Title: Electrical
1Section 15 Electrical
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
2Contents
- System Block Diagram
- Box IT Flow
- Remaining Work to be Performed
- Critical RFAs
- Status of Open Actions
- Residual Risk
- Launch Readiness
3System Block Diagram
4Power System Block Diagram
5Verification Matrix
6Accumulated Power On Time for EO-1 S/C
Components
7Box Level IT Process Flow(SAI-PLAN-130)
8Remaining Work to be Done
- Harness Closeouts
- Remaining work related to re-installation of WARP
and bay closeouts for flight. - WARP Re-Integration
- Repeat of previous successful integration
following repair - Hyperion Re-Integration
- Repeat of previous successful integration
following removal - ALI, Hyperion, and LAC to WARP Re-Integration
- Repeat of previous successful integration
following WARP removal
9Remaining Work to be Done (continued)
- S/A Integration
- Repeat of previous successful integration for
Vibration Acoustic Test - Calorimeter Integration
- Two thermistors. S/C side already verified.
- IRU Re-Integration
- Following removal of IRU due to threat of Helium
exposure - 1773 Bus Characterization (following all 1773
integrations) - Required due to WARP, AST and Hyperion de-mate
- Repeat of previous successful integration
- Trickle Charge Diode installation and test
(WOA 905 PR40-2) - Replacing fuse to enhance reliability and reduce
susceptibility to failure
10Critical RFAs(not dealt with in other topics)
- CDR RFA 4.04 S/A deployment by hardware driven
circuitry - HKRSN has both HW and SW deployment capability
driven by separation switches - CDR RFA 4.10 Perform worst case analysis on all
circuits - Heritage (MAP), design techniques, and testing
provide adequate solution - CDR RFA 4.15 Grounding/Shielding philosophy
- System Level Electrical Requirements
AM149-0020(155) specifies requirements - System level EMI/EMC testing validated design and
implementation
11Status of Open Actions
- 1773 Bus Fault During MOC Sim (WOA 876 PR20-1,
20-3) - Latest MV SW Build eliminated problem
- Solar Array Deployment Test
- All testing to date successful
- Planned for launch site
- Primary side with flight fuse plug
12Residual Risk
- One Time Events
- Chassis current Transient (WOA 770-20-3,
PR20-3) - One event of 300mA, also seen on stripchart
recorder - EMC testing was taking place with probes
connected to spacecraft power bus - No recurrence since event on 11/22/99
- Chassis current event (WOA 572-30-10)
- Prolonged chassis current event reaching a peak
of 925 mA - Solar Array Simulator cable (EGSE) found to have
split insulation on multiple wires within
backshell - Following inspection a new Solar Array Simulator
cable was fabricated - No recurrence ( with exception of 770-20-3 which
was a brief event ) - Deployables (See Special Topic)
- All testing to date successful (see Special
Topic) - Full system test with SA scheduled for launch
site - Nadir Deck Heater Short (See Special Topic)
- WOA 676-20-8, PR20-8
- Re-wiring to bypass stressed components in place
and tested - S/A Cell Bonding Issue (See Special Topic)
- WOA 765-30-1, PR30-1
- Inspection and test are sufficient to resolve
concerns
15 - 12
13Launch Readiness
- Complete system level testing (CPT, S/A
deployment) - Previous success suggests low risk
- Complete remaining activities
- See previous section on Remaining Work to be Done
- Install and test new trickle charge protection
diode - Low risk S/C closeouts and repeats of previous
integrations
14Special Topic MAP Heritage Issues
. . . Mark Perry Swales Aerospace, Inc.
