Electrical - PowerPoint PPT Presentation

1 / 68
About This Presentation
Title:

Electrical

Description:

Problem 7b causes slight errors for some narrow regions of temperature data. ... ( see related Special Topic: A/D Conversion Errors) ... – PowerPoint PPT presentation

Number of Views:79
Avg rating:3.0/5.0
Slides: 69
Provided by: brucezin
Category:

less

Transcript and Presenter's Notes

Title: Electrical


1
Section 15 Electrical
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
2
Contents
  • System Block Diagram
  • Box IT Flow
  • Remaining Work to be Performed
  • Critical RFAs
  • Status of Open Actions
  • Residual Risk
  • Launch Readiness

3
System Block Diagram
4
Power System Block Diagram
5
Verification Matrix
6
Accumulated Power On Time for EO-1 S/C
Components
7
Box Level IT Process Flow(SAI-PLAN-130)
8
Remaining Work to be Done
  • Harness Closeouts
  • Remaining work related to re-installation of WARP
    and bay closeouts for flight.
  • WARP Re-Integration
  • Repeat of previous successful integration
    following repair
  • Hyperion Re-Integration
  • Repeat of previous successful integration
    following removal
  • ALI, Hyperion, and LAC to WARP Re-Integration
  • Repeat of previous successful integration
    following WARP removal

9
Remaining Work to be Done (continued)
  • S/A Integration
  • Repeat of previous successful integration for
    Vibration Acoustic Test
  • Calorimeter Integration
  • Two thermistors. S/C side already verified.
  • IRU Re-Integration
  • Following removal of IRU due to threat of Helium
    exposure
  • 1773 Bus Characterization (following all 1773
    integrations)
  • Required due to WARP, AST and Hyperion de-mate
  • Repeat of previous successful integration
  • Trickle Charge Diode installation and test
    (WOA 905 PR40-2)
  • Replacing fuse to enhance reliability and reduce
    susceptibility to failure

10
Critical RFAs(not dealt with in other topics)
  • CDR RFA 4.04 S/A deployment by hardware driven
    circuitry
  • HKRSN has both HW and SW deployment capability
    driven by separation switches
  • CDR RFA 4.10 Perform worst case analysis on all
    circuits
  • Heritage (MAP), design techniques, and testing
    provide adequate solution
  • CDR RFA 4.15 Grounding/Shielding philosophy
  • System Level Electrical Requirements
    AM149-0020(155) specifies requirements
  • System level EMI/EMC testing validated design and
    implementation

11
Status of Open Actions
  • 1773 Bus Fault During MOC Sim (WOA 876 PR20-1,
    20-3)
  • Latest MV SW Build eliminated problem
  • Solar Array Deployment Test
  • All testing to date successful
  • Planned for launch site
  • Primary side with flight fuse plug

12
Residual Risk
  • One Time Events
  • Chassis current Transient (WOA 770-20-3,
    PR20-3)
  • One event of 300mA, also seen on stripchart
    recorder
  • EMC testing was taking place with probes
    connected to spacecraft power bus
  • No recurrence since event on 11/22/99
  • Chassis current event (WOA 572-30-10)
  • Prolonged chassis current event reaching a peak
    of 925 mA
  • Solar Array Simulator cable (EGSE) found to have
    split insulation on multiple wires within
    backshell
  • Following inspection a new Solar Array Simulator
    cable was fabricated
  • No recurrence ( with exception of 770-20-3 which
    was a brief event )
  • Deployables (See Special Topic)
  • All testing to date successful (see Special
    Topic)
  • Full system test with SA scheduled for launch
    site
  • Nadir Deck Heater Short (See Special Topic)
  • WOA 676-20-8, PR20-8
  • Re-wiring to bypass stressed components in place
    and tested
  • S/A Cell Bonding Issue (See Special Topic)
  • WOA 765-30-1, PR30-1
  • Inspection and test are sufficient to resolve
    concerns

15 - 12
13
Launch Readiness
  • Complete system level testing (CPT, S/A
    deployment)
  • Previous success suggests low risk
  • Complete remaining activities
  • See previous section on Remaining Work to be Done
  • Install and test new trickle charge protection
    diode
  • Low risk S/C closeouts and repeats of previous
    integrations

