Resource LimitedProject Management
  • Vladimir Liberzon
  • spider_at_mail.cnt.ru

2
Introduction
  • We will discuss methodologies and techniques that
    are necessary for the proper project management
    when project resources are limited.
  • And to my knowledge they are always limited.
  • Please feel free to ask questions any time during
    my presentation.
  • We shall learn from each other and more
    discussions create more understanding.

3
Introduction
  • My name is Vladimir Liberzon.
  • I am a head of the leading Russian project
    management consulting company that
  • Implements project management systems at the
    different enterprises,
  • Manages projects for our customers,
  • Provides project management training,
  • Develops the most powerful project management
    software Spider Project.

4
Topics of Discussion
  • We will discuss
  • Organizing data for the proper project computer
    simulation and corporate resource management,
  • Resource constrained scheduling and Resource
    Critical Path,
  • Project Success Criteria,
  • Project Risk Simulation,
  • Success Driven Project Management.

5
Organizing data
  • It is Data Structure that defines the
    possibilities of simulating the situations
    occurring in the actual projects.
  • The main elements of a project computer model are
    project activities, activity dependencies,
    project resources and their assignments, project
    calendars, costs, and Work, Resource and Cost
    Breakdown Structures.
  • We will discuss the main elements of Data
    Structure that are vital for understanding the
    specific approaches to project simulation.

6
Activities
  • In the majority of well-known PM software
    packages project activities are characterized by
    their duration.
  • Besides duration, it is frequently necessary to
    set the activitys physical volume of work.
  • Activity volume can be measured in meters, tons,
    etc., planned work hours, percents or any other
    units.

7
Activities
  • Activity volume is often used as an initial
    activity information instead of duration. If
    assigned resource productivity is defined in
    volume units per hour then activity duration may
    be calculated during project scheduling.
  • Unlike activity duration activity volume does not
    depend on assigned resources.

8
Dependencies
  • Sometimes it is necessary to set more than one
    link between activities.
  • Besides the positive and negative time lags, it
    is useful to set volume lags, which is preferable
    in many cases.
  • The problem with time lags is that if the
    preceding work has started but is executed slower
    than it was planned, the time lag may be
    satisfied earlier than the planned volume of work
    is fulfilled.
  • The time lags call for special attention and
    regular adjustments.

9
Resources
  • Resources are divided into two classes
  • renewable (human resources and mechanisms) and
  • consumable (materials).
  • In most PM software packages, both are set
    together, differing only in setting the costs of
    their use - per work hour or per unit.
  • Thus you can not define that renewable resource
    spends materials during the work.

10
Complex Resources
  • Besides the individual resources one may set
    resource crews (we call them multi-resources) and
    resource skills (roles).
  • Multi-resources are the settled groups of
    resources working together (e.g. a team, a crew,
    a car with a driver, etc.).
  • Multi-resource can be assigned to activity which
    means assignment of all resources comprising the
    multi-resource.

11
Resource Skills
  • Resources sharing the same skills comprise
    Resource Assignment Pools.
  • Resources belonging to the same Pool are
    interchangeable though individuals in a pool may
    have different productivities performing the same
    activities.

12
Calendars
  • The calendars can be set for all activities,
    resources and time lags.
  • Availability of all these calendars is important
    for the proper project simulation.

13
Assignments
  • Assigning resources to activities implies the
    notion of a team - a group of resources working
    on an activity together.
  • The team can include individual resources,
    multi-resources and pools.
  • If the activitys initial information is work
    volume, one should set the productivity of at
    least one of assigned resources, to enable the
    calculation of the work duration. It should be
    noted that when the pools are assigned, activity
    duration can be calculated only in the process of
    scheduling.

14
Assignments
  • In assigning resource assignment pool, one should
    either set a total number of pool resources
    necessary for the execution of activity or their
    aggregate productivity.
  • Example a pool consists of the tip lorries (dump
    trucks) with different carrying capacity. One may
    set a number of lorries necessary for the
    execution of this activity or the aggregate
    productivity (dependent on capacity) of assigned
    tip lorries.

15
Assignments
  • If more than one team is assigned then resources
    belonging with the different teams work on an
    activity independently of each other.
  • One may set the volumes or duration of work for
    each team, but it is not obligatory.
  • When the volume or duration of assignment are not
    defined the team will continue working until the
    work on the activity is completed.
  • Such approach allows to simulate the shift work
    efficiently.

