Acquisition of hardware, software and management of contracts and agreements ... Status Report to be presented to Cabinet & PCC in November 2005 ... – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 49
Provided by: Edw8
Category:

less

Transcript and Presenter's Notes

Title: Social Security Agency Presentation to Portfolio Committee


1
Social Security Agency Presentation to
Portfolio Committee
19 October 2005
2
Outline Of Presentation
  • Background
  • The Journey Map
  • SASSA STATE OF READINESS
  • Key Milestones
  • Legislation
  • Staff Issues
  • Leadership
  • Funds
  • Processes Operations
  • ICT Infrastructure
  • Office Facilities
  • Stakeholders Beneficiaries
  • PROGRESS REPORT
  • Governance Framework
  • Key Strategic Priorities
  • Key Strategic Themes
  • Conclusion

3
Background
  • Providing social assistance grants is a key
    government poverty alleviation program, ensuring
    income support to over 9.8 million vulnerable
    individuals.
  • The Agency is a Schedule 3(a) public entity
    responsible for administration and payment of
    social grants.

4
Background - Vision
  • To ensure a better quality of life for all South
    Africans by providing world-class social security
    services

5
Background - Mission
  • To administer quality social security services,
    cost effectively and timeously using appropriate
    best practices by
  • Developing and implementing policies, programmes
    and procedures for an effective and efficient
    social grants administration system
  • Paying the right grant amount, to the right
    person, at the right time and at the most
    convenient place
  • Delivering innovative, cost effective and
    efficient services to individuals, their families
    and community groups.

6
Background - Core Values
  • Promotion and protection of human dignity
  • Confidentiality
  • Integrity
  • Fairness
  • Transparency
  • Equitability

7
The Journey Map
  • Three distinct phases constitute the journey map
  • Initial phase prior to April 2005 and was
    concluded with MOU signing and introduction of
    the conditional grants - completed
  • Transitional Phase started April 2005, ending
    April 2006. Involves making the Agency
    operational and prepare for function transfer
  • Optimisation phase
  • Full operationalisation follows the transfer of
    the social grants function to the Agency and,
  • Implementing the new delivery model with radical
    improvements in the quality of delivery

8
The Journey Map
  • Defined the Day One Readiness Framework
  • Defined the minimum expected objectives to be
    achieved on DAY One of SASSA - 1 April 2006
  • Developed the Journey Map with key outputs and
    milestones to achieve on Day One
  • Allocated the outputs and milestones to
    Workstreams
  • Aligned work stream charters plans to Journey
    Map
  • Aligned status reporting process to Journey Map

9
SASSA State of Readiness Framework
  • SASSA readiness will involve the consolidation
    and completed preparation of the business pillars

Legal
Finance
HR
ICT
Change comms
Service Delivery
Facilities
Regions
10
SASSA State of Readiness - Day One
  • Day One Readiness is defined by the following
    ten objectives that need to be achieved by 1
    April 2006
  • 1. The service provider contracts are agreed with
    NDoSD, ceded or renewed, and operations aligned
  • 2. Critical regulations are promulgated and
    institutional arrangements are in place
  • 3. Critical staff are appointed and trained
  • 4. Key leadership team appointed performance
    compacts signed
  • 5. Funds for the establishment budget and
    2006/2007 budget are transferred

11
SASSA State of Readiness - Day One
  • 6. Critical processes policies are implemented
    within the governance reporting frameworks
  • 7. Critical ICT systems infrastructure for
    SASSA operational
  • 8. SASSA employees are settled in offices by
    28/02/2006 (whether interim, permanent or
    existing employees)
  • 9. SASSA expectations are communicated to
    stakeholders, beneficiaries and employees
  • 10. SASSA brand established and SASSA launched

