Title: Quarterly update webcall on BT


1
Quarterly update webcall on BTs 21CN programme
Welcome to the
  • 26th October 09

BT's 21CN programme is subject to consultation
and further development. Dates and other details
should be treated as indicative only, and subject
to change
2
Agenda
21CN Deployment Strategy Plan (DSP) and key 21CN programme messages TDM trial of the initial stages of the agreed 2Mbit/s and above strategy
Pathfinder Volume POTS
Consult21 activities
QA and poll
Speakers Nigel Scott, Chris Basey, Bill du Cann,
Becky Hewlett
3
21CN Deployment Strategy Plan (DSP) - key
information changesNigel ScottBTW, Industry
Consultation
BT's 21CN programme is subject to consultation
and further development. Dates and other details
should be treated as indicative only, and subject
to change
4
21CN Deployment Strategy Plan (DSP) - intro
  • The DSP (C21-MG-015) was up-issued on 14th
    October 09
  • Incorporates the 21CN Product Plans and
    describes BTs plans for its next generation
    network known as 21CN.
  • Draws together BTs current view of its 21CN
    deployment plans, regulated product availability
    and voice migration plans on an exchange by
    exchange basis, including points of
    interconnection
  • Dates for Pathfinder Volume POTS are currently
    being reviewed
  • Includes a coherent story of voice and broadband
    customer network affecting activities and impacts
  • NB Available via the secure area of the
    Consult21 website - access is only available to
    BTs CP customers for access please email
    consult21_at_bt.com

5
21CN Deployment Strategy Plan (DSP) product
overview updates
  • IPstream and Datastream
  • Both are retained on the current broadband
    platform until their withdrawal from service (not
    migrated to 21CN)
  • Will be replaced by products that provide
    similar and enhanced end user functionality
    Wholesale Broadband Connect (WBC) and Wholesale
    Broadband Managed Connect (WBMC).
  • WBC
  • Now available at 568 sites
  • ADSL2 deployment being enhanced to enable
    faster upstream line speed. Indicative delivery
    date March 2010
  • Real Time is still on the product roadmap -
    indicative delivery date March 2010
  • DDQ requirement has been removed from the
    product roadmap
  • WBMC
  • WBMC consuming IPstream Connect was launched on
    30th September 2009

6
Wholesale Broadband Connect
  • Service available at end March 2009 to 40 of the
    UK (10m homes/businesses)
  • Service now reaching industrial end user scale
  • Plan is to increase availability to 55
    availability (an extra 302 exchanges) by March
    2010
  • First additional exchanges went live in August
    2009.

WBC rollout
By March 2009
By March 2010
7
WBC footprint expansion next phase intent
  • BT intends to rollout to 75 in 2010/11 -
    subject to wholesale customer demand
  • Plan extends to an additional 650 exchanges, c.
    20 million end users
  • Addressing majority of exchanges in Market 3 and
    extending significantly into Market 2
  • A range of possible rollout scenarios currently
    under consideration

8
Wholesale Ethernet
  • Service available from 600 nodes by March 2009
  • Plan to extend this to 800 nodes by March 2010
  • C. 700 by end Sept 09
  • C. 800 by end Dec 09
  • Remainder by March 2010

By March 2009
Shows nodes planned by December 2009.
9
21CN Deployment Strategy Plan (DSP) product
overview updates
  • MSIL
  • Continuing to develop a resilient offering for
    launch early 2010
  • 21CN PSTN Interconnect capability
  • Launch date is currently under review
  • Bilateral meetings with CPs taking place to
    understand requirements

