Title: Introduction and Requirements
1Introduction and Requirements
- R. Assmann
- for the collimation team
2Basic constraints
- Have a collimation system produced and installed
for 2007, with a reasonable cost. - The system must be a robust and flexible tool for
operation. - Nominal performance must be achievable.
- The layout of cleaning insertions must be
finalized by the end of 2003.
3Collimation project
- Started in last October.
- Team and individual responsibilities set up by
January. - Half a year of intense work to arrive at a
coherent proposal. - Final consensus was built in the collimation team
over the last month (collimation WG, collimator
project meeting, ABPATB meetings). - Proposal is presented now, as we must enter into
the detailed engineering phase.
4Ideas/comments/work by many different people
- E.g. 23 persons presented their work at the CWG
or CPM in 2003 (see web). - Strong support from AB/ABP, AB/ATB, AB/BDI,
AB/BT, AB/CO, AB/OP, AB/RF, AT/MTM, AT/VAC,
EST/ME, MPWG, TIS/RP collaborators at IHEP and
TRIUMF. Thanks for the support! - Proposal refers to work mostly done in AB/ABP,
AB/ATB, AB/BT, AT/VAC, TIS/RP groups (1000s of
CPU and man hours). - Not one revolutionary idea but many ideas in an
evolutionary process. - The result has been achieved by the whole team
and would not have been possible without relying
on the past work.
5Driving beam impact requirements
- 450 GeV
- 1 full p batch (4 PS batches) on 1.2 mm 1.2 mm.
- 7 TeV
- 8 p bunches over 1 mm 0.2 mm (irregular dump
after factor 2.5 improvement due to AB/BT
efforts). Severe 2 full Tevatron beams. - 41011 p/s for 10 s, 81010 p/s continuously in
200 nm surface. 10 times less for secondary
collimators. (slow case) - Note
- Only one failure at a time is assumed.
- Almost any jaw can be hit (keep flexibility for
the LHC tune). - Transfer line collimation protects the LHC arcs
but not always the LHC collimators. - Corresponding requirements defined for ions.
- Collimators should withstand these impact
scenarios (expected problems, not worst-case
collimators will be destroyed in worst case dump
failure). - Choice of appropriate materials/cooling! (V.
Vlachoudis O. Aberle N. Hilleret).
6Other requirements
- Mechanical tolerances can be met ( 25 mm
surface flatness, ) - Collimator opening gap can be guaranteed at all
times (error lt 50 mm) - Collimators can be moved by small steps ( mm,
mrad) - Settings must be reproducible to lt 20 mm
- Vacuum is manageable (for C Tlt50C, small
surface, good outbaking) - Local e-cloud is manageable (installing clearing
electrodes, solenoids?) - Collimators can be serviced and exchanged in
high-radiation area - Downstream equipment is OK for considered cases
- Reliability must be sufficiently good
-
- Impedance is manageable ( 110 MO/m) for the
overall system - Operational tolerances (orbit/beta beat) are
manageable - Cleaning efficiency is sufficient
- Loss rates are acceptable (no quenches,
acceptable background)
- Choice of appropriate technology (O. Aberle) and
impedance (F. Ruggiero).
7Presentations
- Several 10 min presentations on particular
aspects of LHC collimation followed by the
proposal - Energy desposition in different materials (V.
Vlachoudis) - Mechanical robustness, choice of material, and
mechanical design (O. Aberle) - Vacuum issues for the collimator jaws (N.
Hilleret) - Impedance issues (F. Ruggiero)
- Proposal (R. Assmann)
8Proposal
- R. Assmann
- for the
- Collimation Team
9Basic constraints
- Have a collimation system produced and installed
for 2007, with a reasonable cost. - The system must be a robust and flexible tool for
operation. - Nominal performance must be achievable.
- The layout of cleaning insertions must be
finalized by the end of 2003.
10Guiding principles
- Most rapid advancement by
- pursuing most simple solutions.
- avoiding additional concerns like toxic
materials (at least for initial installation). - minimizing changes with respect to V6.4
collimation system. - selecting designs where we have experience at
CERN (e.g. LEP). - introducing flexibility into the design (solve
some problems later).
11How to achieve this?
- Specialized sub-systems targeted at specific
purposes instead of one general purpose system. - Stage collimation system over 4 more years (RD,
production, installation, cost, ). - Minimum cost, maximum robustness start-up systems
with placeholders for upgrades (fewer
components). - Additional upgrade phases for nominal performance
(more components).
12Imagine collimation as a game of golf
- You can do it with one club only. However, if
you want to win you better have more than one
club - Best chances to win the collimation game with
specially adapted, specialized sub-systems. - More effort to understand what club to use for
what. - However, easier and better playing (operation)
though there are more collimators.
13The collimation clubs
- Maximum robustness, minimum cost IR3/IR7
collimation system (C) for injectionramping,
commissioning, early physics (running at
impedance limit). Thin metallic coating for going
further (survival of coating unclear). - Tertiary collimators in IR1, IR2, IR5, IR7 for
local protection and cleaning at the triplets. - Thin targets for beam scraping.
