? - What is the proper differentiation between local
and shared facilities? Does DG alter the
allocation of shared facilities to DG customers?
How easily and quickly are shared facilities
redeployed? - Tension between the fixed nature of the
facilities in the short run and their
demand-driven nature in the long-run
61Issues and Ideas
- How do the load profiles of customers with DG
differ from those without? Do they? - What rate design policies flow from this? Should
DG customers be treated differently than non-DG
customers? - If not, will DG customers be penalized by full
requirements tariffs? - What costs does on-site generation impose on the
system? - Distinctions between T, D, and G
- What benefits does on-site generation provide the
system? - Diversity of opinion on diversity benefits
- Cost of service reductions from avoided
generation, transmission, and distribution costs
e.g., MN recognizes - Environmental, reduced losses, improved
reliability e.g., in recognition of such, RI
allows PUC to order rate discounts
62Issues and Ideas
- Demand charges
- As-used Monthly, daily
- Ratchets
- Distribution planning and the sizing of the wires
- Ability of planning methods to properly value DG
- Incentives for DG incentives for utilities
- Impacts on utility profitability regulatory
fixes - Policy leadership assuring consistency among
state agencies, utilities - What technical issues are consistent across
systems? - When does a policy overlay make sense (beyond
technical and economic issues)? - Cost-shifting vs. future cost avoidance
- How can rates for DG customers be structured to
promote environmental policy objectives? Should
they be?
63Issues and Ideas
- Best efforts or Non-Firm Stand-by Service
- A customer would not be creating any requirement
for the utility to invest in any generation or
transmission plant or equipment to provide
standby service. This could justify no demand
charge at all. - Low Demand, High Energy
- Demand charges based on a fraction of nameplate
capacity, high energy charge - Reflects low probability of DG outages coincident
with peak - Strong incentive to maintain and operate DG
- Similar to RI settlement where customers are not
charged TD for back-up, only for supplemental
(reflects diversity)