Northeast Utilities Senior Design Project - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Northeast Utilities Senior Design Project

Description:

Mapped all substations onto a Connecticut site map ... Berlin. 0.9967. Bokum. 1.0254. Haddam. 10. 11. Impedance. Impedance varies with distance. ... – PowerPoint PPT presentation

Number of Views:53
Avg rating:3.0/5.0
Slides: 26
Provided by: engrU
Category:

less

Transcript and Presenter's Notes

Title: Northeast Utilities Senior Design Project


1
Northeast Utilities Senior Design Project
Michael A. Gargano (Overview) William H. Morrison
(Theory) Rodney Plettner (Software) Mark Pacileo
(Mapping) Advisors Rajeev Bansal and Steven Boggs
2
Project Goals
  • Enable NU to select substations pairs for
    immediate parallel operation
  • Derive trends from project data for general
    parametric analysis
  • Provide NU with analysis for future substation
    construction

3
Practical Application
4
Procedure
  • The load-flow software will be installed on UConn
    computers
  • Build a scaled version of the 115kv NU
    transmission/substation system
  • The Team will conduct a load-flow analysis study
    of the 107 substations on the 115kv system

5
Whats Been Done
  • So far we have
  • We have assimilated the 75 pages of NU data into
    Excel
  • Mapped all substations onto a Connecticut site
    map
  • Begun identifying possible substation pairs
    through specific parameters

6
Constraints and Restrictions
  • Distribution Voltages must be on the same
    per-unit base
  • Transmission system must be whole and fully
    operational
  • Vector distance between subs not to exceed 30
    miles
  • Delta-Wye substations will not be tied
  • 115 kv and 69 kv systems are one system
  • No ties to other Utility Owners

7
Parameters of Interest
  • Current thru TRs and SRs
  • Phase Angle
  • Line Impedance
  • Transformer Impedance
  • Substation Load
  • Tap Changers (on Transmission side)

8
The Per-Unit System
  • Makes calculations easier
  • Focuses on actual changes in a system
  • The system that almost all power engineers use
  • If a system is a 13.6kV system and the actual
    voltage is 13.78kV, then the per-unit value is

9
Examples of Per Unit Values
10
(No Transcript)
11
Impedance
  • Impedance varies with distance.
  • Reactive part increases with distance
  • Impedance changes depending on line
    configurations
  • Due to this we have a limit of 30 miles

12
Phase Angles
  • The reactive elements of the network determine
    the phase angle
  • Differences in phase angles between substations
    will result in a voltage differential
  • If the phase angle difference is too large and
    the distribution line impedance is too low, too
    much current will flow

13
Examples of Phase Angles
  • Mansfield to Glenbrook
  • Mansfield is 75.88
  • Glenbrook is 116.44
  • Difference is
  • 40.56
  • N. Canaan to Salisbury
  • N Canaan is 99.4
  • Salisbury is 98.02
  • Difference is
  • 1.38

14
Load Flow Analysis
  • Software to be used and how
  • Power Flow Software
  • Power System Simulator for Engineering (PSS/E)
  • Designed by Power Technologies, Inc
  • Used by North East Utilities
  • Why not Matlab or Pspice?
  • Time/Modification of data
  • Not specifically designed for utility simulation

15
Load Flow Analysis cont.
  • Software to be used cont.
  • Ordered PSS/E from PTI
  • Due to security clearance we will use PSS/E at
    Uconn
  • Will arrive before spring semester 2003
  • How will we use the software?
  • Data gathered for 115KV system
  • Actual transformer, load and phase angle values
  • Other various parameters
  • Data evaluated graphically

16
(No Transcript)
17
How will we use the data?
  • Build power models
  • Transformers
  • Loads
  • Tie reclosers
  • Sectionalizing reclosers
  • Enter actual substation parameters using GUI
    (graphical user interface)
  • Run simulation on substation pairs

18
After the Simulations
  • Know the current through tie reclosers
  • Produce a list of possible substation pairings
    for future reference by NU

19
115kV Substations
  • 107 NU substations
  • Without restrictions 5671 combinations

20
Limitations
  • Substations must have same base voltage
  • Vector distance must be less than or equal to 30
    miles
  • Line distance approximately 10 longer because
    there is no distribution along highways
  • Allowable current through a tie recloser is 50
    Amps

21
Litchfield County
13.2kV Distribution Voltage
22
(No Transcript)
23
Substation Pairs
24
Conclusion
  • This study will enable NU to
  • Pick substation pairs for immediate parallel
    operation for particular outage situations
  • Provide valuable information for future
    substation construction and location via general
    study

25
?
Write a Comment
User Comments (0)
About PowerShow.com