16
Assignments
  • Resources can be assigned to activities part
    time.
  • In this case one shall set percentage of assigned
    resources utilization together with resource
    quantity (not just the total percentage
    calculated by multiplying percents and
    quantities, that leaves the necessary amount of
    resources unclear - two resource units with 50
    utilization are equivalent to one resource unit
    used to its full capacity).

17
Assignments
  • Another useful option variable resource
    assignments.
  • Example
  • You may define that the number of resources that
    may be used at some work is between 2 and 4, and
    their workload should be not less than 40 and
    not more than 80.
  • In this case activity will start if two units of
    assigned resource are available not less than 40
    of their time, and the team may be increased if
    additional resources become available. Finishing
    other assignments resources may apply more of
    their time to the specified assignment but not
    more than 80.

18
Assignments
  • Resources can consume materials in the process of
    their work,
  • Besides materials can be assigned to activities
    or resource assignments directly.
  • In some projects it is necessary to simulate not
    only material consumption but also production of
    resources and materials on activities and
    assignments.

19
Cost
  • Usually it is not enough just to define activity
    and resource costs. It is necessary to know
    project expenses and revenues, what will be spent
    on wages, on machinery and equipment, on taxes,
    etc.
  • Sometimes it is necessary to allow for multiple
    currencies.
  • So there is a need to define and assign cost
    components.
  • Besides setting the cost of an hour of renewable
    resource work and the cost of material unit, it
    is necessary to be able to set the cost directly
    for activities and assignments.

20
Cost
  • People may be paid not only for the hours spent
    on the task but also by the quantity of work they
    have done.
  • It means that labor resource cost that is usually
    defined by the cost of work hour is not enough.
  • Frequently it is necessary to set costs for
    resource assignments (fixed or per unit of
    volume).
  • Cost of assignment is one example of setting
    contract costs for the project.

21
Centers
  • Setting costs for the components of the project
    expenses, materials and resources you may need to
    get different reports on the groups of cost
    components, materials and resources. That is why
    it is necessary to define Cost, Material and
    Resource Breakdown Structures or Centers.
  • Material center can include any group of
    materials.
  • Resource center can include any group of
    resources.
  • Cost center includes selected cost components.

22
Multiple Breakdown Structures
  • It is also very useful to have an opportunity to
    get project reports that aggregate project data
    different ways.
  • Usually we use at least three Work Breakdown
    Structures in our projects based on project
    deliverables, project processes and
    responsibilities.
  • The use of multiple breakdown structures allows
    not only to obtain different project reports as
    seen from the different standpoints, but also to
    provide that the project model is truly
    comprehensive.

23
Multiple Breakdown Structures
  • The use of resource breakdown structures is
    especially important in multi-project management.
  • In this case the matrix organizational structure
    determines the necessity of obtaining the reports
    on both Project and Functional Resource Breakdown
    Structures.

24
Project Archives
  • Another feature that is necessary for the proper
    project control is an ability to store project
    history.
  • The planners should be able to store project
    versions and to analyze the progress in project
    execution, comparing current project schedule not
    only with the baseline but with any other
    previous version too.
  • This possibility enables to assess the progress
    in project execution for the last week, last
    month, last year, compared to the baseline, etc.

25
Project Reference Books
  • Corporate project management has to be based on
    the corporate standards.
  • These standards shall include not only processes
    and documents that should be used in all projects
    but also estimates of the typical activity and
    assignment parameters.

26
Project Reference Books
  • Reference books that should be created should
    include at least
  • Activity cost and material requirements per
    activity volume unit,
  • Assignment cost and material requirements per
    activity volume unit,
  • Assignment productivity,
  • Assignment work load.

27
Fragnet Library
  • Another necessary thing to create a library of
    typical project fragnets.
  • Project fragnets usually describe typical
    processes and technologies that are used more
    than once.
  • Creating project computer models using the
    corporate library of typical fragnets will help
    to avoid inconsistencies and assures that the
    project model follows corporate standards.

28
Fragnet Library
  • A library of typical fragments is a very
    important tool for the development of corporate
    culture and management standards.
  • An interesting side effect of the use of typical
    fragnets library is the technology of work
    breakdown structure development not top-down, as
    usual, but bottom-up.
  • In such structure typical fragments serve as work
    packages. Since we commonly use several Work
    breakdown structures top-down and bottom-up
    technologies are used in parallel, complementing
    each other.