15Review of MAP PRs for Relevance to EO-1
- Special topic 15a, response to RFA 14.11 and 1.19
- All MAP PRs were reviewed assessed for
relevance to EO-1. Only two PRs were added to the
list of 14 that was presented at the PSR. - Verified that there is no risk to EO-1 mission
success. For some PRs, additional action was
required. - Statistics for the 16 PRs (EO-1 used multiple
approaches for some PRs, so three PRs have two
categories) - 7 PRs categorized as SAME EO-1 incorporated the
same corrections as MAP - 2 PRs categorized as OTHER Fixed with a
different method than used for MAP - 6 PRs categorized as NOT SEEN These problems
depend on MAP-specific workmanship, part lot, or
design - 4 PRs categorized as NO RISK Not fixed on EO-1,
but determined that they are not a mission risk.
16Residual Risk Effects Due to MAP PRs
- Problem 5 (from the next page) has a very low
probability of causing a very slight attitude
disturbance. The maximum disturbance should not
cause the ACS to exceed its stability
requirement, and should be undetectable in an
image even if the ACE resets during an image. - Problem 7b causes slight errors for some narrow
regions of temperature data. Since none of this
data is used on board for S/C control, there is
no risk to the mission, but it may complicate
some data analysis. (see related Special Topic
A/D Conversion Errors) - Problem 11 has a very low probability of causing
an MV watchdog reset in the ACDS or WARP. If the
WARP MV resets, stored data may be lost. If the
ACDS MV resets, the only effect is reduced
operational efficiency following the event (the
spacecraft will enter safemode, and images are
cancelled until restored by ground operations).
There is no risk to mission safety. - See table on next page for additional details
17MAP PRs Relating to EO-1
18MAP PRs Relating to EO-1 (2)
19MAP PRs Relating to EO-1 (3)
20Special Topic Nadir Deck Heater Short
. . . Bruce Zink EO-1 Electrical Lead, Swales
Aerospace, Inc.
21Nadir Deck Short Circuit
- Summary of Event (WOA 676-20-8)
- Two LVPC Over Current Trips experienced in PSE
LVPC during TVAC. No indication of chassis
current coincident with the events. Strip chart
data shows high current being sourced by the
battery in both incidents. - Following events, two LVPC services failed to
respond (no current flow) for the remaining tests
in TVAC. - PSE LVPC service 9 provides power to nadir deck
primary, and panel 6 secondary heater services - CDH LVPC service 2 provides power to nadir deck
secondary, and panel 2 primary heater services
22Nadir Deck Short Circuit
- Cause of Event / Problem in S/C
- Nadir Deck heater wiring (both primary and
secondary) had wiring error that caused a
short-circuit with the closure of certain
thermostats in the wiring network. Identical
error present in both primary and secondary.
Telemetry data is consistent with a short circuit
in the nadir deck primary heaters for the first
event. - Ramifications to mission
- Two LVPC switched services have been removed from
operational use. - LVPC over-current protection not as robust as
assumed. - Selective fusing incorporated. See Special Topic
15c - Nadir deck and Panel 2 will only have primary
heater services, no secondary in either
location.
23Nadir Deck Short Circuit
- Testing Performed Following Event
- Nadir deck heaters subjected to full battery of
continuity testing. - Wiring errors found in both circuits which can
cause a short-circuit under certain combinations
of thermostat closures. - LVPC services in question subjected to testing to
evaluate functionality/state of health - Both services functioning since testing began
following TVAC - LVPC Service 9 shows leakage and increased
on-resistance (WOA-723-20-14 Problem Report) - CDH Service 2 functioning normally
- Spacecraft harness subjected to passive and
powered testing - All wiring found to be correct and functioning
properly - Panel 2 secondary heater wiring
- Exercised using power while chilling thermostats.