10
Migration from NetVIEWplus to WCR (Wholesale
Customer Reporting)
WCR is the new reporting tool to replace the
Netview Plus system and will include 21CN product
measures. You will shortly receive more details
about this, including an invitation to attend a
Web Cast where you will see a live demonstration
of the WCR system and have the opportunity to ask
any questions you may have. We look forward to
your attendance on the forthcoming Web Cast and
to speaking to you all. In the meantime, if you
have any questions you would like to ask
beforehand, please do not hesitate to contact us
by e-mailing the WCR Team at btw.wcr_at_bt.com
11
Partial private circuits update TDM trial of
the initial stages of the agreed 2Mbit/s and
above strategyBill du CannTDM industry
consultation manager
12
21CN Deployment Strategy Plan (DSP) product
overview updates
  • BTW Partial Private Circuits (PPCs)
  • Sub 2Mbit/s PPCs
  • Sub-2Mbit/s TDM portfolio infrastructure
    strategy is being evaluated as part of a separate
    feasibility study.
  • We are investigating two main options
  • 1) Extending the life of the current 20C DPCN
    beyond the current stated closure date of 2014
  • 2) 21CN delivered options requiring the use of a
    sub 2Mbit/s NTE in conjunction with a 2Mbit/s
    circuit.
  • 2Mbit/s (and above)
  • BT Wholesales strategy for 2Mbit/s (and above)
    Partial Private Circuits is to retain the
    majority of its existing 2Mbit/s (and above) 20C
    PPC products and incorporate 21CN components over
    time to replace obsolete 20C network components.
  • PPC portfolio retains its existing framework
    i.e. Points of Handover (POH) and will continue
    to use native TDM (SDH) technology.
  • Initial technical trial towards the end of BTs
    financial year 2009/10.

13
Trial description
VC4 phase 2 FOA (Internal BT) is planned to
complete 11/12. Network embargo from 14/12 /09
to 8/1/10 TDM demonstration is planned for Q4.
Dates to be finalised along with scope. The TDM
demonstration is being considered in two
parts 1. basic VC4 highway as below with testers
at each end 2. once 1 is proven, extend to CP
and route their circuits as below and test
performance
14
TDM trial details
  • The current proposed trial area is in Scotland
    (route between Edinburgh and Inverness)
  • A briefing has been issued asking CPs to register
    interest and to indicate the following
  • Preferred geographic area (with reasons)
  • Confirmation of existing services and access
    infrastructure
  • Preferred circuit types to test (speed,
    resilience, etc)
  • An update will be provided in due course
    however if you wish to participate please let us
    know

15
Pathfinder Volume POTS Network Upgrades
Chris BaseyPrincipal Consultant21CN PSTN/WLR
Transformation Programme
BT's 21CN programme is subject to consultation
and further development. Dates and other details
should be treated as indicative only, and subject
to change
16
Pathfinder Volume POTS a quick recap
  • Again voice migrations only
  • Will complete a further 7 DLEs in South Wales
  • - Cardiff, G, L, E, F, Bridgend, Cardiff B,
    Pontypridd
  • Will complete the migration of up to 350K voice
    lines
  • Will provide key learning following migration of
    a complete DLE in a night
  • Switched-on communications will be issued
  • Project plan being revised in line with customer
    input
  • MSAN upgrades in Pathfinder area will take place
    prior to Pathfinder Volume POTS
  • First Call Server upgrades have already been
    successfully completed in readiness
  • Second Call Server software drop being planned
  • Includes remigration of groomed/regressed lines
    (eg EPOS lines)

17
CMSAN upgrades required
  • The upgrade schedule for the CMSANs is being
    developed
  • There will be short voice line outages for end
    users 2 impacts
  • Upgrades will be performed in the early hours of
    the morning to minimise the impact
  • 25 of non-live sites will be upgraded before
    the first live site
  • Nelson will be the first CMSAN to be upgraded,
    followed by one weeks stability period

