The Palmdale Fuel Cell Project: FiveYear Review - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

The Palmdale Fuel Cell Project: FiveYear Review

Description:

Parallel renewable combined heat and power projects using digester gas ... 250 kW Ingersoll-Rand microturbine at Lancaster. Palmdale Water Reclamation Plant ... – PowerPoint PPT presentation

Number of Views:63
Avg rating:3.0/5.0
Slides: 35
Provided by: serv521
Category:

less

Transcript and Presenter's Notes

Title: The Palmdale Fuel Cell Project: FiveYear Review


1
The Palmdale Fuel Cell Project Five-Year Review
  • SCAP Energy Management Committee Meeting
  • Mark McDannel
  • Los Angeles County Sanitation Districts
  • July 28, 2009

2
Presentation Overview
  • Facility Descriptions and Design Parameters
  • Results
  • Lessons Learned Conclusions

3
Antelope Valley Green Energy Program
  • Parallel renewable combined heat and power
    projects using digester gas
  • Similar size units at similar size plants
  • 250 kW Fuel Cell Energy molten carbonate fuel
    cell at Palmdale
  • 250 kW Ingersoll-Rand microturbine at Lancaster

4
Palmdale Water Reclamation Plant
STARTED NOVEMBER 1952 CAPACITY 15 MGD
CURRENT FLOW 9.2 MGD
5
Project Design Data
6
Palmdale Fuel Cell Project
  • Fuel Cell Energy molten carbonate fuel cell
  • Capital cost 2.4 million
  • 50 of cost recovered from SGIP

7
Fuel Cell Project Team
  • Quinn Power Systems Associates
  • Prime contractor
  • Operation and maintenance under contract to LACSD
  • Fuel Cell Energy-
  • Fuel cell supplier
  • Subcontracted to Quinn for fuel cell OM
  • SCS Energy-
  • Design and installation
  • Gas treatment skid om
  • Facility ownership retained by LACSD

8
Fuel Cell Fuel Skid
9
Load Profiles at Palmdale
10
Results
  • Plant Performance
  • Economics
  • Siloxane Removal
  • Lessons Learned Conclusions

11
Fuel Cell Availability and Capacity
12
Fuel Cell Availability and Capacity
  • Availability has increased during the program
  • Capacity has decreased despite improvements in
    availability
  • Capacity factor well below 90 target

13
Breakdown of Downtime
14
Palmdale Availability
  • Fuel cell balance of plant equipment
  • Routine repairs on water treatment system
  • Multiple significant fuel skid issues
  • Four electrode stack replacements
  • Carbon filter media replacement

15
Stack Replacements
  • Four stack replacements
  • 3975 hrs - Replaced with new stack design
  • 2696 hrs Stack degradation
  • 5386 hrs - Sulfur poisoning excessive
    startups
  • 9889 hrs - Sulfur poisoning

16
Causes of Capacity Reduction at Palmdale Fuel Cell
  • Frequent long time periods at reduced loads due
    to fuel cell issues
  • Variations in digester gas pressure due to issues
    with the fuel skid
  • Lower digester gas flows and higher methane
    content due to sewer cleaning
  • Defective stack installed in 2008

17
Causes of Capacity Reduction at Palmdale Fuel
Cell, ctd
  • Long start up times after outages
  • Parasitic Loads
  • Internal fuel cell loads of 18-20 kW not counted
    against net, but cost plant when fuel cell is in
    hot standby
  • Fuel skid, 25 kW (design value, not metered)
  • Three sulfur poisoning events have resulted in
    reduced power output for several months

18
Net Electrical Generation per Quarter
19
Other Issues at Palmdale
  • Integration into plant digester gas system
    including flare and boilers was complex
  • Remote monitoring and operation help minimize
    down time
  • Installation of natural gas line was necessary
    for backup and controlled shutdown

20
Capital Cost
21
Facility Economics (design, assuming 90 capacity
factor)
22
Cost of Power Production
23
Net Savings per Year
  • 2005 66,551
  • 2006 69,452
  • 2007 46,543
  • 2008 2,119

24
Cumulative Net Savings
25
Siloxane Removal
  • Carbon absorption
  • Also removes Cl, S to protect fuel cell
  • Requires periodic testing for breakthrough
  • Short term high siloxane levels could cause
    undetected breakthrough

26
Criteria Pollutant Emissions
  • NOX 0.05 ppm _at_ 15 O2
  • 0.0017 lb/MWh
  • CO 1.2 ppm _at_ 15 O2
  • 0.025 lb/MWh
  • TGNMO 2.07 ppm
  • 0.016 lb/MWh

27
Sulfur Compounds
Note-detection limit not sensitive enough to
fully protect fuel cell
28
Trace Organic Compounds
29
Recent Operating Status
  • Stack replaced in Sep 2008.
  • A leak in the new stack forced reduction in
    output to 40 kW in Dec 2008
  • Operated at nearly 100 availability at reduced
    load
  • Fuel cell was shutdown June 11 upon discovery of
    sulfur breakthrough
  • Unit will not be restarted

30
Lessons Learned by LACSD
  • Ambient temperature considerations
  • Chiller was undersized for high summer
    temperatures
  • Lower digester gas production during winter
    months
  • Carbon media must be monitored and/or replaced
    periodically
  • Site involvement
  • Digester gas system balancing

31
Lessons Learned by Fuel Cell Energy
  • Natural gas must be used as a backup fuel
  • A load bank should be installed to mitigate grid
    disturbances
  • Ensure proper maintenance of the fuel skid

32
Contracting Issues Impacting the Facility
  • These were demonstration projects as such,
    providers would not provide availability
    guarantees
  • The current OM contracts have no performance
    incentive or penalty down time costs the owner
    but does not cost the contractor
  • Fast response not always justified by plant
    economics
  • Other contracting options
  • Incentives and penalties for response time and
    availability
  • Power purchase agreement, unit owned by provider
    or third party
  • These options are generally currently available

33
Conclusions
  • The Palmdale fuel cell did not meet performance
    goals
  • The Palmdale fuel cell met its goal to
    demonstrate a high efficiency, low emission
    technology on digester gas
  • As an early adopter, Districts allowed
    manufacturers to address and resolve design and
    operating issues

34
Questions?
  • Contact information
  • mmcdannel_at_lacsd.org
  • (562) 908-4228 x2442
Write a Comment
User Comments (0)
About PowerShow.com