Found to function properly
24Nadir Deck Short Circuit
- Conclusions resulting from Testing
- PSE LVPC Service 9 was subjected to a short
circuit emanating from the miswired nadir deck
heater services. This resulted in damage to the
switch. - CDH LVPC Service 2 appears to be healthy, as
does all wiring and circuitry for Panel 2s
thermal harnessing. No direct evidence that CDH
Service 2 experienced a short circuit. - No collateral damage, or potential future
collateral damage - Analysis and testing on a breadboard support
conclusions - Corrective Actions
- Nadir Deck Heater circuits abandoned by
disconnecting and grounding to structure
25Pre-Thermal Balance Heater Layout
26Post-Thermal Balance Heater Layout
Service 6
Service 6
CDH LVPC
Active
Panel 6
P
S
Reinstate
Service 9
PSE LVPC
Abandoned
NADIR DECK
P
Ground
S
Abandoned
Service 2
CDH LVPC
Abandoned
Thermal analysis shows sufficient margin without
Panel 2 Primary Heater Circuit
Panel 2
P
Ground
S
Active
Service 4
CDH LVPC
Thermostat Setpoints Primary Close _at_8, Open
_at_13C Secondary Close _at_4, Open _at_9C
27Nadir Deck Short Circuit
- PSE LVPC Service 9 abandoned
- Wires removed from LVPC connector and terminated
to ground - Damaged switch not to be used in flight
- CDH LVPC Service 2 abandoned
- Wires removed from LVPC connector and terminated
to ground - Suspect switch not be used in flight
- New nadir deck heaters implemented
- All new wiring, heaters, and thermostats
- Serviced by remaining spare
- Panel 6 heaters re-routed to different service
- Serviced by remaining spare
28Nadir Deck Short Circuit
- Residual Risk / Redbook Candidates
- Changes verified (jumpered thermostats to
simulate closure where possible) - Not a Redbook Candidate
29Special Topic Fusing / Overcurrent Review
. . . Bob Vernot Swales Aerospace
30EO-1 Power Distribution Block Diagram
31EO-1 Power Services
- Unswitched
- Mission Critical Loads, no fault protection
- Fault Protection
- SSPC (PSE Output Module)
- Used for most mission critical loads plus
instruments - Breaker trips at 16-22 A, no accommodation for
faults below these levels - Over-current is sensed on power side of interface
- Critical load SSPCs are reset by flight software
- LVPC
- Used for most non-mission critical and
contingency loads - Selective fusing for fault protection of
individual services - Ground ops programmable over-current set point
for summed services - Removes power to all LVPC loads when over-current
trips - Resets 5 times or continuously (for essential
services ) until fault clears itself - Over-current sensed in power return only
32SSPC Overcurrent Protection
- EO-1 SSPCs are rated for 15 Amps steady state
(represented by 100 on curve) - Steady state trip levels at 110 (16.5 A) to 145
(21.75 A) - All Load I/F analyzed to demonstrate that hard
short will draw enough current to trip SSPC
May trip
Always trip
Never trip
33Fusing Considerations
- Existing fault protection
- SSPC vs. LVPC
- Ease of fusing implementation
- S/C access required
- Design modifications required
- Reliability and induced failure modes
- Designing to survive launch environment
- Testing to survive space environment
- Risk vs. benefit
- Fuse non-critical loads to prevent fault
propagation to mission critical functions.
34Fusing Decision Process Matrix
35Summary Actions
- Not necessary to fuse PSE Output Module Services
as SSPCs provide protection against a hard short - Fuse non-essential PSE, ACE and CDH LVPC
Services in order to - Provide individual service protection
- Protect against chassis ground short
- Provide an approach that is verifiable
- Provide benefits that outweigh the risk
- For all fused loads, loss of a single service
results in no appreciable degradation of critical
mission functions
36Fuse Plug Design
- Standard 50 derating criterion used, including
protection against smart shorts. - Minimum allowable fuse rating is 2A
- Redundant fusing used selectively for more
essential loads - Redundant fusing meets derating criterion via
steering resistors.
37Fuse Plug Construction
- Flight proven implementation using back-to-back
connectors - All splices are solder splices
- Custom brackets to stiffen assembly
- Fuse plugs fully potted
38LVPC Fuse Plug Verification Summary
- Fuse Plug Verification during Assembly
- Full continuity and isolation performed as
follows - After termination and before potting.
