Concrete Test Section at Roodekrans - PowerPoint PPT Presentation

1 / 49
About This Presentation
Title:

Concrete Test Section at Roodekrans

Description:

Concrete Test Section at Roodekrans – PowerPoint PPT presentation

Number of Views:55
Avg rating:3.0/5.0
Slides: 50
Provided by: BryanP
Category:

less

Transcript and Presenter's Notes

Title: Concrete Test Section at Roodekrans


1
Concrete Test Sectionat Roodekrans
  • RPF
  • November 2002

2
Outline
  • Objectives
  • Design details Material properties
  • Instrumentation
  • Traffic
  • Construction
  • Present condition
  • Preliminary findings
  • Future

3
(No Transcript)
4
Objectives
  • Calibrate design method cncPave
  • Quantify and define failure of low-volume
    concrete pavements
  • Compare the performance of pavements and subbase
    types
  • Evaluate effect of joint spacing load transfer
    mechanisms

5
Parties
  • Cement and Concrete Institute
  • CSIR Transportek
  • University of Pretoria
  • Alpha Stone and Readymix
  • BKS
  • Raubex

6
Design details
  • Section 1
  • 75 mm SFRC (30 kg/m3) Joint spacing 3 m
  • 140 mm Foam concrete subbase
  • In situ
  • Section 2
  • 75 mm SFRC (30 kg/m3) Joint spacing 6 4 m
  • 125 mm CTS
  • In situ

7
Design details
  • Section 3
  • 75 mm SFRC (30 kg/m3) No joints
  • 25 mm ETB
  • 125 mm CTS
  • In situ

8
Design details
  • Section 4
  • 50 mm CRCP with mesh
  • 50 mm ETB
  • 125 mm CTS
  • In situ
  • Section 5
  • 75 mm CRCP with mesh
  • 25 mm ETB
  • 125 mm CTS
  • In situ

9
Design details
  • Section 6
  • 100 mm CRCP with mesh
  • 125 mm CTS
  • In situ

10
Design details
  • Section 7
  • 100 mm butt joints spaced 2 and 3 m
  • 125 mm CTS
  • In situ
  • Section 8
  • 100 mm butt joints spaced 2 and 3 m
  • 40 mm continuously graded asphalt
  • 100 mm CTS
  • In situ

11
Design details
  • Section 9
  • 140 mm butt joints spaced 2, 3 and 4 m
  • 125 mm gravel
  • In situ
  • Section 10
  • 140 mm shrinkage joints spaced 2, 3 and 4 m
  • 125 gravel
  • In situ

12
Design details
  • Section 11
  • 140 mm dowel joints spaced 2, 3 4 m
    25 mm dowels _at_ 300 c/c
  • 125 mm gravel
  • In situ

13
Material Properties
  • In situ
  • CBR 80
  • Quartzitic gravel A-1-a G5/G6
  • Compaction 97 Mod. AASHTO
  • FWD deflections ? 1,0 mm

14
Material Properties
  • Subbase
  • Gravel same as in situ material
  • Compaction 97 Mod. AASHTO
  • Stabilized with 2 CEM I 42.5 (C3)
  • UCS ? 2000 kPa
  • FWD deflection 0,9 mm and Stab 0,5 mm

15
Material Properties
  • ETB
  • Subbase material
  • Stabilized with 1,5 anionic stable grade
    emulsion 1 cement
  • Asphalt
  • Continuously graded hot mix 60/70 pen
  • 12 mm aggregate size

16
Material Properties
  • Concrete
  • Strength
  • fc 22 - 42 MPa
  • ff 3,7 - 5,6 MPa
  • Mod E 24 - 33 GPa
  • Shrinkage 0,05 - 0,06
  • Cement CEM I 42,5/GGBS 80/20

17
Instrumentation
  • LVDTs
  • Centre
  • Side
  • Thermocouples
  • Conventional
  • Programmable
  • Weather station
  • Falling Weight Deflectometer (FWD)

18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
(No Transcript)
23
Construction
  • Readymix concrete
  • Compaction by poker and beam
  • Curing compound
  • Plastic sheeting

24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
Traffic
  • Trucks leaving quarry
  • Weigh bridge data
  • No of axles
  • Approximately 300 E80s per day
  • To date 80 000 E 80s

32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
(No Transcript)
36
(No Transcript)
37
(No Transcript)
38
(No Transcript)
39
Observations
  • Very little distress to date
  • Vertical movement at joints under traffic
  • Rocking of slabs on foam concrete
  • Some corner and mid-slab cracking
  • Plastic shrinkage cracks not affecting
    performance
  • Some cracks becoming active

40
Preliminary Findings
  • Performance 100 better than expected, thin
    CRCP sections doing very well
  • Critical thickness around 90 mm
  • Higher deflections at cracks joints forerunner
    of relative vertical movement
  • Slab curling dry erosion lead to pumping
  • Failure in the eyes of the beholder

41
Future
  • Ongoing observations measurements of
    deflections and movements (FWD)
  • Continual recording of traffic loading
  • Panel to define failure for different types of
    pavements and facilities
  • Analysis of results and calibration of design
    program cncPave
  • Availability of data

42
Thank you
43
(No Transcript)
44
(No Transcript)
45
(No Transcript)
46
(No Transcript)
47
(No Transcript)
48
(No Transcript)
49
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com