Title: Wanted
1Wanted!
WANTED ALIVE!
Professional Building-Owner Representative
for Construction Management
Dr. Patrick Wenzel, HAYEK ENGINEERING AG, Zürich
2Challenges to Airports
- Steady Growth-Rates in Air Transportation
- Formation of Airline Alliances
- Concentration of Traffic Patterns
- Future Large Aircraft
- Privatization of Airports
- ...
Each one of these factors produces its very own
set of new requirements!
3Functional Specification
A successfull functional specification must
consider the specific requirements of the most
important user groups. These
- Passenger
- Concessions
- Service Provider
- Authorities and Security Services
- Citizens
4Economical Requirements
- Fast Return on Investment
- Balance of Capacity
- Flexibility
- Modularity
- Expandability
5Meeting the Challenge
In order to successfully manage an
airport-expansion project, the project manager
must
- be objective and independent
- be loyal and reliable
- act, as if the project was his own
- have extensive know-how and experience
6Timeline
Project Definition
Architectural Design Competition
Refinement Phase
Start of Project
?
Planning and Construction
1
2
3
4
5
6
7
8
9
10
7Awarding Contracts
Phased Issue
General Contractor
The investor splits the project into groups and
puts them out to tender
The entire project is completely handed over to
the General Contractor
Fixed Price
Fixed Completion Date
Low Management Effort
Time for Planning
Changes of Concept
Scope of Supply
Low Costs
High Quality
8Phased Issue
9Phased Issue
- Earthworks
- Construction Shell
10Phased Issue
11Phased Issue
- Baggage Handling Systems
- Security Screening Devices
12Phased Issue
- Movable Passenger Boarding Bridges
- Ground Power
- Pre-Conditioned Air
- Aircraft Guidance System
13Phased Issue
- Cladding
- Roof
- Exterior Doors and Gates
14Phased Issue
- Air Conditioning
- Heating
- Plumbing
- Electrical Power Distribution
15Phased Issue
- Telecommunication
- Hazard Warning
- Security Systems
- Passenger Information
16Phased Issue
- Floor Covering, Ceilings
- Dividing Walls and Interior Doors
- Painter
- Locksmith
17Phased Issue
18Timeline Realization
Project Definition
Architectural Design Competition
Refinement Phase
Start of Project
Planning Phase
Initial Tendering and Contracting
Construction Phase
Beginning of Operation
Contract Follow-up
1
2
3
4
5
6
7
8
9
10
19Project Structure
- Project Definition
- Project Draft
- Cost Estimate
Phase I
- Draft Planning
- Application for Building Permit
- Update of Cost Estimate
Phase II
- Implementation Planning
- Contracting
- Cost Calculation
Phase III
- Supervision Monitoring
- Project Handover
Phase IV
20Project Confirmation
Phase I
Phase II
Phase III
Phase IV
21Management Organization
22Management Organization
23Project Link
Terminal 2
Parking Garage
24Project Link
Facts about HAYEK ENGINEERING AG
- Swiss Engineering Company
- 40 Years of Experience in International Business
Consulting - Totally Independent and only committed to the
Customer - Full Service Provider
- Airport Experience
25Still Wanted?
HAYEK ENGINEERING AG Dreikönigstr. 21, CH-8027
Zürich Switzerland Tel 41 1 284 2626 Fax 41 1
201 2757 eMail p.wenzel_at_HAYEK.CH
Passenger Terminal EXPO 2000 20-22nd March
2000Stand 2008