Title: The Palmdale Fuel Cell Project: FiveYear Review
1The Palmdale Fuel Cell Project Five-Year Review
- SCAP Energy Management Committee Meeting
- Mark McDannel
- Los Angeles County Sanitation Districts
- July 28, 2009
2Presentation Overview
- Facility Descriptions and Design Parameters
- Results
- Lessons Learned Conclusions
3Antelope Valley Green Energy Program
- Parallel renewable combined heat and power
projects using digester gas - Similar size units at similar size plants
- 250 kW Fuel Cell Energy molten carbonate fuel
cell at Palmdale - 250 kW Ingersoll-Rand microturbine at Lancaster
4Palmdale Water Reclamation Plant
STARTED NOVEMBER 1952 CAPACITY 15 MGD
CURRENT FLOW 9.2 MGD
5Project Design Data
6Palmdale Fuel Cell Project
- Fuel Cell Energy molten carbonate fuel cell
- Capital cost 2.4 million
- 50 of cost recovered from SGIP
7Fuel Cell Project Team
- Quinn Power Systems Associates
- Prime contractor
- Operation and maintenance under contract to LACSD
- Fuel Cell Energy-
- Fuel cell supplier
- Subcontracted to Quinn for fuel cell OM
- SCS Energy-
- Design and installation
- Gas treatment skid om
- Facility ownership retained by LACSD
8Fuel Cell Fuel Skid
9Load Profiles at Palmdale
10Results
- Plant Performance
- Economics
- Siloxane Removal
- Lessons Learned Conclusions
11Fuel Cell Availability and Capacity
12Fuel Cell Availability and Capacity
- Availability has increased during the program
- Capacity has decreased despite improvements in
availability - Capacity factor well below 90 target
13Breakdown of Downtime
14Palmdale Availability
- Fuel cell balance of plant equipment
- Routine repairs on water treatment system
- Multiple significant fuel skid issues
- Four electrode stack replacements
- Carbon filter media replacement
15Stack Replacements
- Four stack replacements
- 3975 hrs - Replaced with new stack design
- 2696 hrs Stack degradation
- 5386 hrs - Sulfur poisoning excessive
startups - 9889 hrs - Sulfur poisoning
16Causes of Capacity Reduction at Palmdale Fuel Cell
- Frequent long time periods at reduced loads due
to fuel cell issues - Variations in digester gas pressure due to issues
with the fuel skid - Lower digester gas flows and higher methane
content due to sewer cleaning - Defective stack installed in 2008
17Causes of Capacity Reduction at Palmdale Fuel
Cell, ctd
- Long start up times after outages
- Parasitic Loads
- Internal fuel cell loads of 18-20 kW not counted
against net, but cost plant when fuel cell is in
hot standby - Fuel skid, 25 kW (design value, not metered)
- Three sulfur poisoning events have resulted in
reduced power output for several months
18Net Electrical Generation per Quarter
19Other Issues at Palmdale
- Integration into plant digester gas system
including flare and boilers was complex - Remote monitoring and operation help minimize
down time - Installation of natural gas line was necessary
for backup and controlled shutdown
20Capital Cost
21Facility Economics (design, assuming 90 capacity
factor)
22Cost of Power Production
23Net Savings per Year
- 2005 66,551
- 2006 69,452
- 2007 46,543
- 2008 2,119
24Cumulative Net Savings
25Siloxane Removal
- Carbon absorption
- Also removes Cl, S to protect fuel cell
- Requires periodic testing for breakthrough
- Short term high siloxane levels could cause
undetected breakthrough
26Criteria Pollutant Emissions
- NOX 0.05 ppm _at_ 15 O2
- 0.0017 lb/MWh
- CO 1.2 ppm _at_ 15 O2
- 0.025 lb/MWh
- TGNMO 2.07 ppm
- 0.016 lb/MWh
27Sulfur Compounds
Note-detection limit not sensitive enough to
fully protect fuel cell
28Trace Organic Compounds
29Recent Operating Status
- Stack replaced in Sep 2008.
- A leak in the new stack forced reduction in
output to 40 kW in Dec 2008 - Operated at nearly 100 availability at reduced
load - Fuel cell was shutdown June 11 upon discovery of
sulfur breakthrough - Unit will not be restarted
30Lessons Learned by LACSD
- Ambient temperature considerations
- Chiller was undersized for high summer
temperatures - Lower digester gas production during winter
months - Carbon media must be monitored and/or replaced
periodically - Site involvement
- Digester gas system balancing
31Lessons Learned by Fuel Cell Energy
- Natural gas must be used as a backup fuel
- A load bank should be installed to mitigate grid
disturbances - Ensure proper maintenance of the fuel skid
32Contracting Issues Impacting the Facility
- These were demonstration projects as such,
providers would not provide availability
guarantees - The current OM contracts have no performance
incentive or penalty down time costs the owner
but does not cost the contractor - Fast response not always justified by plant
economics - Other contracting options
- Incentives and penalties for response time and
availability - Power purchase agreement, unit owned by provider
or third party - These options are generally currently available
33Conclusions
- The Palmdale fuel cell did not meet performance
goals - The Palmdale fuel cell met its goal to
demonstrate a high efficiency, low emission
technology on digester gas - As an early adopter, Districts allowed
manufacturers to address and resolve design and
operating issues
34Questions?
- Contact information
- mmcdannel_at_lacsd.org
- (562) 908-4228 x2442