- Metallic hybrid secondary collimators in IR7
for nominal performance, used only at end of
squeeze and stable physics. - Additional placeholders for upgrading to maximum
cleaning efficiency.
Phase 1
Phase 2
Phase x
14Phase 1 The robust 3-stage system for
injection/ramp and early physics
TCDQ inj, 7 TeV (squeezed)
Primaries at inj, 7 TeV (squeezed)
Secondaries at 0.45 7 TeV (unsqueezed)
Secondaries at 7 TeV (squeezed)
Tertiaries at 7 TeV (squeezed)
Cu
C
Triplet
C
C
C
13.5 s
10 s
13.5 stop
8 mm (7 sinj)
2 mm (10.5 stop)
6 s
13 stop
- 10 s
- 13.5 s
C
C
C
C
Cu
Triplet
100 cm
100 cm
20 cm
10 m
100-150 cm
Primaries very robust, robust low-Z secondaries,
relaxed tolerances mechanical and for orbit/beta
beat, good efficiency. Space allocations for
phase 2 upgrade. Triplet protection (possible
later local cleaning at triplets).
15Phase 2 The robust 3-stage system plus low
impedance hybrids
TCDQ inj, 7 TeV (squeezed)
Primaries at inj, 7 TeV (squeezed)
Secondaries at 0.45 7 TeV (unsqueezed)
Secondaries at 7 TeV (squeezed)
Tertiaries at 7 TeV (squeezed)
Metal
Metal
Cu
C
C
C
C
Triplet
13.5 s
10 s
1.5 mm (7 stop)
10 stop
8 mm (7 sinj)
6 s
10 stop
8 mm (7 sinj)
Metal
- 10 s
- 13.5 s
C
C
C
C
Triplet
Cu
Metal
100 cm
100 cm
100 cm
100 cm
20 cm
10 m
100-150 cm
A few hybrid collimators (1-2) might be
retracted to 10.5 s (into shadow of TCDQ). Take
into account known phase advances for any given
configuration. Hybrid secondaries with metallic
surface, only used towards end of squeeze and in
stable physics (only dump failure relevant for H
collimators in phase). Rely on local triplet
cleaning for these few collimators.
16Efficiency for different solutions
Efficiency at 10 sigma (7 TeV) roughly the same
as with the Al/Cu system! Larger impact
parameters (results in larger tolerances).
17Required lengths of low Z jaws
- Keep secondaries (0.5 m Cu) and vary material and
length of primary collimators! - Choose 0.2 m C for primary collimators and vary
material and length of secondary collimators!
Observations Win factor two for 0.2 m graphite
(C)! Stay with 0.2 m length for primary
Observations Secondary C collimators of 1 m
length will restore the cleaning efficiency of
the old system.
C system 0.2 m and 1.0 m jaws!
R. Assmann, J.B. Jeanneret
18Why running at the impedance limit?
We must choose
- Maximum robustness, e.g. C
- run at impedance limit
- limit beta
- If limit is violated
- Dump of unstable beam
- Low impedance, e.g. Be
- run at robustness limit
- limit beam intensity
- If limit is violated
- Damage to Be jaw, possible
- contamination
or
Our solution Choose a maximum robustness system
(reliable and robust tool). It will
last. Complement with metallic triplet
collimators (protection and local
cleaning). Complement with thin metallic
coating. Upgrade with hybrid metallic
secondary jaws, only used in stable conditions.
19System summary
- Phase 1 (2007-2008)
- Injection optics Settings 6/7 s.
- Squeezed optics Settings 7/10.5 s.
- Tightest tolerances at collimators relaxed by a
factor 3. - Impedance OK for 50 nominal intensity.
- Minimum beta 0.85 m. (loose factor 0.85/0.55
1.6) - Maximum luminosity reach 16 (25 ns) (with
factor 4 from half bunch intensity) - Hope to gain further on impedance Modified
optics. - Options to go beyond
- Use 10 mm Cu coating if still existing (gain
factor 5 in impedance, go to nominal 6/7 s
settings). Problem Coating might not survive
(further studies)! - Use local cleaning at triplets for smaller beta.
Problem Generation of background in the
experiments. - Use metallic hybrid collimators of phase 2.
Likely need to rely on this. - Far future, if required
- Upgrade for best possible cleaning efficiency,
using placeholders in optics.
20Our proposal
- Consider phase 1 collimation as new baseline for
all further work. - Start detailed engineering of Phase 1 and
finalization of LHC optics and layout now. - Rely on LEP experience for the mechanical design
choices. - Start detailed studies on efficiency, machine
protection, beam loss, radiation, operational
studies for the new baseline in September 2003. - Authorize RD for phase 2 collimation to support
a later decision on implementations beyond Phase
1.
21Questions
- Is this staging concept reasonable and should be
pursued? - Are all the components for phase 1 accepted
(IR3/IR7 collimation, tertiary collimators,
scrapers)? - Is the reduction in number of components in IR7
accepted, reducing the cleaning efficiency to
that of V6.4 collimation? - Are the imposed limitations acceptable for the
LHC commissioning and early running? - Can we start the further work with the proposed
schedule?