Cause Timing Experience Scale
MSAN upgrade-first impact. Between midnight 6am (10 mins elapsed time) Between 3am-5am, 5 minutes incoming outgoing call outage for all customers simultaneously non-critical calls in progress will be cut off. No Star Services freeze Only one MSAN Site will be completed per night.
MSAN upgrade -second impact On the same night between 1 and 30 mins after MSAN upgrade- first impact 2 minutes incoming outgoing call outage for all customers in batches of 5 linecards, successively, until all linecards have been upgraded. Non-critical calls in progress as a linecard is upgraded will be cut off. No Star Services freeze Impacts all end users on an MSAN site, in batches (max 320 at a time)
18
Migrations after Pathfinder Volume POTS
  • Voice line migrations will be done on an entire
    Digital Local Exchange (DLE) basis.
  • The pace and order of these will be determined by
    continuous review of the condition and capability
    of the current voice network and the pattern of
    demand for new voice services.
  • BT intends to start additional DLE migrations
    when the subsequent pilot Pathfinder phases
    involving Belfast, Thamesmead and Redditch have
    also been concluded.
  • This ensure the comprehensive proving of
    migration techniques
  • BT intends to provide a minimum of two years
    notice of DLE migration.
  • This means that voice line migrations to 21CN
    (beyond the DLEs listed for the pilot phases)
    will now occur no earlier than October 2011.
  • Migrations post Pathfinder Volume POTS will be
    available via the Datasets

19
Migrations after Pathfinder Volume POTS
  • Candidate list objective
  • To provide a view of probable customer migrations
    beyond Pathfinder Volume Pots.
  • Enable you to identify future migrations and
    impact on customers
  • Selection criteria
  • The criteria by which the sites have been
    selected ..
  • 20C obsolescence capacity performance
  • Where DLE Interconnect migration has been
    completed or underway
  • Maximise use of proven 21CN core network.
  • Confirmation of dates
  • At this stage, planned dates are not available.
  • As we confirm our plans and determine dates these
    will be announced
  • We maintain our commitment to provide a 2 year
    window for notification when customer migrations
    will take place at these candidate sites


these sites complete the Pathfinder proving
capability with dates yet to be confirmed, we
have included with Candidate list for
completeness.
20
ISDN
  • ISDN Strategy
  • BT is developing an ISDN like-for-like service
    to be deployed in line with the roll out of WLR
    services on 21CN
  • Huawei ISDN equipment will be tested in Northern
    Ireland - the trial will involve migration of all
    voice products (POTS, ISDN2 and ISDN30) on one
    DLE (Belfast East Unit B
  • Fujitsu ISDN equipment in the Pathfinder area in
    South Wales - the trial will involve the
    migration of ISDN services onto all nine DLEs in
    the Pathfinder area in South Wales that have
    already had their POTS services migrated
  • Two BT own-use ISDN trials as well as initially
    preparing Swansea for CP testing
  • CPs will be able to make use of the Swansea test
    facility from October 2009 and/or, if suitably
    located, one of the BT own-use sites for the
    voluntary trialling at an appropriate date
  • Delivery plans are currently under review

21
Key Consult21 engagement activities Becky
HewlettBTW Consult21 work stream lead
22
Consult21 headlines - latest news
  • IPstream EUA withdrawal consultation nearing
  • conclusion
  • Bilateral engagement continuing on
  • interconnect requirements
  • Industry discussions on timings of Pathfinder
  • Volume POTS and network upgrades continue
  • via IMWG
  • TDM 2Mbit/s and above trial
  • Reminder to opt-in to Consult21 distribution
    lists
  • to receive the latest information

23
Consult21 headlines - latest news
  • Next phase of voice line migrations Pathfinder
    Volume POTS
  • A further 7 DLEs in the South Wales area
  • We are inviting the CPs most affected to an
    event at the BT Tower
  • A chance to get up to speed on 21CN plans
  • A chance to see what practical help is available
  • Understand how to get engaged with the programme
  • Spaces are limited, if you receive an invite
    please
  • register early
  • We will be holding a further webcall in January

24
Useful information how to get engaged
  • More information?then contact helen.nurse_at_bt.com
  • Or visit these sites
  • The Consult21 website www.btwholesale.com/consul
    t21
  • The independent public information website
    covering the process of migration
    http//www.switchedonuk.org
  • For general information about BTs 21CN
    programme go to http//www.btplc.com/21CN/
  • If you have any hot topics for future 21CN
  • webcalls please email-
  • Consult21_at_bt.com

25
Questions
?
Answers
26

Please help us to improve future webcalls by
answering a few poll questions
27
Thank you for coming on the call