14
Special Topic MAP Heritage Issues
. . . Mark Perry Swales Aerospace, Inc.
15
Review of MAP PRs for Relevance to EO-1
  • Special topic 15a, response to RFA 14.11 and 1.19
  • All MAP PRs were reviewed assessed for
    relevance to EO-1. Only two PRs were added to the
    list of 14 that was presented at the PSR.
  • Verified that there is no risk to EO-1 mission
    success. For some PRs, additional action was
    required.
  • Statistics for the 16 PRs (EO-1 used multiple
    approaches for some PRs, so three PRs have two
    categories)
  • 7 PRs categorized as SAME EO-1 incorporated the
    same corrections as MAP
  • 2 PRs categorized as OTHER Fixed with a
    different method than used for MAP
  • 6 PRs categorized as NOT SEEN These problems
    depend on MAP-specific workmanship, part lot, or
    design
  • 4 PRs categorized as NO RISK Not fixed on EO-1,
    but determined that they are not a mission risk.

16
Residual Risk Effects Due to MAP PRs
  • Problem 5 (from the next page) has a very low
    probability of causing a very slight attitude
    disturbance. The maximum disturbance should not
    cause the ACS to exceed its stability
    requirement, and should be undetectable in an
    image even if the ACE resets during an image.
  • Problem 7b causes slight errors for some narrow
    regions of temperature data. Since none of this
    data is used on board for S/C control, there is
    no risk to the mission, but it may complicate
    some data analysis. (see related Special Topic
    A/D Conversion Errors)
  • Problem 11 has a very low probability of causing
    an MV watchdog reset in the ACDS or WARP. If the
    WARP MV resets, stored data may be lost. If the
    ACDS MV resets, the only effect is reduced
    operational efficiency following the event (the
    spacecraft will enter safemode, and images are
    cancelled until restored by ground operations).
    There is no risk to mission safety.
  • See table on next page for additional details

17
MAP PRs Relating to EO-1
18
MAP PRs Relating to EO-1 (2)
19
MAP PRs Relating to EO-1 (3)
20
Special Topic Nadir Deck Heater Short
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
21
Nadir Deck Short Circuit
  • Summary of Event (WOA 676-20-8)
  • Two LVPC Over Current Trips experienced in PSE
    LVPC during TVAC. No indication of chassis
    current coincident with the events. Strip chart
    data shows high current being sourced by the
    battery in both incidents.
  • Following events, two LVPC services failed to
    respond (no current flow) for the remaining tests
    in TVAC.
  • PSE LVPC service 9 provides power to nadir deck
    primary, and panel 6 secondary heater services
  • CDH LVPC service 2 provides power to nadir deck
    secondary, and panel 2 primary heater services

22
Nadir Deck Short Circuit
  • Cause of Event / Problem in S/C
  • Nadir Deck heater wiring (both primary and
    secondary) had wiring error that caused a
    short-circuit with the closure of certain
    thermostats in the wiring network. Identical
    error present in both primary and secondary.
    Telemetry data is consistent with a short circuit
    in the nadir deck primary heaters for the first
    event.
  • Ramifications to mission
  • Two LVPC switched services have been removed from
    operational use.
  • LVPC over-current protection not as robust as
    assumed.
  • Selective fusing incorporated. See Special Topic
    15c
  • Nadir deck and Panel 2 will only have primary
    heater services, no secondary in either
    location.

23
Nadir Deck Short Circuit
  • Testing Performed Following Event
  • Nadir deck heaters subjected to full battery of
    continuity testing.
  • Wiring errors found in both circuits which can
    cause a short-circuit under certain combinations
    of thermostat closures.
  • LVPC services in question subjected to testing to
    evaluate functionality/state of health
  • Both services functioning since testing began
    following TVAC
  • LVPC Service 9 shows leakage and increased
    on-resistance (WOA-723-20-14 Problem Report)
  • CDH Service 2 functioning normally
  • Spacecraft harness subjected to passive and
    powered testing
  • All wiring found to be correct and functioning
    properly
  • Panel 2 secondary heater wiring
  • Exercised using power while chilling thermostats.
    Found to function properly

