Connection Details Manual ABC Project that Save Money - PowerPoint PPT Presentation

About This Presentation
Title:

Connection Details Manual ABC Project that Save Money

Description:

Connection Details Manual ABC Project that Save Money – PowerPoint PPT presentation

Number of Views:108
Avg rating:3.0/5.0
Slides: 85
Provided by: mikec49
Learn more at: https://www.iowadot.gov
Category:

less

Transcript and Presenter's Notes

Title: Connection Details Manual ABC Project that Save Money


1
Connection Details ManualABC Project that Save
Money
Iowa DOT Accelerated Bridge Construction
Workshop August 11, 2008
Michael P. Culmo, P.E. CME Associates, East
Hartford, CT
2
Roadblocks to Accelerated Construction
  • The primary concerns that owner agencies have
    with respect to adopting accelerated construction
    techniques are
  • Need for Quality Details
  • Durability
  • Design Methodologies and Training
  • Construction Methodologies

3
Connections for Prefabricated Bridge Elements
and Systems
  • FHWA has initiated a project to develop this
    manual
  • This publication is intended to provide
    information that will go a long way to answering
    all four of the previous concerns.
  • Focus on details that have been used in the past.

4
Project Goals
Connection Details for Prefabricated Bridge
Elements and Systems
  • Gather details of Connections that have been used
    on accelerated bridge construction projects
  • Investigate transfer of technology from other
    markets into the bridge market
  • Parking Garages
  • Stadiums
  • Buildings

5
  • All details needs to pass a critical test
    before being published in the document
  • Does the connection result in a rapid
    construction process?
  • Does the connection transmit the forces between
    elements effectively?
  • Is the connection durable?
  • Has it performed well under traffic and in an
    exposed environment?
  • Is it cost effective and easy to construct?
  • If a process or connection is proprietary, can it
    be incorporated into numerous projects without
    producing contracting issues?

6
Source of Data
  • State DOTs
  • Questionnaires sent via e-mail
  • Federal Agencies
  • International Organizations
  • Researchers (previous and current)
  • Producers
  • Questionnaires sent via e-mail

7
Manual Organization
8
Connection Data Sheets
9
Some Information that is available today
  • PCI Northeast Bridge Technical Committee
  • Guidelines for Accelerated Bridge Construction
  • Available at www.pcine.org
  • FHWA
  • Framework for Prefabricated Bridge Elements and
    Systems (PBES) Decision-Making
  • Manual on Use of Self-Propelled Modular
    Transporters to Move Bridges

10
Precast Abutments
11
Precast Abutments
12
Precast Piers
13
Precast Piers
14
Precast Decks on PS Beams
15
Precast Decks on Steel Framing
16
Precast Decks
17
FRP Decks
18
Grid Decks
19
Partial Depth Deck Forms
20
Total Bridge Prefabrication
21
Total Bridge Prefabrication
22
Examples Epping NH
construction of 1-07.avi
23
Project Schedule
  • Gather information
  • Fall 2006 through Spring 2007
  • Visit states that are leaders in accelerated
    bridge construction
  • Winter 2007
  • Develop manual
  • Summer/Fall 2007
  • Complete Manual
  • Fall 2008

24
Project Delivery
  • The document will be available for all owners and
    designers for use in future accelerated bridge
    projects
  • Website will be established on the FHWA Highways
    for Life Website
  • www.fhwa.dot.gov/hfl/

25
Schematic Design of an Accelerated Bridge
26
Case Scenario
  • 4 lane bridge over an expressway
  • Existing bridge has deteriorated beyond repair
  • Heavy traffic on both roadways
  • There is a short but undesirable detour

27
Public Involvement
  • Public hearing held
  • Businesses do not want a long construction
    process with stage construction
  • Businesses are not keen about a detour
  • They will accept a short term closure with the
    detour
  • As opposed to a long term staged project

28
Design Options
  • Build a temporary bridge to speed up construction
    of the new bridge
  • Not that fast
  • Build bridge along side and slide into place with
    SPMTs
  • Definitely possible
  • Does not easily solve problem with foundations
  • Establish the detour and accelerate the bridge
    construction to less than 30 days

29
Existing Bridge
30
Existing Bridge
Deck Joints
Low Clearance
31
Issues with the Existing Bridge
  • Minimal Underclearance
  • 14-5
  • Piers and abutments are close to roadway
  • Spray from vehicles damaged the piers
  • Leakage through deck joints
  • Led to severe beam end deterioration