- After Potting.
- Visual inspection at key points in assembly
process - X-ray after Potting
- Assembly Level Verification
- All fuse plugs tested in T/V environment using
worst case current plus 20 (min) for steady
state duration (including transitions and 8
cycles, per GEVS). - Current through all fuses and bus bars monitored
continuously - High fidelity Continuity and Isolation
verification before and after environmental test. - All fuse plugs subjected to protoflight random
vibration levels in three axes (unpowered). - Harness mass loads simulated for test.
- High fidelity Continuity and Isolation
verification before and after environmental test. - S/C Level Verification
- All fuse plugs verified at system level via
safe-to-mate open circuit voltage measurements,
loaded voltage and current balance measurements.
Dummy loads used for thermostatically controlled
circuits.
39Summary
- EO-1 is protected against overcurrent faults for
all non-essential loads by selective fusing of
LVPC services - Essential, non-redundant loads serviced by an
LVPC are not fused to provide opportunity for
fault to clear - Mission Critical loads services by SSPC are not
fused, but S/C is protected against hard shorts
by SSPC overcurrent protection - All fuse plugs successfully tested and installed
on S/C - Complete Design drawings, Certification Logs and
Verification documentation package delivered to
GSFC customer
40Special Topic Solar Array Adhesion
. . . Mike Cully Swales Aerospace, Inc.
41Contents
- Overview of Problem
- Inboard Panel Inspection Results by TECSTAR
- Impact to On-Orbit performance
42Overview of Problem
- Based on TIMED Program Solar Array panel
problems, an inspection was performed to evaluate
cell bonding integrity of cells on outboard
panel. At the time only outboard panel was
accessible since array was in stowed
configuration. Both TIMED, MAP EO-1 solar
arrays cells were manufactured at TECSTAR in
around the same time frame (includes cell
laydown). - Note that TIMED panel has significantly different
cells, bond area requirements and substrate
characteristics - Inspection technique used by APL/TECTSAR in
response to TIMED problem is a newly developed
inspection technique developed by TECSTAR for
TIMED. Standard inspection consists of cleaning
each cell and assessing any motion of the cell.
Verifying final bonding area percentage is never
performed. - All of the EO-1 panels passed this inspection
without issue - Solar Array was fully inspected cleaned at
Swales by TECSTAR prior to environmental testing
at GSFC. Inspection revealed no issues with Cell
Bonding using standard inspection technique. - Post Environmental Inspection by TECSTAR of
Outboard panel revealed one crack in the cover
glass
43Initial Inspection Results
- Initial inspection by APL of EO-1 Outboard
personnel indicated several silicon cells had
bonded areas less than 65 which is the
specification for EO-1 (Landsat 7, GPS,...).
TIMED requirement is 85. Typical programs use a
bond area of between 65 70 (VCL, ORBVIEW3-4,
Marie Curie Orbcomm) - Swales performed a further detailed inspection
mapping of cells (100 grid) in question and
confirmed APL results for silicon cells (GaAS/GE
all seem to be within spec.). Following this
TECSTAR was called in to perform more detail
mapping (12/15-12/99) and confirmed results. - Based on outboard panel inspection TECSTAR
personnel were called in a second time to perform
detailed inspection of inboard panels. This was
to be performed after the array was deployed off
the spacecraft prior to LAPSS testing.
44Inboard Panel Inspections Results by TECSTAR
- Mid Inboard Panel
- Deflection test performed on 200 300 cells
- No unacceptable deflection failures identified.
Met requirements of 65 bonded. - 100 inspection performed for cracked cells
- No cell cracks found. Cover glass crack
identified touched up with Epoxy 9350 per Std
repair procedures. (see map) - 100 inspection of interconnects
- No out of spec conditions found
- Inboard Panel
- Deflection test performed on 200 300 cells (see
map) - No unacceptable deflection failures identified.