12
Key Monthly Milestones
SASSA ready
Day 1
Day 1 State
Sept
Oct
Nov
Dec
Jan
Feb
Mar
Service providers contracts listed
Contracting Strategy approved planned
Contracting renewal MoU discussions started
Contracts renewed or ceded or MoUs signed
Service provider operations aligned
SASSA verified alignment of service provider
operations
Service providers briefed on future expectations
Service Providers contracts agreed with NDoSD,
ceded or renewed, and operations aligned
Critical Regulations defined
Institutional arrangements defined planned
Critical Regulation changes effected
Critical Regulations promulgated
Stakeholder consultations re regulations
Institutional arrangements verified
Shareholder agreements signed
Critical regulations promulgated Institutional
Arrangements in place
Organisation Structure approved
Critical Staffing plan approved positions
advertised
Critical staff screened interviewed
Staff transferred from provinces disputes
settled
Critical staff appointed
Staff trained
Day 1 Staff Contingency planned
Critical staff appointed and trained
Skeleton executive positions advertised
HO CXOs appointed
Top management appointments continued
HO SMs regional CXOs appointed
Regional SMs appointed
Leadership Alignment workshops SASSA Vision
Strategy
Leadership performance contracts signed
Skeleton leadership team appointed performance
compacts signed
Establishment budget submitted
Establishment funds transferred
SASSA 2006/2007 budget approved Re-allocation of
HO funds
Re-allocation of RO funds
Registration for levies
2006/2007 budget loaded
Trial balance signed off preparations
Funds for Establishment budget 2006/2007 Budget
transferred
Policies approved
HO admin functions established To-be Procedures
drafted
To-be procedures reporting formats approved
Detail process, policy procedure implementation
plans
Functions separated
Governance reporting frameworks in place
Policies actioned
SDI strategy approved Final Readiness
Verification
Mission critical processes policies actioned
within Governance reporting frameworks
HO RO system requirements approved decisions
finalised
HO transversal systems, Socpen and Support in
place
Regional infrastructure critical system
migration started
Regional transversal systems Socpen systems
ready
Regional systems operational infrastructure in
place
SASSA users trained
ICT improvement recommendations submitted
Critical ICT systems infrastructure for SASSA
operational
Office premises identified agreed
Occupation dates agreed Office migration strategy
Detail migration plan Preparation completed
Office Migration started
Office migration completed staff settled
Freeze on Office moves
Freeze on office moves
SASSA staff settled in offices by 28/02/06
(whether interim, permanent or existing)
Stakeholder beneficiary Engagement planned
HO internal comms capacity change network in
place
HO External comms capacity in place
Migration objectives communicated
Appointments communicated
Readiness expectations communicated
SASSA vision strategy communicated
SASSA expectations communicated to stakeholders,
beneficiaries staff
Service provider RFT issued
Service provider appointed
Brand, PR/marketing strategy plan, Visual
Identity Approved
Corporate Identity established
PR marketing continued
PR marketing continued
SASSA launched
SASSA Brand Established Launched
Version 2.0 Finalised Journey Map for Alignment
of Regional and Work Stream Plans
Last edit date 10/10/2005
13
Legislation
  • Statutory and Regulatory NDoSD is in the
    process of finalising the specific regulations
    require
  • Litigation NDoSD is managing a process of
    evaluating the extent of and impact of litigation
    on social security
  • Governance the relevant governance frameworks,
    instruments structures and institutions required
    are being identified and established

14
Staff Issues
  • H/O Organisation Structure has been finalised
  • Most of the Regional Office Organisation
    Structures have been approved
  • Job evaluations 90 complete
  • Key staff positions on the organisation
    structures have been identified if need be can
    still absorb support staff if transferred from
    the provincial departments

15
Staff Issues
  • Recruitment of the key management and operational
    positions has commenced
  • Existing NDoSD Employment Terms and Conditions
    will be used in the interim period
  • Persal is being configured to enable new staff to
    be captured on the system
  • Migration strategy for provincial staff to be
    finalised by NDoSD 11 November 2005 major
    dependency

16
Leadership
  • SASSA strategic plan developed awaiting
    finalisation
  • Most H/O Executive posts filled
  • Regional Executive Management Positions
    Advertised
  • H/O and Regional Office General Management and
    Senior Management positions advertised

17
Funds
  • Developed Funds Flow Proposal and ready for
    Treasury approval
  • Developed proposed Budget Structure and Standard
    Chart of Accounts
  • Decision to remain on BAS as the SASSA financial
    system until implementation of the ERP
    implication need to remain on cash accounting
  • Are applying for permission to remain on cash
    accounting for the next financial year
  • Financial Ring Fencing of Assets and Liabilities
    not yet complete in all provinces

18
Funds
  • Finalising the SASSA establishment budget and
    will submit to NDoSD by end of the month
  • Process of refining the FY06/07 operating budget
    in line with the strategic plan
  • In process of applying for listing as a Schedule
    3A entity with National Treasury
  • In process of finalising required registrations
    e.g. SARS, UIF, etc

19
Processes - Operations
  • Delegations were finalised for all SASSA
    functions and submitted to Exco for approval
  • Establishment of H/O support functions (Finance,
    IT HR) to be fully operational by 31/10/05
  • Provinces completed the Operational Ringfencing
    Checklists and submitted to H/O
  • The policies to roll out to regions were approved
    for Finance, HR IT