29
Resource constrained schedulingand Resource
Critical Path
  • The problems solved with the help of project
    management software usually include
  • Project scheduling without the limitations of
    resources taken into the consideration,
  • Project resource constrained scheduling (resource
    leveling),
  • Determination of critical path and time float for
    project activities,
  • Determination of the project requirements for
    finance, materials and equipment for any time
    period,

30
Resource constrained schedulingand Resource
Critical Path
  • Determination of renewable resources utilization
    in time,
  • Risk analysis and development of the project
    schedule and other project characteristics
    allowing for the risks,
  • Project performance measuring,
  • Project performance analysis and forecasting main
    project parameters.

31
Resource constrained schedulingand Resource
Critical Path
  • The problem of project schedule development
    without allowing for resource constraints has a
    correct mathematical solution (critical path
    method), which would be the same for all PM
    packages, provided that initial data are
    identical.
  • All other problems are solved using different
    approaches and yielding different results.

32
Resource constrained scheduling
  • Resource constrained schedules produced by
    different PM software are different.
  • The software that calculates shorter resource
    constrained schedules may save a fortune to its
    users.
  • Spider Project is based on advanced heuristics
    that consistently obtains shorter resource
    constrained schedules than using other PM
    software packages.

33
Resource constrained scheduling
  • The schedule stability is no less important,
    especially at the project execution phase.
  • Thats why Spider Project features an additional
    option - the support of the earlier project
    version schedule (the order of activity execution
    is the same as in selected earlier project
    schedule).

34
Resource Critical Path
  • Traditional notion of Critical Path works only in
    case of unlimited resources availability.
  • Let us consider a simple project consisting of
    five activities, presented at the next slide.
  • Activities 2 and 5 are performed by the same
    resource

35
Resource Critical Path
36
Resource Critical Path
  • At the next slide you will see the results of
    resource constrained scheduling (leveling).
  • Please pay attention to activities that became
    critical (red on the diagram).
  • Now delaying each of the activities 1, 2 and 5
    will delay the project finish date.
  • And though these activities are not linked we
    call them Resource Critical and their sequence
    comprise Resource Critical Path.

37
Resource Critical Path
38
MS Project Example
  • At the next slide you may find MS Project
    resource constrained schedule for the same
    project.
  • Please pay attention to the total slack figures
    and which activities were considered as critical.
  • Unfortunately resource constrained floats are not
    calculated not only by MS Project but by other
    popular PM software as well.

39
MS Project Example
40
Resource Critical Path
  • In many projects it is necessary to simulate
    financing and production, and calculate project
    schedules taking into account all limitations
    (availability of renewable resources, material
    supply and financing schedules).
  • True critical path should account for all
    schedule constraints including resource and
    financial limitations.

41
Resource Critical Path
  • We call it Resource Critical Path (RCP) to
    distinguish it from the traditional
    interpretation of the critical path definition.
  • The calculation of RCP is similar to the
    calculation of the traditional critical path with
    the exception that both early and late dates (and
    corresponding activity floats) are calculated
    during forward and backward resource (and
    material, and cost) leveling.

42
Resource Constrained Floats
  • Activity resource constrained floats have one
    large advantage over the total floats calculated
    by most PM software. This advantage is
    feasibility.
  • Activity resource constrained float shows the
    period for which activity execution may be
    postponed within the current schedule with the
    set of resources available in this project.

43
Resource Critical Path and Critical Chain
  • It appears that by adding financial and supply
    constraints to the Critical Chain definition as
    well as the way of the Critical Chain
    calculation, we will obtain something very
    similar to RCP.
  • Thus the proven technology of project management
    based on RCP that is described further may be of
    particular interest for the Critical Chain theory
    supporters.

44
Project Success Criteria
  • If project success criteria are set as finishing
    project in time and under budget then proper
    decision making will be complicated.
  • Project managers will not be able to estimate the
    effect of their decisions to spend more money but
    to finish the project earlier.
  • If some project is business oriented then this
    project has to have business criteria of its
    success or failure.

45
Project Success Criteria
  • One of potential options to set the profit that
    should be expected at some point in time basing
    on the forecast of the profit that will be
    obtained after the project will deliver its
    results.
  • Such success criterion will permit to weight time
    and money making managerial decisions.