Met requirements of gt65 bonded. - 100 inspection performed for cracked cells
- No cell cracks found
- 100 inspection of interconnects
- No out of spec conditions found
45Outboard Panel Inspection Results by TECSTAR
- Outboard Panel (12/15/00 12/16/00 findings)
- Deflection test performed on 100 of cells
- Approximately 50 of the Si cells exhibited
deflection ranging from 5 to 58 of the cell
area - Cascade cells (Hyperion Mod), bonded in a
different time period, did not exhibit out of
spec conditions - 100 inspection performed for cracked cells
- No cell cracks found. Cover glass crack
identified and touched up with Epoxy 9350 per
standard repair procedures. - 100 inspection of interconnects
46TECSTAR Process Assessment
- In an effort to troubleshoot cause of outboard
panel non-conformance TECSTAR reviewed all
paperwork associated with process of EO-1 panels
(including Hyperion). Evaluation of process - All panels were within limits of the process
however, the outboard panel, during initial
curing of adhesive, was at the lower limit of
Shore A hardness (coupon). This is significant
since, at this stage of the process, the tape
which is used to secure the cells to the mylar
template is removed. When this occurs the cells
have a small normal tension load applied.
Insufficient hardness of the cell adhesive can
cause the pre-existing voids (65 bonded) to grow
in size. It is believed that this was the cause
of the non-conformance of the outboard panel - TECSTAR has implemented process improvements
independent of EO-1 to assure that the adhesive
hardness is adequate prior to tape removal
47TECSTAR Conclusion
- The number of out of spec conditions on the
outboard panel is minimal. Studies by TECSTAR
working with APL to understand the TIMED void
anomaly concluded that any area of the cell that
remains bonded after bonding adhesive full cure
through environmental test, does not degrade
further even after additional thermal vacuum
testing. - Panel tests data indicate very high pull
strengths were demonstrated with this bonding
recipe for all panels - Inboard and center panels show no adhesion out of
spec conditions - Based on inspection results, traveler review
experiments TECSTAR recommends no further action
be taken with the outboard panel - Swales Performed Further Assessment
- Mechanical Analysis
- Thermal Analysis
- Power Performance
48Mechanical Assessment
- Margin of Safety for 100 G static load for a 35
bonded area, using a factor of safety 2.6 - Maximum EO-1 adhesive stress with 100 G static
load and 35 bond area is .38 psi - MS gt 150
- Array has seen full Protoflight Acoustic and been
exposed to S/C level sine environment - Margin of Safety for rapid depressurization for a
35 bonded area using a factor of safety of 2.6 - MS 2.738
- All panels have been exposed to TV with outboard
panel being exposed twice for Hyperion
Modification
49Thermal Assessment
- Summary
- Thermal analysis indicates that a 65 percent
bond requirement (i.e., 35 disbonding) does not
have a significant effect on the cell
temperature. It is not until you reach a 10-15
bond that the cell temperature increases
significantly. This can be attributed to the
conductivity of the Silicon adhesive (CV 2568 by
Nusil, Inc.) and the conductivity of the cells. - Assumptions
- Inboard Panel with 651 Silicon Cells
- Solar Absorptivity 0.75, Emissivity 0.88
- 8 mil coverglass and 8 mil Silicon Cells
- Cell Adhesive is CV 2568
- Solar Constant 450 Btu/hr-sq.ft.-F
- Modeling results are consistent with TIMED
analysis
50Assess On-Orbit Performance Value AssumingWorst
Case Bonded Value (35)
- The primary assumption is that all cells exhibit
adhesive voids of 65 (35 bonded). This
extremely conservative since only a small
percentage of cells on outboard panel exhibit
this. - EOL current for baseline Solar Array running at
an average cell temperature of 72C - Current 18.876A at 33.5 Volts
- EOL current for Solar Array running at an average
cell temperature of 76C due to reduced bond area
of 35 - Current 18.273A at 33.5 Volts
- Reduction in current for worst-case bonding (35
bonded) is less than 3.1. Minimal impact to
on-orbit EOL performance.
