Title: Power Distributrion System PDS Status Report
1Power Distributrion System (PDS)Status Report
- Chin E. Lin (NCKU)
- PDS-Subgroup
- MIT (M. Capell, A. Lebedev)
- NSPO (J. R. Tsai, S. Tsai, J. J. Yeh, H. Y.
Chang) - ETHZ (G. Viertel, K. S. Kim)
- NCKU (C. E. Lin, C. C. Li, S. M. Lin)
2Ongoing activities
- Box Mechanics Production
- Harness design
- Ongoing Boards tests
- PB2
- ESEM 3A
- ESEM 3B,
- Can bus I/F
- Boards manufacturing
- Input Stage
- Distribution Board
- Thermal analysis
- Structural analysis ?completed
- ESEM 1A and 1 ESEM 3A test ? completed
3EM Boards testing ESEM 3A, ESEM 3B
ESEM 3-A
4EM Boards testing PB2 and CAN BUS I/F
PB2 board and test setup CAN BUS I/F
5EM Boards testing DCDC Aux mezzanine
- The DCDC Aux
- Is a mezzanine on all ESEM 3A, ESEM 3B and PB2
boards - Supplies internal power to each main board
- Can be tested independently from the main boards
PB2 test setup with DCDC Aux mezzanine board
6EM Boards testing ESEM 1A
- Test completed
- Mezzanine, transformer and flying components that
have been trimmed need final mounting and then
the board can be closed
7Box Mechanics under production
8(No Transcript)
9(No Transcript)
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14Input Stage
Telemetry section EMI section
15Harness design
Area for cables between connectors and DB
Input stage Side A
Input stage Side B
Distribution Board (DB)
Area for ESEM boards Side A Side
B
Area for cables between motherboard and DB
Cable connecting the two motherboards together
16Collaborators at CGSETH, NSPO, NCKU
17ETH _at_
- September 1st Ms. Kyung Sook Kim, assistant of
Prof. Viertel, joined CGS for two months
- ONGOING ACTIVITIES
- Prepare preliminary test procedure at unit level
- Support to EGSE preparation for board testing
18NSPO _at_
- September 29th two engineers from Mechanical
Engineering section (Head J.-R. Tsai) and
Electrical Engineering Section (Head S. Tsai),
Mr. Jia-Jing Yeh and Mr.Hung-Yuan Chang, joined
CGS for one month
- ONGOING ACTIVITIES
- Preparation of EGSE
- test connector for ESEM 3A
- PC adapter
- ESEM 3A board visual inspection
- Debugging of ESEM 3A (28V distributer)
temperature sensing circuit - ESEM 3A board testing
19NCKU _at_
- October 14th two research assistants of Prof.
Chin E. Lin, NCKU, Mr. Suei Moo Lin and Mr.
Chih-Chi Li joined CGS for one month
- TASKS
- Update EM drawings to FM standard for FM
mechanics production - Support to board testing and organize FM
components procurement
20EM Planning
Successful Design Review held in May at CGS
Support from NCKU/NSPO and ETH in
September-October at CGS for test activities
Preliminary CAN tests
EM delivery for FIT at KSC
21Planning with FM delivery March 2006
22(No Transcript)