32
Proposed Bridge
  • After a formal type study, the owner opted with
    the following structure criteria
  • Continuous steel girders (weathering steel)
  • Reduce to a two span bridge
  • Increase clearance by raising approach grades
    (3)
  • Use integral abutments (no deck joints)
  • Composite concrete deck
  • Membrane waterproofing and Bituminous wearing
    surface
  • Open steel railings (galvanized)

33
Existing Bridge
34
Proposed Bridge
35
Proposed Bridge
36
Features of New Bridge
  • Move pier far from roadway
  • Possible future widening options
  • Push abutments back to top of slope
  • Minimize wingwall requirements
  • Use integral abutments with flying wings
  • Both abutments and the pier are in a different
    footprint than the existing
  • facilitates construction
  • Eliminate spray attack on piers and abutments
  • No deck joints

37
How to select details
  • FHWA manual Connection details for prefabricated
    bridge elements and systems
  • Review Chapter 1
  • Investigate connection types, materials,
    tolerances
  • 2. Search applicable sections of other chapters
    for details

38
Section 1.4 Typical Connection Types
  • After reviewing chapter 1, the owner chose the
    following connection types
  • Grouted reinforcing splice couplers
  • Quick, proven system
  • Can develop full bar strength
  • Simplifies the design process (similar to CIP)
  • Grouted Voids
  • Easy for simple connections
  • Concrete Closure pours between precast elements
  • Use for a limited number of connections (slower)

39
Grouted Reinforcing Splice Connectors
  • Emulates a reinforcing steel lap splice
  • Multiple companies non-proprietary
  • Used in precast parking garages and stadiums and
    bridges

40
Schematic Pier Design
  • Footing to subgrade connection
  • Section 4.1.1 Precast footing to subgrade
    connection
  • Detail developed by New Hampshire DOT

41
Data Sheet
42
Footing Details
43
Schematic Pier Design
  • Footing to column connection
  • Section 3.1.4.2 Precast column to Precast Footing
    connection
  • Detail developed by the Northeast PCI Bridge
    Technical Committee based on work done in Florida
  • Used extensively in vertical construction
  • Parking garages, stadiums and hotels

44
Data Sheet
45
Footing/Column Details
46
Schematic Pier Design
  • Column to Cap Beam connection
  • Section 3.1.1.2 Precast cap beam to precast
    column connection
  • Detail used by the Florida DOT
  • Edison Bridge

47
Data Sheet
48
Column/Cap Beam Details
49
Completed Pier
Column to cap connection
Column to footing connection
Footing to subgrade connection
50
Schematic Abutment Design
  • Integral Abutment to precast piles
  • Section 3.2.3.1 Precast Integral Abutment to
    Piles
  • Detail developed by Maine DOT
  • Used on three different bridges

51
Data Sheet
52
Schematic Abutment Design
  • Integral Abutment wall splices and wingwall
    connection
  • Section 3.2.3.3 and 3.2.4.1 Precast Integral
    Abutment Connections
  • Detail developed by the Maine DOT
  • Used on three different bridges

53
Data Sheet
54
Abutment Cap Splices
55
Schematic Abutment Design
  • Approach Slab to Abutment wall connection
  • Section 3.2.4.2 Precast Approach Slab to Abutment
    Connections
  • Detail developed by the New Hampshire DOT
  • Based on a design used by the Maine DOT

56
Data Sheet
57
Completed Abutment
Approach slab connection
Flying Wingwall connection
Abutment cap connection
Pile to cap connection
58
Schematic Deck Design
  • Precast Full Depth deck on steel stringers
  • Section 2.1.1.2 Precast full depth deck to steel
    stringer
  • Detail used by many states
  • CT, NY, NH, ID, etc.
  • Details proven by research and real world projects

59
Data Sheet
60
PC Deck to Stringer Details
61
Schematic Deck Design
  • Precast Full Depth deck transverse connection
  • Section 2.1.1.1 Connection between slab elements
  • Detail also used by many states
  • Post tensioned according to AASHTO
  • 250 psi net (concentric)

62
Data Sheets
63
Data Sheets
64
PC Deck Connection Details
65
Schematic Deck Design
  • Precast Full Depth deck longitudinal connection
  • Section 2.1.1.1 Connection between slab elements
  • Detail also used by several states
  • CT, NH
  • Simple closure pour
  • Accommodates crown in deck