51Conclusions
- All required performance will be achieved
- Removal of cells that are out of specification
would result in risk to array - Array has been exposed to all flight environments
without any problems - Disposition is Use As Is
52Special Topic Contingency Plan for Partially
Deployed Solar Array Including Initial Power
Consumption if Solar Array Does Not Deploy (RFA
16.20)
. . . Bob Vernot EO-1 Systems Engineer
53List of Assumptions
- EO-1 goes to internal power prior to launch with
battery at 100 SOC at T-10 minutes - Consistent with launch countdown and narrow
launch window - Battery has nameplate capacity of 50 AH
- Battery has actual capacity of between 50 and 55
AH - SA collects zero power prior to attempted Sun
Acquisition - Outer panel is likely to collect some power
during coast and after tip-off. Power collection
not quantified. - Following contingency Sun Acquisition, SA
collects 192 W of power when lit - Consistent with IV curve predicts for outer panel
at 100º C, 28 VDC and sun intensity of 0.97
54List of Assumptions
- EO-1 orbit average load of 130 Watts until
heaters are required, then 198 Watts with heaters - Consistent with Thermal Balance Test data power
predicts - Current drain on Battery assumes above loads at
26.5 VDC - Reflects bus voltage with battery at minimum SOC.
Actual voltage will be higher - S/C requires heater power six hours after launch
- Consistent with Thermal predicts for thermostatic
control to 8 C - S-band transmitter on for 10 minutes per orbit
following heater power on - One contact per orbit
- Contingency sun pointing to within 10 degrees of
sun line - ACS should provide better than 1 degree accuracy
using AST
55Contingency Operations
- Assumes that all reasonable efforts to deploy SA
have been exhausted - All subsequent subsystem activation events to be
aborted - Operations to activate AST
- ACS to use AST to control attitude for undeployed
SA sun pointing (procedure under development) - Transmitter duty cycle minimized
- See Additional Considerations to follow
56Battery SOC through Sun Acquisition
57Worst Case Battery SOC for Undeployed SA
58Additional Considerations
- Additional power may be available.
- Possible 3-5 AH during coast phase of ascent
(6-10 SOC) - Possible 0-14 AH during despin, dependent upon
spin axis (not predictable before separation) - Contingency Sun Acquisition may occur prior to
worst case predict for Sun Acquisition - Ground management of heaters could greatly extend
life - Selectively allow areas of S/C to get cold
- Thermostatic control is set for 8 C, survival
temperatures are at -10 C - Many areas of S/C will settle to steady state
temperatures above survival limits, without
heaters. Further analysis is required. - Will report on this topic at the Red Team
Follow-up Review
59Bounded SOC for Undeployed SA
60Summary
- For nominal heater operation SOC is reduced by
10 per orbit - Under worst case conditions EO-1 can survive 10
orbits - With all heaters disabled SOC is reduced by
1.25 per orbit - Under worst case conditions EO-1 can survive 60
orbits(4 days) - Reality lies somewhere between these conditions
but is skewed toward the latter case if S/C is
allowed to go to survival temperatures
61Special Topic Oscillatory Starts on HSSR 7110
Switches
. . . Dave Speer Litton Amecom, ACS Lead
Designer
62Oscillatory Starts on HSSR 7110 Switches
- Background Description
- LVPC switched 28V power services can exhibit
3-amp current spikes, negative-going voltage
oscillations, or even lack of turn on for
sufficiently capacitive loads. Two known
examples are Autonomous Star Tracker (AST) and
Magnetic Torquer Bar (MTB) loads on ACE LVPC. - Problem was first recognized during MAP testing
with their AST power interface. The EO-1 MTB
power interface was tested for same problem due
to electrically similar load circuitry. - At high input voltage, there is an LVPC output
oscillation into the AST and MTB (refer to PR
346-20-4 and PR 483-20-1) reactive loads - At low to nominal bus voltage (22V to 28V), these
service-to-capacitive-load circuits turn on
normally. - At intermediate to high bus voltages (30V to
35V), these service-to-load circuits will
oscillate momentarily but then turn on after a
short delay (msecs).