20
ICT Infrastructure
  • Procedures to roll out to regions were drafted
    for Finance, other functions on track to be
    completed by 30/11/05
  • Critical systems (BAS, Persal, Logis) will be
    operational at H/O by 28/10/05
  • The provincial assessments were completed, and a
    another round to refine the assessment is planned
  • A detail plan is being developed in order to
    assess the feasibility to migrate from Walker to
    BAS in North West province before Day 1

21
Office Facilities
  • SASSA H/O refurbishment and IT infrastructure is
    in place
  • In the process of finalising the agreements for
    regional offices

22
Stakeholders Beneficiaries
  • Stakeholder Communications
  • Stakeholder map developed
  • Internal Communication plan created
  • Stakeholder Engagement, Leadership Alignment and
    Communication Approach developed
  • Communication Strategy presented at Guiding
    Coalition

23
Change Management
  • Change Management
  • Change Agent network requirements confirmed and
    template developed for HOSSs
  • Need for change agents positioned with HOSSs
  • Change Management overview presented at Guiding
    Coalition
  • Agenda for Change Agent mobilisation session
    developed and approved and will be distributed
    soon
  • Received draft Terms of Reference for Change
    Management Tender
  • Editorial process created with regard to the
    development, printing and distribution of the
    SASSA Update

24
Governance Framework
  • In terms of the governance arrangements, progress
    includes
  • The Agency Act and Social Assistance Act will be
    in force by March 2006
  • MOU governs the transitional period, but a
    Business Partnership Agreement was drafted for
    post April 2006
  • Reporting framework in terms of Agency Act and
    the relevant PFMA sections has been finalised
    National Treasury
  • An Advisory Panel was established with members
    from the public and private sector and
    international experts to advise the Agency
  • A Panel of Ministers and Directors General has
    been established
  • National Department in the process of rolling out
    structures and staff for oversight responsibility

25
Key Strategic Priorities
  • Key Performance Areas are
  • Service delivery quality
  • Grant process integrity
  • Financial Management
  • Management of Payment Contractors
  • Minimization of fraud
  • Organizational capacity

26
Key Strategic Themes
  • Ensure a High Performance Institution
  • Service Delivery Improvement
  • Good Governance
  • Building Human Capital
  • Sound Financial Management

27
Ensure a High Performance Institution
  • Create/Establish a High Performance Institution
  • Business Continuity Transition Plan
  • Establish offices
  • Staffing recruitment, migration and change
    management
  • ICT systems/enablers established and in place
  • Organisational Structure implemented
  • Policies, processes, delegations finalised
  • Contracts reviewed, ceded and new contract
    management frameworks established
  • Financial Administration in place and funds
    transferred
  • Brand established

28
Ensure a High Performance Institution
  • Develop and operationalise high performing,
    efficient effective institution
  • Implement and integrate a high performance system
    and culture
  • Enhance all policies and procedures
  • Implement Communications Strategy
  • Governance Framework of co-operation

29
Ensure a High Performance Institution
  • Consolidate a high performance institution
  • Develop consolidation processes with strategic
    review
  • Aligned with other outputs (consolidate through
    reviews evaluate, consolidate position and
    re-align)
  • Ensure Agency compliance with legislative
    mandates
  • Development of uniform training programmes that
    address compliance
  • Implement Training Programme
  • Setting up structures (RR) to match compliance

30
Service Delivery Improvement
  • Improve administration of social security in a
    manner that meets stakeholder expectations
  • Design and implement strategy for back office
    integration, including ERP system
  • Roll-out priority ICT systems
  • Complete revenue and debt management strategy
    and commence implementation
  • Develop options for alternative service delivery
    models with other partners
  • Commence data improvement quality programme
  • Effective forecasting model

31
Service Delivery Improvement
  • Improve delivery of social security in a manner
    that meets stakeholder expectations
  • Implement norms and standards
  • Piloting of Service Delivery Model and commence
    implementation
  • Design and introduce standardise contracts and
    guidelines
  • Optimise (incrementally) infrastructure to
    improve access to social assistance
  • Develop customer relationship strategy
  • Introduce call centres
  • Develop customer charter for beneficiaries

32
Good Governance
  • To ensure a culture of integrity
  • Align policies and procedures with relevant
    legislation
  • Develop a communication strategy
  • Develop a complaints mechanisms
  • Appeal mechanism

33
Good Governance
  • To ensure good corporate governance
  • Develop fraud prevention strategy and commence
    implementation
  • Implement structures, systems and procedures in
    line with legislation, King Report on Corporate
    Governance and state owned entity protocols
  • Develop a code of conduct and ethics
  • Strengthening partnership and collaborations
  • Develop maintain risk management plan