46
Project Success Criteria
  • At the next slide you may see the project
    schedule that is calculated without allowing for
    project financing and supply restrictions.
  • There are periods when project has no money to
    proceed and necessary materials are absent.
  • But if project manager will find money and
    materials then total profit to some imposed date
    will be close to 225,000.

47

48
Project Success Criteria
  • If to calculate project resource, financing and
    supply constrained schedule than total profit
    will become more than 16,000 less.
  • Maybe it will be reasonable to borrow 41,000 for
    ten days or to find some other solution?
  • To be able to weight options and to choose the
    best it is necessary to simulate not only
    expenses.

49

50
Risk Simulation
  • Our experience of project planning shows that the
    probability of successful implementation of
    deterministic project schedules and budgets is
    very low.
  • Therefore project planning technology should
    always include risk simulation to produce
    reliable results.
  • Risk simulation may be based on Monte Carlo
    simulation or use three scenarios approach that
    will be described further.

51
Risk Simulation
  • Monte Carlo simulation is very time consuming and
    not practical for the large projects.
  • Current practice of its implementation mostly do
    not consider correlation between activity
    duration and cost estimates that exists if
    activities are performed by the same resources,
    do not consider risk events that may change a set
    of project activities.

52
Risk Simulation
  • Even if everything is properly simulated the
    number of necessary iterations is too high for
    receiving reliable results in the reasonable
    time.
  • A project planner may be happy with the
    probability estimates that has plus or minus 10
    accuracy but only if the error will be stable. If
    it may change from one calculation to another
    then these estimates can not be used as
    performance management tool.

53
Risk Simulation three scenarios approach
  • A project planner obtains three estimates
    (optimistic, most probable and pessimistic) for
    all initial project data (duration, volumes,
    productivity, calendars, costs, etc.).
  • Risk events are selected and ranked using the
    usual approach to risk qualitative analysis.
  • Usually we recommend to include risk events with
    the probability exceeding 90 in the optimistic
    scenario, exceeding 50 in the most probable
    scenario, and all selected risks in the
    pessimistic scenario.

54
Risk Simulation three scenarios approach
  • These data are used to calculate optimistic, most
    probable and pessimistic project schedules and
    budgets.
  • The most probable and pessimistic project
    scenarios may contain additional activities and
    costs due to corresponding risk events and may
    employ additional resources and different
    calendars than the optimistic project scenario.

55
Risk Simulation three scenarios approach
  • As the result project planner obtains three
    expected finish dates, costs and material
    consumptions for all major milestone.
  • They are used to rebuild probability curves for
    the dates, costs and material requirements.
  • Defining desired probabilities of meeting project
    targets a project planner obtains desired finish
    dates, costs and material requirements for any
    project deliverable.

56
Risk Simulation setting targets
  • There is a preferable interval for setting
    project targets that is defined by market
    competition.
  • Lets consider an example
  • Some company delivers projects that bring her
    10,000 profit per project if the project is
    successful.
  • Unsuccessful project means 10,000 lost.

57
Risk Simulation setting targets
  • Lets create a table with the following data
  • P - Probability of project success
  • M - Mean profit from the single project
  • N - Number of expected customers
  • T - Expected total profit

58
Risk Simulation setting targets
P M N T
100 10000 3 30000
90 8000 5 40000
80 6000 8 48000
70 4000 12 48000
60 2000 20 40000
59
Risk Simulation setting targets
  • For this company it is reasonable to propose
    project targets that will be met with the
    probability that is between 70 and 80.
  • These data form basis for the negotiations that
    may result in establishing other target dates,
    costs, material consumption.

60
Success Probabilities
  • In this case it is necessary to calculate the
    probabilities of meeting required project
    targets.
  • If they are reasonable then they may be accepted.
  • Probabilities to meet approved project targets we
    call Success Probabilities.

61
Baseline
  • Target dates do not belong to any schedule.
    Usually they are between most probable and
    pessimistic dates.
  • A set of target dates and costs (analogue of
    milestone schedule) is the real project baseline.
    But baseline schedule does not exist!
  • A schedule that should be used for setting tasks
    for project implementers is optimistic.

62
Critical Schedule
  • Project planner obtains not only the set of
    target dates but also a critical schedule a
    project schedule calculated backward from target
    dates.
  • Usually this schedule is based on most probable
    estimates of activity durations and the
    difference between current and critical dates
    shows current schedule contingency reserves
    (buffers).
  • At the next slide critical schedule is shown in
    blue.