63Oscillatory Starts on HSSR 7110 Switches
- Key Issue
- Whether the spiking/oscillating condition
damaged/overstressed components on either the
LVPC side of 28V power interface or on the
AST/MTB load side of power interface. - Analysis Test Results
- Voltage and current waveforms that have been
directly observed at the power-to-load interfaces
(on a scope) do NOT represent an overstress
condition. Max observed ?Vout was 56V, less
than 90V rating. Current spikes are 3A for 2
usec, less than 10A for 10 msec (one-shot)
rating. - Circuit simulations that drove current spiking
waveform into the MTB load circuitry did NOT
indicate an electronic component overstress
condition at the load side. Lab testing found
that continuous spikes/oscillations are not a
thermal overstress condition for 7110 switch - Action Taken
- Transient Suppression Assembly (TSA) box was
integrated in-line between AST 28V power service
and AST load, which eliminated spikes/oscillations
prior to first electrical integration and
operation of AST. So no overstress on load side
of AST power interface. - NO TSA box integrated in-line between MTB power
service and MTB load, and this interface still
experiences spikes/oscillations when turned on at
high (29V to 35V) bus voltages. - MTB service is turned ON at launch. Command
restrictions have been implemented such that the
MTB can only be turned on at VB ? 28V
64Context Diagram
65Special Topic Torquer Bar Potential Overstress
. . . Dave Speer Litton Amecom, ACS Lead
Designer
66Torquer Bar 15V Output Variations
- Background Description
- During normal Magnetic Torquer Bar (MTB)
operations, the dedicated MTB 15V output supply
voltage telemetry exceeded limits based on
manufacturers specification for balanced load
output regulation. Refer to PR 677-20-2 and PR
681-20-12. - Problem was first recognized when Interpoint
MTR2815D converter was being operated with very
light (less than 40 mA) load on 15V output, and
range (-110 to -190 mA) of load on -15V output. - Problem was repeated when this range of output
load conditions was entered on four separate
occasions during normal testing. When the
torquer bars were operated in this range, the
15V output varied by about 1, and the -15V
output varied by about 2. - Status
- Special MTB output characterization test was run
(WOA-915) to verify that - With less than 40 mA on the 15V output, the
behavior was independent of which individual bar
was operating in the -110 mA to -190 mA range. - With less than 40 mA on the 15V output, the
behavior was independent of whether the 3-bar
total current was in the -110 mA to -190 mA
range. - Amplitude of the 15V output variations was much
smaller as load on 15V output was increased
above 40 mA, and the output variation behavior
disappeared when the load on the 15V output was
above 70 mA.
67Torquer Bar 15V Output Variations
- Closure
- Four sets of Excel data files and output voltage
variation plots were sent to Interpoint for their
review and analysis. They were then able to
duplicate the same behavior that we saw, in their
laboratory set-up, under nearly the same type and
range of MTR output load conditions. They were
also able to confirm that the 15V output voltage
variations disappear when slightly more load
(above the 40 mA level) is added to the 15V
output. - Apparently, there is an output inductor inside
the MTR2815D that goes into a discontinuous
mode over a range of -15V loads when the 15V
load is small. The discontinuous mode of
operation affects the output voltage control loop
and causes small variations in the 15V output
voltages. If the 15V load is increased, or if
the -15V load is above or below the sensitive
range, then the output inductor goes back into
continuous mode, and the output variations stop. - Small MTB converter output voltage variations do
NOT represent a damaged condition, will NOT
affect the operation of the MTB drivers, and are
acceptable now that we understand them. Telemetry
limits will be expanded slightly to allow for the
observed behavior under a certain range of normal
operating conditions.
68Context Diagram