24
Nadir Deck Short Circuit
  • Conclusions resulting from Testing
  • PSE LVPC Service 9 was subjected to a short
    circuit emanating from the miswired nadir deck
    heater services. This resulted in damage to the
    switch.
  • CDH LVPC Service 2 appears to be healthy, as
    does all wiring and circuitry for Panel 2s
    thermal harnessing. No direct evidence that CDH
    Service 2 experienced a short circuit.
  • No collateral damage, or potential future
    collateral damage
  • Analysis and testing on a breadboard support
    conclusions
  • Corrective Actions
  • Nadir Deck Heater circuits abandoned by
    disconnecting and grounding to structure

25
Pre-Thermal Balance Heater Layout
26
Post-Thermal Balance Heater Layout
Service 6
Service 6
CDH LVPC
Active
Panel 6
P
S
Reinstate
Service 9
PSE LVPC
Abandoned
NADIR DECK
P
Ground
S
Abandoned
Service 2
CDH LVPC
Abandoned
Thermal analysis shows sufficient margin without
Panel 2 Primary Heater Circuit
Panel 2
P
Ground
S
Active
Service 4
CDH LVPC
Thermostat Setpoints Primary Close _at_8, Open
_at_13C Secondary Close _at_4, Open _at_9C
27
Nadir Deck Short Circuit
  • PSE LVPC Service 9 abandoned
  • Wires removed from LVPC connector and terminated
    to ground
  • Damaged switch not to be used in flight
  • CDH LVPC Service 2 abandoned
  • Wires removed from LVPC connector and terminated
    to ground
  • Suspect switch not be used in flight
  • New nadir deck heaters implemented
  • All new wiring, heaters, and thermostats
  • Serviced by remaining spare
  • Panel 6 heaters re-routed to different service
  • Serviced by remaining spare

28
Nadir Deck Short Circuit
  • Residual Risk / Redbook Candidates
  • Changes verified (jumpered thermostats to
    simulate closure where possible)
  • Not a Redbook Candidate

29
Special Topic Fusing / Overcurrent Review
. . . Bob Vernot Swales Aerospace
30
EO-1 Power Distribution Block Diagram
31
EO-1 Power Services
  • Unswitched
  • Mission Critical Loads, no fault protection
  • Fault Protection
  • SSPC (PSE Output Module)
  • Used for most mission critical loads plus
    instruments
  • Breaker trips at 16-22 A, no accommodation for
    faults below these levels
  • Over-current is sensed on power side of interface
  • Critical load SSPCs are reset by flight software
  • LVPC
  • Used for most non-mission critical and
    contingency loads
  • Selective fusing for fault protection of
    individual services
  • Ground ops programmable over-current set point
    for summed services
  • Removes power to all LVPC loads when over-current
    trips
  • Resets 5 times or continuously (for essential
    services ) until fault clears itself
  • Over-current sensed in power return only

32
SSPC Overcurrent Protection
  • EO-1 SSPCs are rated for 15 Amps steady state
    (represented by 100 on curve)
  • Steady state trip levels at 110 (16.5 A) to 145
    (21.75 A)
  • All Load I/F analyzed to demonstrate that hard
    short will draw enough current to trip SSPC

May trip
Always trip

Never trip
33
Fusing Considerations
  • Existing fault protection
  • SSPC vs. LVPC
  • Ease of fusing implementation
  • S/C access required
  • Design modifications required
  • Reliability and induced failure modes
  • Designing to survive launch environment
  • Testing to survive space environment
  • Risk vs. benefit
  • Fuse non-critical loads to prevent fault
    propagation to mission critical functions.

34
Fusing Decision Process Matrix
35
Summary Actions
  • Not necessary to fuse PSE Output Module Services
    as SSPCs provide protection against a hard short
  • Fuse non-essential PSE, ACE and CDH LVPC
    Services in order to
  • Provide individual service protection
  • Protect against chassis ground short
  • Provide an approach that is verifiable
  • Provide benefits that outweigh the risk
  • For all fused loads, loss of a single service
    results in no appreciable degradation of critical
    mission functions

36
Fuse Plug Design
  • Standard 50 derating criterion used, including
    protection against smart shorts.
  • Minimum allowable fuse rating is 2A
  • Redundant fusing used selectively for more
    essential loads
  • Redundant fusing meets derating criterion via
    steering resistors.

