Title: Arup K. Ghosh
1WBS 2.4.2 STRAND PROCUREMENT
2Outline
- Present status of strand procurement
- Future strand for LARP
- Smaller Filament Deff
- PIT strand
- Tolerance of RRP conductors to cabling
degradation - Filament Spacing
- Rolled strand
- Revisit strand specification
3Procurement PlanNov-05
4Nb3Sn Strand SpecificationRRP-54/61
Spec. No. LARP-MAG-M-8001-RevB
5Procurement Status3-30-06
6Strand Purchase and Inventory as of 4-20-06
7RRP 54/61 Piece Length
- 250 kg of wire produced for LARP and CDP in the
last 12 months, single billet yield is 35kg - 93 in lengths gt1Km, 57 in lengths gt3 km
- With the following HT 665C/50 hrs
- Average Jc(12T)2880 A/mm2
- Average RRR 189
8Procurement Plan For FY07 3-30-06
9Projected Inventory
10Towards a more flux-jump stable conductor
- Why ?
- Intrinsic (Adiabatic) stability of wire
- Field quality in magnets
- Reduce Effective Filament Diameter Deff
- Deff lt 30 mm (adiabatic limit not established
experimentally for high Jc wire ) - For Deff gt 35 mm, maintain high RRR after
reaction ? prevent Sn-leakage - OST-RRP- 91 and 127 sun-element billet design
- Cabling Effects
- Shearing of sub-elements ?RRR degradation
- SMI-PIT- 288
- 50 mm at 1.25 mm wire
- 32 mm at 0.8 mm wire
11Decreasing the sub-element size
- Pack increasing number of sub-elements into
Re-stack - Increasing number of bundles ? packing more
difficult - More cold work increases the hardness of non-Sn
parts - Additional Cu-Cu surfaces ? worse bonding ? yield
?
1291-127-217 series made with Nb-Ta for CDP RD
- High Jc design (3000 A/mm2)
- Objective was to only vary the sub-element size
- same sub element billet for all restacks
- all restacks 53 non-Cu, 0.7 mm strand
- Significant wire breakage for all, 217-stack the
worst - For a reaction at 665 C/50hrs
- (Jc, RRR)
- 91-stack 2920, 134
- 127-stack 2720, 110
- 217-stack 2660, 7 (Many broken barriers)
- Suggests there is some size effect controlling
the maximum Jc
13Future RRP Strand
- Is OST ready to produce 91 and 127 sub-element
billets ?
Further to our discussions today about 61 ? 127
stack designs for LARP, this year we are
producing 91-stack material for the EFDA dipole.
The sub-element design is for lower Jc and uses
Nb-Ti (Jc 2400 _at_ 12 T), but the work will give
us some yield data on our way to 127 stacks.
Based on CDP RD billet 8079 (90/91) and FNAL
billet 8195 (108/127) both of which uses the
same sub-elements of Nb/Nb-47Ti
14(No Transcript)
15EFDA Dipole Project
E. Salpietro
Strand based on 90/91-stack design using Nb/
Nb-47Ti rods
Due dates Delivery One (30 kg strand) delivered
Delivery Two (120 kg strand) 9 months
Delivery Three (280 kg strand) 15 months
16Future RRP Strand
- Is OST ready to produce 91 and 127 sub-element
billets ? - At present the lower Jc ( gt 2000 A/mm2) 91-design
billet is moving into production ? EFDA Order of
400 kg - Under CDP RD this year, a high Jc 108/127
billet is being processed (Nov-06) - FNAL has OST fabricating a RD billet using
120/127 design (Dec-06)
17Powder-in-Tube (NbTa)3Sn (PIT)Shape Metal
Innovation (SMI)
J. Lindenhovious
B179
18PIT -Strand
Luc Oberli (CERN) WAMDO-06
- NED is pushing SMI-VAC to develop strand.
- Latest billet B207 is 288 filament, similar to
B179 - Strand Diameter 1.25 mm
- Cu/Non-Cu 0.96
- Jc gt 2400 A/mm2 At 12 T
B179
B 207
19SMI 288 filament
Luc Oberli (CERN) WAMDO-06
Jc 2077 A/mm2 at 12 T Jc 1118 A/mm2 at 15
T HT 84 hours at 675 0C Jc non Cu lower than
B179 by 10 - 15 due to powder preparation
which underwent by mistake an additional HT.
- Stability measurements performed by LASA
Field rate 15 mT/s - At 1591 A, no quench in the field range 0 - 5
T
20SMI-PIT B-207
Wire drawn to 0.8 mm Jc(12T) 2145 A/mm2 , Js gt
4500 A/mm2 (Is gt1200A) Filament size 32 mm (No
flux-jump observed in magnetization)
21Cabling Degradation
- Strand Deformation at the cable edges
- Filament Distortion
- Simulate by rolling strands
- E. Barzi (FNAL)
- Filament Merging
- Microscopy, Ic and Is measurements
22Rolled Strands
RRP 54/61
Def28
Def14
23SMI Strand deformation by rolling
Luc Oberli (CERN) WAMDO-06
B 201
B 179
Deformation of 25 , i.e. d0 - t 0.25 mm.
Distribution of Cu within the strand important
in order the strand can sustain heavy
mechanical deformation as in cabling.
24SMI Deformation by rolling on B207
Luc Oberli (CERN) WAMDO-06
Ic Degradation of 15 17 on samples with a
deformation level of 28 RRR value dropped to 80
indicating Sn diffusion in the Cu matrix
Def 28
No HT
Def 28 after 84 h at 675 0C
With HT
2.8 at. Sn
25 Re-visit Strand Specification
26Summary
- There is sufficient RRP 54/61 strand for the
magnets in the near term - 91-filament is moving into production
- 127 filament can be in production within 12
months. - PIT strand with 288 filaments is flux-jump
stable at 0.8 mm wire diameter with Jc 2100
A/mm2 at 12 T - Cabling Degradation from filament shearing
- Optimization of cabling parameters
- Optimization of strand design
- Increase filament spacing ? (FNAL has already
ordered a 60/61 billet with larger Cu-spacing,
evaluation in progress)