63

64
Buffers
  • There are time, cost and material buffers that
    show contingency reserves not only for a project
    as a whole (analogue of Critical Chain project
    buffer) but also for any activity in the
    optimistic project schedule.
  • Time buffer for activity is defined as the
    difference between activity starts (finishes) in
    the current and critical schedules.
  • During project execution it is necessary to
    estimate if these buffers are properly utilized.

65
Success Probability Trends
  • The best way to measure project performance is to
    estimate what is going on with the project
    success probabilities.
  • If they rise it means that contingency reserves
    are spent slower than expected, if they drop it
    means that project performance is not as good as
    it was planned and corrective actions are needed.
  • In any case if the project meets project targets
    then corresponding success probabilities will
    reach 100 before project finish.

66

67
Success Probability Trends
  • Success probabilities may change due to
  • Performance results
  • Scope changes
  • Cost changes
  • Risk changes
  • Resource changes
  • Thus success probability trends reflect not only
    project performance results but also what is
    going on around the project.

68
Success Probability Trends
  • We consider success probability trends as the
    really integrated project performance measurement
    tool.
  • Success probability trends may be used as the
    only information about project performance at the
    top management level this information is
    sufficient for performance estimation and
    decision making.
  • We call the described methodology Success Driven
    Project Management.

69
Success Probability Trends
  • If project performance is estimated by success
    probability trends then project managers are
    encouraged to resolve uncertainties ASAP
  • This can increase success probabilities even with
    activity finish delays cost overruns.
  • Postponing problem activities leads to negative
    trends in success probabilities.
  • This attribute of success probability trends is
    especially useful in new product development
    project management.

70
Success Probability Trends
  • It is useful to set not one but several targets
    for the same project parameter.
  • In this case success probability trends will show
    to what interval of final results project is
    going.
  • In any case there are always several sets of
    target data for each project.
  • Lets discuss it using project budget as an
    example.

71
Project Budgets
  • The first project budget is the optimistic budget
    that is set as a target for the project team.
  • The second one is the budget of the project
    management team that includes approved
    contingency reserves.
  • The third budget includes management reserves and
    may be called executive budget.
  • And at last the project may have contract cost
    that includes profit.

72
Project Budgets
  • Optimistic budget has zero success probability.
  • As for others it is useful to know what is going
    on with the probabilities to meet project
    management team budget, executive budget and
    contract cost.

73
Critical Chain
  • You may notice that the approaches to the project
    management discussed today are similar to those
    that are used in Critical Chain Project
    Management.
  • I do not see the difference between Resource
    Critical Path and Critical Chain except I have
    never met the description of the Critical Chain
    calculation.

74
Critical Chain
  • Both the SDPM and the Critical Chain theories
    recommend project managers to use optimistic
    estimates of the project data to set the tasks
    for the project manpower and to control
    contingency and management reserves. SDPM also
    offers a technique for calculating necessary
    contingency reserves, while CCPM suggests to use
    qualitative estimates.

75
Critical Chain
  • Unlike Critical Chain theory SDPM approach states
    that
  • RCP can change during the project execution,
  • multitasking is sometimes necessary, and
  • critical (drum) resources can be different at the
    different stages of the project life cycle.

76
Critical Path
  • RCP and classical Critical Path are the same if
    project resources are unlimited.
  • If project resources are limited then the
    classical Critical Path is useless and total
    floats calculated without considering resource
    limitations are not feasible.
  • Really critical activities belong to Resource
    Critical Path and resource constrained floats
    show real activity time reserves.

77
Conclusions
  • Resource Limited Project Management requires
    implementing special techniques that include
  • Organizing data in a way that supports proper
    resource work simulation and application of
    corporate norms and standards.
  • Creating a set of reference-books and a fragnets
    library that are obligatory for creating project
    computer models.

78
Conclusions
  • Calculating Resource Critical Path and resource
    constrained floats.
  • Risk assessment and simulation.
  • Defining target dates and costs (and
    corresponding contingency reserves) that may be
    achieved with reasonable probability.
  • Recalculating the current probabilities of
    meeting project targets during project execution
    and analyzing success probability trends.
  • Applying corrective actions if these trends are
    negative.

79
Thank you
  • Thank you for your participation.
  • I am looking forward to your feedback and
    comments.
  • My E-mail spider_at_mail.cnt.ru
  • Vladimir Liberzon
  • ???????? ????????