37
Fuse Plug Construction
  • Flight proven implementation using back-to-back
    connectors
  • All splices are solder splices
  • Custom brackets to stiffen assembly
  • Fuse plugs fully potted

38
LVPC Fuse Plug Verification Summary
  • Fuse Plug Verification during Assembly
  • Full continuity and isolation performed as
    follows
  • After termination and before potting.
  • After Potting.
  • Visual inspection at key points in assembly
    process
  • X-ray after Potting
  • Assembly Level Verification
  • All fuse plugs tested in T/V environment using
    worst case current plus 20 (min) for steady
    state duration (including transitions and 8
    cycles, per GEVS).
  • Current through all fuses and bus bars monitored
    continuously
  • High fidelity Continuity and Isolation
    verification before and after environmental test.
  • All fuse plugs subjected to protoflight random
    vibration levels in three axes (unpowered).
  • Harness mass loads simulated for test.
  • High fidelity Continuity and Isolation
    verification before and after environmental test.
  • S/C Level Verification
  • All fuse plugs verified at system level via
    safe-to-mate open circuit voltage measurements,
    loaded voltage and current balance measurements.
    Dummy loads used for thermostatically controlled
    circuits.

39
Summary
  • EO-1 is protected against overcurrent faults for
    all non-essential loads by selective fusing of
    LVPC services
  • Essential, non-redundant loads serviced by an
    LVPC are not fused to provide opportunity for
    fault to clear
  • Mission Critical loads services by SSPC are not
    fused, but S/C is protected against hard shorts
    by SSPC overcurrent protection
  • All fuse plugs successfully tested and installed
    on S/C
  • Complete Design drawings, Certification Logs and
    Verification documentation package delivered to
    GSFC customer

40
Special Topic Solar Array Adhesion
. . . Mike Cully Swales Aerospace, Inc.
41
Contents
  • Overview of Problem
  • Inboard Panel Inspection Results by TECSTAR
  • Impact to On-Orbit performance

42
Overview of Problem
  • Based on TIMED Program Solar Array panel
    problems, an inspection was performed to evaluate
    cell bonding integrity of cells on outboard
    panel. At the time only outboard panel was
    accessible since array was in stowed
    configuration. Both TIMED, MAP EO-1 solar
    arrays cells were manufactured at TECSTAR in
    around the same time frame (includes cell
    laydown).
  • Note that TIMED panel has significantly different
    cells, bond area requirements and substrate
    characteristics
  • Inspection technique used by APL/TECTSAR in
    response to TIMED problem is a newly developed
    inspection technique developed by TECSTAR for
    TIMED. Standard inspection consists of cleaning
    each cell and assessing any motion of the cell.
    Verifying final bonding area percentage is never
    performed.
  • All of the EO-1 panels passed this inspection
    without issue
  • Solar Array was fully inspected cleaned at
    Swales by TECSTAR prior to environmental testing
    at GSFC. Inspection revealed no issues with Cell
    Bonding using standard inspection technique.
  • Post Environmental Inspection by TECSTAR of
    Outboard panel revealed one crack in the cover
    glass

43
Initial Inspection Results
  • Initial inspection by APL of EO-1 Outboard
    personnel indicated several silicon cells had
    bonded areas less than 65 which is the
    specification for EO-1 (Landsat 7, GPS,...).
    TIMED requirement is 85. Typical programs use a
    bond area of between 65 70 (VCL, ORBVIEW3-4,
    Marie Curie Orbcomm)
  • Swales performed a further detailed inspection
    mapping of cells (100 grid) in question and
    confirmed APL results for silicon cells (GaAS/GE
    all seem to be within spec.). Following this
    TECSTAR was called in to perform more detail
    mapping (12/15-12/99) and confirmed results.
  • Based on outboard panel inspection TECSTAR
    personnel were called in a second time to perform
    detailed inspection of inboard panels. This was
    to be performed after the array was deployed off
    the spacecraft prior to LAPSS testing.