66
Data Sheet
67
PC Deck connection Details
68
Schematic Deck Design
  • Precast Full Depth deck to curb connection
  • There is a lack of crash tested precast parapets
    or curbs
  • Use a simple cast-in-place curb
  • High Early Concrete
  • Can be done at the same time as the crown joint
  • Continuous pour with crack control joints

69
Schematic Design
  • Connection of superstructure to integral abutment
  • There is a need for significant tolerances at
    this connection
  • It also has very complex geometry
  • Use a simple cast-in-place pour
  • High early concrete
  • Forming can be done while deck is being installed
  • Could use a precast backwall as a partial form

70
Completed Superstructure
Longitudinal crown connection
Connection to beam
CIP Curb
Transverse slab connection
Integral Abutment Connection
Longitudinal PT
71
Complete Bridge
Membrane waterproofing with bit. Wearing surface
Precast full depth composite deck
Precast Pier
Precast Integral Abutment
72
Estimated Construction Schedule
73
Costs
  • Typical New Bridge (Cost175/sf) 2,200,000
  • Premium for ABC (assume 20) 440,000
  • Temporary Bridge (Cost50/sf) (620,000)
  • Net Savings 180,000
  • Note These prices will vary greatly by region

74
Quality
  • Florida has had very good success with precast
    piers in very harsh environments
  • CT has had Precast full depth decks in place for
    over 17 years
  • Crack Free Deck
  • Excellent condition
  • Integral abutments eliminate deck joints

75
Old Adage
You can only have any two
By elimination of temporary bridges or costly
stage construction schemes, you CAN have all
three
76
Other Cost Savings
  • Reduced Bid Prices
  • Standardization
  • Programmatic (not one of a kind)
  • Reduced project site costs (trailers, etc.)
  • Reduced Maintenance Of Traffic Costs
  • Inflation
  • Non- Bid Savings
  • Fewer Police Details
  • Reduced Inspection time
  • User Costs
  • Plus Can be significant
  • Minus Not in the budget

77
FDOT Graves Avenue over I-4 Bridge Replacement -
2006
Each new span installed in few hours overnight
I-4 closed two partial nights for installations
78
FDOT Graves Avenue over I-4 Bridge Replacement -
2006
  • Costs
  • Supplemental Agreement for Change Order to
    existing contract 570,000
  • Benefits
  • Graves Avenue detour from 12 to 8 months, in time
    for start of school
  • I-4 lane closures from 32 nights to 4 nights
  • Delay-related user cost savings of 2.2M

79
UDOT 4500 South over I-215E Bridge Replacement -
2007
removal
4-lane, 173-ft long, 1,750 ton span installed
over weekend
installation
with no Impact to rush-hour traffic
80
UDOT 4500 South over I-215E Bridge Replacement -
2007
  • Costs
  • Additional 800,000 for use of SPMTs
  • Benefits
  • I-215E closed 53 hours over a weekend (versus
    6-month conventional construction)
  • 4500 South Bridge closed 10 days
  • Delay-related user cost savings of 4M

81
NJDOT Rt. 1 over Olden/Mulberry Span Replacements
2005
New Jerseys 1st Hyperbuild Project
Elevation of new Route 1 Bridges over Mulberry
Street
Replaced 3 spans in 3 weekends
82
NJDOT Rt. 1 over Olden/Mulberry Span Replacements
2005
  • Costs
  • 3.5M low bid compared to engineers estimate of
    3.8M (8 savings)
  • Benefits
  • Each bridge opened in less than 57 hours
  • 3 spans over 3 weekends (6 days vs. 22 mo.)
  • No impact to peak-hour traffic
  • Anticipated 75-100 year life (vs. 50 years)
  • 2M design/construction savings incl. user cost

83
Conclusions
  • It is possible to build a complete bridge in 30
    days (or less)
  • The FHWA manual provides a starting point for a
    complete bridge prefabrication project
  • You do not need to sacrifice quality to get rapid
    construction
  • By eliminating a temporary bridge or staging, you
    could save money on an accelerated bridge project
  • ABC can lead to a significant reduction in user
    costs

84
Questions?culmo_at_cmeengineering.com
Write a Comment
User Comments (0)
About PowerShow.com