BUILDING INSPECTION WORKSHOP
  • Excavation Readiness To Construct Footings

2
AGENDA
  • Notification
  • Project Review
  • Undisturbed Soil
  • Minimum Depth
  • Compacted Fill Part 4 Designed
    Footings/Foundations
  • Form Layout Setbacks
  • Footings
  • Precautions
  • Waterproofing
  • Termite Control

3
Notification
  • Notification to Building Inspection Division
    ResFax
  • Telephone 905-475-4850
  • Fax 905-415-7501
  • Notification of Inspection Request must be before
    100pm to receive a next day inspection
  • Reports do not substitute for inspections
    performed by the Building Standards Department
    building inspection staff

4
Project Review
  • Permit drawings on site E02
  • Ensure changes made to permit drawings are
    incorporated into project
  • Frost Protection Plan during cold weather to
    avoid freezing of the soil concrete
  • Not permitted to displace water within the
    footing with concrete pouring
  • Pour footings continuously, if not possible
    provide a proper joint with 2 reinforcement bars
    E22

5
Undisturbed Soil9.12.2.1
  • The Town of Markham Building Standards service
    level
  • Is limited to a visual inspection of the
    excavation
  • For conducting prescribed inspections does NOT
    include testing to determine the bearing capacity
    of soil for compliance with the building code
  • The builder, owner and the person to whom this
    permit is issued to, shall assure themselves,
    that the soil bearing capacity of supporting the
    loads imposed from the proposed building and that
    the Town of Markham may not b relied on to
    certify soil properties
  • Footings on solid, clean unfrozen ground E12,
    E14, E15, B0820
  • 9.12.1.3
  • Geotechnical engineer confirming design net
    bearing pressure of soil
  • Excavation free of standing water E08, E25
  • 9.12.1.2
  • Bottom of excavation free of organic material E09
  • 9.12.1.1
  • Professional engineer report where high ground
    water level is suspected or water at the bottom
    of the excavation cannot be accounted for

6
Minimum Depths
  • Elevation of footings are minimum 1.2 m below
    finished grade level provide the proper frost
    protection cover E16
  • Ensure depth of footings has accounted for drains
    serving rear yard catch basins that the drains
    dont undermine the footings or are within the
    angle of repose E17
  • Excavation inspection of deck post footings
    required

7
Compacted Fill Part 4 Designed
Footings/Foundations
  • Submit professional geotechnical engineer
    reports
  • Confirming compacted granular fill
  • Confirming compacted fill capable of supporting
    the net bearing pressure
  • Part 4 designed footings/foundations, i.e. Piles,
    grade beams, etc. (28), (27)

8
Form Layout Setbacks
  • Footing form layout in accordance with permit
    plans E18, B0830, B0840
  • If setbacks are suspect , a survey from an
    Ontario Land Surveyor (O.L.S.) will be required
    E19

9
Footings
  • Confirm size, depth and design of strip footings
    E18
  • Column pad thickness greater than strip footings
    E20
  • Stepped footings have proper vertical rise
    horizontal distance between risers E21
  • Reinforcement has been placed at the location
    where drains pass under the footings E23
  • Sleeves used in forms for weeping tiles E24
  • Footing thickness conforms to permit plans
  • Bottom of excavation within the footing forms is
    cleaned of loose debris, soil water E06
  • Angle of repose of the soil critical for existing
    footings and are affected by new excavations, the
    footings foundations must be designed by a
    professional engineer E07

10
Precautions
  • Watch for excavation damage to services
    adjacent property, including public property
  • Fencing hoarding installed when constructing
    adjacent to an occupied property E29

11
Waterproofing
  • Consider the cause of wet conditions, if
    waterproofing is required submit a report from a
    professional engineer E30, (2)

12
Termite Control
  • Certain areas of Markham are termite infested,
    check with your building inspector for required
    termite control action to be taken E31