44
Inboard Panel Inspections Results by TECSTAR
  • Mid Inboard Panel
  • Deflection test performed on 200 300 cells
  • No unacceptable deflection failures identified.
    Met requirements of 65 bonded.
  • 100 inspection performed for cracked cells
  • No cell cracks found. Cover glass crack
    identified touched up with Epoxy 9350 per Std
    repair procedures. (see map)
  • 100 inspection of interconnects
  • No out of spec conditions found
  • Inboard Panel
  • Deflection test performed on 200 300 cells (see
    map)
  • No unacceptable deflection failures identified.
    Met requirements of gt65 bonded.
  • 100 inspection performed for cracked cells
  • No cell cracks found
  • 100 inspection of interconnects
  • No out of spec conditions found

45
Outboard Panel Inspection Results by TECSTAR
  • Outboard Panel (12/15/00 12/16/00 findings)
  • Deflection test performed on 100 of cells
  • Approximately 50 of the Si cells exhibited
    deflection ranging from 5 to 58 of the cell
    area
  • Cascade cells (Hyperion Mod), bonded in a
    different time period, did not exhibit out of
    spec conditions
  • 100 inspection performed for cracked cells
  • No cell cracks found. Cover glass crack
    identified and touched up with Epoxy 9350 per
    standard repair procedures.
  • 100 inspection of interconnects

46
TECSTAR Process Assessment
  • In an effort to troubleshoot cause of outboard
    panel non-conformance TECSTAR reviewed all
    paperwork associated with process of EO-1 panels
    (including Hyperion). Evaluation of process
  • All panels were within limits of the process
    however, the outboard panel, during initial
    curing of adhesive, was at the lower limit of
    Shore A hardness (coupon). This is significant
    since, at this stage of the process, the tape
    which is used to secure the cells to the mylar
    template is removed. When this occurs the cells
    have a small normal tension load applied.
    Insufficient hardness of the cell adhesive can
    cause the pre-existing voids (65 bonded) to grow
    in size. It is believed that this was the cause
    of the non-conformance of the outboard panel
  • TECSTAR has implemented process improvements
    independent of EO-1 to assure that the adhesive
    hardness is adequate prior to tape removal

47
TECSTAR Conclusion
  • The number of out of spec conditions on the
    outboard panel is minimal. Studies by TECSTAR
    working with APL to understand the TIMED void
    anomaly concluded that any area of the cell that
    remains bonded after bonding adhesive full cure
    through environmental test, does not degrade
    further even after additional thermal vacuum
    testing.
  • Panel tests data indicate very high pull
    strengths were demonstrated with this bonding
    recipe for all panels
  • Inboard and center panels show no adhesion out of
    spec conditions
  • Based on inspection results, traveler review
    experiments TECSTAR recommends no further action
    be taken with the outboard panel
  • Swales Performed Further Assessment
  • Mechanical Analysis
  • Thermal Analysis
  • Power Performance

48
Mechanical Assessment
  • Margin of Safety for 100 G static load for a 35
    bonded area, using a factor of safety 2.6
  • Maximum EO-1 adhesive stress with 100 G static
    load and 35 bond area is .38 psi
  • MS gt 150
  • Array has seen full Protoflight Acoustic and been
    exposed to S/C level sine environment
  • Margin of Safety for rapid depressurization for a
    35 bonded area using a factor of safety of 2.6
  • MS 2.738
  • All panels have been exposed to TV with outboard
    panel being exposed twice for Hyperion
    Modification

49
Thermal Assessment
  • Summary
  • Thermal analysis indicates that a 65 percent
    bond requirement (i.e., 35 disbonding) does not
    have a significant effect on the cell
    temperature. It is not until you reach a 10-15
    bond that the cell temperature increases
    significantly. This can be attributed to the
    conductivity of the Silicon adhesive (CV 2568 by
    Nusil, Inc.) and the conductivity of the cells.
  • Assumptions
  • Inboard Panel with 651 Silicon Cells
  • Solar Absorptivity 0.75, Emissivity 0.88
  • 8 mil coverglass and 8 mil Silicon Cells
  • Cell Adhesive is CV 2568
  • Solar Constant 450 Btu/hr-sq.ft.-F
  • Modeling results are consistent with TIMED
    analysis

50
Assess On-Orbit Performance Value AssumingWorst
Case Bonded Value (35)
  • The primary assumption is that all cells exhibit
    adhesive voids of 65 (35 bonded). This
    extremely conservative since only a small
    percentage of cells on outboard panel exhibit
    this.
  • EOL current for baseline Solar Array running at
    an average cell temperature of 72C
  • Current 18.876A at 33.5 Volts
  • EOL current for Solar Array running at an average
    cell temperature of 76C due to reduced bond area
    of 35
  • Current 18.273A at 33.5 Volts
  • Reduction in current for worst-case bonding (35
    bonded) is less than 3.1. Minimal impact to
    on-orbit EOL performance.