34
Building Human Capital
  • To recruit, develop, and retain skilled competent
    employees
  • Develop and Implement compliant HR Strategies,
    Policies and processes
  • Implement job competency profiles linked to new
    Service Delivery model
  • Develop new Induction and Performance Management
    System aligned to Organisational Performance
    Model
  • Design and implement an optimal HR planning,
    training and development strategy
  • Develop and implement a Remuneration Strategy

35
Sound Financial Management
  • Improve financial administration
  • Complete revenue and debt management strategy
  • Commence implementation of financial accounting
    policies and systems
  • Delegation of Authority in place
  • Budget structure and SCOA for transfers and
    operations

36
Programme 1 Corporate Services
  • Management (Office of CEO)
  • Overall Strategic Management of the Agency
  • Regular reports to principal stakeholders
  • Human Capital Management
  • Human Resource Strategy and Policies
  • Implement new Performance Management System
  • Capacity building based on HR development
    strategy
  • Office Services
  • Provision of office services
  • Finalised policies, processes, delegations for
    office services

37
Programme 1 Corporate Services
  • Communication
  • Develop a communication strategy, including
    mechanism for stakeholder redress and complaints
  • Provincial Operational Support
  • Development of effective Management Structure
  • Contracts ceded, and new contract management
    frameworks established
  • Develop Code Of Ethics
  • Corporate Governance Structures of corporate
    governance established
  • Change Management Change management implemented

38
Programme 2 Service Delivery Assurance
  • Internal Audit
  • Quality Internal Audit reports on risk management
    and control
  • Quality Internal Audit reports on governance
    processes
  • Risk and Fraud Management
  • Promotion of good corporate governance
  • Culture of integrity is promoted
  • Complete fraud prevention strategy and commence
    implementation

39
Programme 3 Finance
  • Financial Accounting and Administration
  • Finalise the transfers of Budgets, Assets
    Liabilities
  • Financial capacity in place
  • Financial accounting policies and systems
  • Delegation of Authority
  • Budgeting and Reporting
  • Budget structure and SCOA for transfers and
    operations
  • Funds flow model finalised

40
Programme 3 Finance
  • Procurement and Contract management
  • Monitor review the management of the contracts
    for Service Delivery Payment Contractors
  • Procurement policies implemented for suppliers of
    goods and services
  • Contract management strategy and plans
  • Develop the outsourced model for non-core
    services
  • Risk Management
  • Develop Risk Management plan applicable to Finance

41
Programme 4 Information Technology
  • Systems Development
  • Implement ERP systems
  • Automate Grants processes (ECM)
  • Implement Data warehouse
  • Socpen Replacement
  • Implement a CRM solution

42
Programme 4 Information Technology
  • Information Management
  • Implementation of e-Government and portal
    services
  • Implementation of a Business Intelligence (BI)
    solution
  • Provision, utilisation and management of
    information as a strategic resource that ensures
    realisation of the business objectives

43
Programme 4 Information Technology
  • IT Operations
  • Enhancement and Maintenance of SOCPEN and
    Provision of information technology solutions
  • Implementation of interim ERP system (BAS,
    PERSAL, LOGIS)
  • Maintenance of Network Hardware and software
  • User support and service management
  • Acquisition of hardware, software and management
    of contracts and agreements

44
Programme 4 Information Technology
  • IT Governance and Architecture
  • Develop governance plan Development and
    Implementation of the Master Information Systems
    Plan
  • Development of Enterprise IT Architecture,
    principles and standards
  • Develop and implement IT organizational structure
  • Develop IT Security plan and Risk Management
    Plan (BCP)

45
Programme 5 Service Delivery
  • Improve delivery of social security services in a
    manner that meets stakeholder expectations
  • Improve service delivery to restore the dignity
    of beneficiaries
  • Design and introduce standardised contracts
  • Optimise infrastructure to improve access to
    social assistance
  • Customer relationship strategy
  • Introduce call centres
  • Develop customer charter for beneficiaries

46
Programme 6 Strategy and Business Development
  • Strategy formulation
  • Institutional Policy and strategy formulation
  • System of Reporting in place
  • Corporate Governance
  • Structures of corporate governance established
  • Corporate Governance policy guidelines
    implemented

47
Programme 6 Strategy and Business Development
  • Innovation and Change Management
  • Research and development
  • Monitoring and evaluation
  • International and national liason
  • Collaboration at international and national level
    for exchange of best practices and to explore new
    business opportunities

48
Conclusion
  • Status Report to be presented to Cabinet PCC in
    November 2005
  • Consultative process with Provinces has been
    initiated
  • Agency is working on ensuring State of Readiness
    by 01 April 2006
Write a Comment
User Comments (0)
About PowerShow.com