51
Conclusions
  • All required performance will be achieved
  • Removal of cells that are out of specification
    would result in risk to array
  • Array has been exposed to all flight environments
    without any problems
  • Disposition is Use As Is

52
Special Topic Contingency Plan for Partially
Deployed Solar Array Including Initial Power
Consumption if Solar Array Does Not Deploy (RFA
16.20)
. . . Bob Vernot EO-1 Systems Engineer
53
List of Assumptions
  • EO-1 goes to internal power prior to launch with
    battery at 100 SOC at T-10 minutes
  • Consistent with launch countdown and narrow
    launch window
  • Battery has nameplate capacity of 50 AH
  • Battery has actual capacity of between 50 and 55
    AH
  • SA collects zero power prior to attempted Sun
    Acquisition
  • Outer panel is likely to collect some power
    during coast and after tip-off. Power collection
    not quantified.
  • Following contingency Sun Acquisition, SA
    collects 192 W of power when lit
  • Consistent with IV curve predicts for outer panel
    at 100º C, 28 VDC and sun intensity of 0.97

54
List of Assumptions
  • EO-1 orbit average load of 130 Watts until
    heaters are required, then 198 Watts with heaters
  • Consistent with Thermal Balance Test data power
    predicts
  • Current drain on Battery assumes above loads at
    26.5 VDC
  • Reflects bus voltage with battery at minimum SOC.
    Actual voltage will be higher
  • S/C requires heater power six hours after launch
  • Consistent with Thermal predicts for thermostatic
    control to 8 C
  • S-band transmitter on for 10 minutes per orbit
    following heater power on
  • One contact per orbit
  • Contingency sun pointing to within 10 degrees of
    sun line
  • ACS should provide better than 1 degree accuracy
    using AST

55
Contingency Operations
  • Assumes that all reasonable efforts to deploy SA
    have been exhausted
  • All subsequent subsystem activation events to be
    aborted
  • Operations to activate AST
  • ACS to use AST to control attitude for undeployed
    SA sun pointing (procedure under development)
  • Transmitter duty cycle minimized
  • See Additional Considerations to follow

56
Battery SOC through Sun Acquisition
57
Worst Case Battery SOC for Undeployed SA
58
Additional Considerations
  • Additional power may be available.
  • Possible 3-5 AH during coast phase of ascent
    (6-10 SOC)
  • Possible 0-14 AH during despin, dependent upon
    spin axis (not predictable before separation)
  • Contingency Sun Acquisition may occur prior to
    worst case predict for Sun Acquisition
  • Ground management of heaters could greatly extend
    life
  • Selectively allow areas of S/C to get cold
  • Thermostatic control is set for 8 C, survival
    temperatures are at -10 C
  • Many areas of S/C will settle to steady state
    temperatures above survival limits, without
    heaters. Further analysis is required.
  • Will report on this topic at the Red Team
    Follow-up Review

59
Bounded SOC for Undeployed SA
60
Summary
  • For nominal heater operation SOC is reduced by
    10 per orbit
  • Under worst case conditions EO-1 can survive 10
    orbits
  • With all heaters disabled SOC is reduced by
    1.25 per orbit
  • Under worst case conditions EO-1 can survive 60
    orbits(4 days)
  • Reality lies somewhere between these conditions
    but is skewed toward the latter case if S/C is
    allowed to go to survival temperatures

61
Special Topic Oscillatory Starts on HSSR 7110
Switches
. . . Dave Speer Litton Amecom, ACS Lead
Designer
62
Oscillatory Starts on HSSR 7110 Switches
  • Background Description
  • LVPC switched 28V power services can exhibit
    3-amp current spikes, negative-going voltage
    oscillations, or even lack of turn on for
    sufficiently capacitive loads. Two known
    examples are Autonomous Star Tracker (AST) and
    Magnetic Torquer Bar (MTB) loads on ACE LVPC.
  • Problem was first recognized during MAP testing
    with their AST power interface. The EO-1 MTB
    power interface was tested for same problem due
    to electrically similar load circuitry.
  • At high input voltage, there is an LVPC output
    oscillation into the AST and MTB (refer to PR
    346-20-4 and PR 483-20-1) reactive loads
  • At low to nominal bus voltage (22V to 28V), these
    service-to-capacitive-load circuits turn on
    normally.
  • At intermediate to high bus voltages (30V to
    35V), these service-to-load circuits will
    oscillate momentarily but then turn on after a
    short delay (msecs).

63
Oscillatory Starts on HSSR 7110 Switches
  • Key Issue
  • Whether the spiking/oscillating condition
    damaged/overstressed components on either the
    LVPC side of 28V power interface or on the
    AST/MTB load side of power interface.
  • Analysis Test Results
  • Voltage and current waveforms that have been
    directly observed at the power-to-load interfaces
    (on a scope) do NOT represent an overstress
    condition. Max observed ?Vout was 56V, less
    than 90V rating. Current spikes are 3A for 2
    usec, less than 10A for 10 msec (one-shot)
    rating.
  • Circuit simulations that drove current spiking
    waveform into the MTB load circuitry did NOT
    indicate an electronic component overstress
    condition at the load side. Lab testing found
    that continuous spikes/oscillations are not a
    thermal overstress condition for 7110 switch
  • Action Taken
  • Transient Suppression Assembly (TSA) box was
    integrated in-line between AST 28V power service
    and AST load, which eliminated spikes/oscillations
    prior to first electrical integration and
    operation of AST. So no overstress on load side
    of AST power interface.
  • NO TSA box integrated in-line between MTB power
    service and MTB load, and this interface still
    experiences spikes/oscillations when turned on at
    high (29V to 35V) bus voltages.
  • MTB service is turned ON at launch. Command
    restrictions have been implemented such that the
    MTB can only be turned on at VB ? 28V

64
Context Diagram
65
Special Topic Torquer Bar Potential Overstress
. . . Dave Speer Litton Amecom, ACS Lead
Designer
66
Torquer Bar 15V Output Variations
  • Background Description
  • During normal Magnetic Torquer Bar (MTB)
    operations, the dedicated MTB 15V output supply
    voltage telemetry exceeded limits based on
    manufacturers specification for balanced load
    output regulation. Refer to PR 677-20-2 and PR
    681-20-12.
  • Problem was first recognized when Interpoint
    MTR2815D converter was being operated with very
    light (less than 40 mA) load on 15V output, and
    range (-110 to -190 mA) of load on -15V output.
  • Problem was repeated when this range of output
    load conditions was entered on four separate
    occasions during normal testing. When the
    torquer bars were operated in this range, the
    15V output varied by about 1, and the -15V
    output varied by about 2.
  • Status
  • Special MTB output characterization test was run
    (WOA-915) to verify that
  • With less than 40 mA on the 15V output, the
    behavior was independent of which individual bar
    was operating in the -110 mA to -190 mA range.
  • With less than 40 mA on the 15V output, the
    behavior was independent of whether the 3-bar
    total current was in the -110 mA to -190 mA
    range.
  • Amplitude of the 15V output variations was much
    smaller as load on 15V output was increased
    above 40 mA, and the output variation behavior
    disappeared when the load on the 15V output was
    above 70 mA.

67
Torquer Bar 15V Output Variations
  • Closure
  • Four sets of Excel data files and output voltage
    variation plots were sent to Interpoint for their
    review and analysis. They were then able to
    duplicate the same behavior that we saw, in their
    laboratory set-up, under nearly the same type and
    range of MTR output load conditions. They were
    also able to confirm that the 15V output voltage
    variations disappear when slightly more load
    (above the 40 mA level) is added to the 15V
    output.
  • Apparently, there is an output inductor inside
    the MTR2815D that goes into a discontinuous
    mode over a range of -15V loads when the 15V
    load is small. The discontinuous mode of
    operation affects the output voltage control loop
    and causes small variations in the 15V output
    voltages. If the 15V load is increased, or if
    the -15V load is above or below the sensitive
    range, then the output inductor goes back into
    continuous mode, and the output variations stop.
  • Small MTB converter output voltage variations do
    NOT represent a damaged condition, will NOT
    affect the operation of the MTB drivers, and are
    acceptable now that we understand them. Telemetry
    limits will be expanded slightly to allow for the
    observed behavior under a certain range of normal
    operating conditions.

68
Context Diagram
Write a Comment
User Comments (0)
About PowerShow.com