Title: Layer 0 Installation and Commissioning
1Layer 0 Installation and Commissioning
This talk will cover plans for pre-installation
work in the 2004 shutdown, final installation in
2005, and post-installation hardware
commissioning
- We want to maximize physics from the experiment
minimal down time and efficient use of shutdowns - The Fall 2004 shutdown is expected to be rather
long (gt13 weeks) but manpower may be limited.
The 2005 shutdown may be shorter. - We wish to refurbish and reinstall the H disks so
that we have close to 100 functionality in the
remaining device. This could be done in 2004 but
will be difficult in 2005 - We want to be sure that layer 0 can be installed
safely and easily
2Fall 2004 Plans
- We plan to install and operate a 4-hybrid SVX4
string during the 2004 shutdown. This will allow
us to test a mixed SVX2/4 readout system with the
associated controls and download software. It
will also test our grounding isolation scheme
with new adapter cards - Test operating the cooling system at lower
temperature - Reroute H disk cabling consistent with L0 scheme
- We are also considering removing and refurbishing
the H disks. This depends mainly on personnel
availability. If we do this we can also - Photograph H-disk and support cylinder regions
- Survey installation clearances
3Fall 2004 SVX4 String Infrastructure
- Moving counting house
- Weiner Power Supply
- VESDA/Cooling interlock chassis
- Cathedral
- Mini Fuse Panel
- Calorimeter Gap (Horseshoe)
- Adapter Card
Need to move 3 H disk cables 16C1 ? 10C1 16C2
? 24C2 17C2 ? 18C1
4H Disk Refurbishment
This would involve removing the 4 disks,
producing two 100 disks and 2 poorer disks,
and reinstallation. The goal is to avoid effort
in the (shorter) 2005 shutdown.
- Mechanical work in the gap
- H-disk removal requires that the beryllium pipe
be disconnected from the EC pipe at one end. - In addition, a piping section would need to be
removed outside the EC to allow the EC pipe to be
moved 39 outward (the same 39 by which the EC
is opened). - No beam pipe cutting will be necessary.
EC
5H Disk Refurbishment
- Detector work would be done at SiDet
- Estimate 12 weeks (including end effects), 1.5
techs - Part of this decision will be based on
availability of visas for the Moscow State group
(3 people for 2-3 months) they are not likely
to be available next summer. - Fixtures for H disk alignment and assembly are
available in Lab A - Decision can be made in late August based on
manpower and schedule
6Installation Clearance
Run 2a beam pipe and silicon
L0 and Run 2b beam pipe
7Installation Clearance
- We continue to work to maximize the installation
clearance
Run2a flange
minimum clearance
8Installation Clearance
- We can gain enough clearance to match the Run2a
flange by - Removing mesh spacers between analog cables in
area of maximum radius slight increase in
capacitance - Tests show that this does not affect signal/noise
- Only needs to be done in the outer (B) layer
- Removing spacers between digital jumper cables
- Using ½ oz copper and thinner adhesive for the
digital cables - If H disks are removed we will use the
opportunity to survey z0 aperture
9Installation plan
- Remove H disks
- Layer 0 slides through the North End Calorimeter
pipe - Is carried by a cradle (not shown) which spans
the EC-CC gap - Left end engages the current beryllium beam pipe
which serves to guide L0 through the SMT
10Installation Conceptual Design
Layer 0
Run2a pipe
cradle
11Cabling and Connections
- We are making a mock up of the SMT support end
region to understand space, connections and
cabling
junction cards connected in horizontal position
then rotated 90 degrees
Digital cables in installation position
D0SMT Support
12Online Software
- Online layer 0 occupies existing H wedge
electronics slots so much of the existing control
interface can be used - Data format should be identical to SVX2
- Change database and download GUI to accommodate
extra SVX4 bits - Add monitoring of Weiner power supplies
- STT changes for additional inputs
- L3 tracking to accommodate additional silicon
layer - Much of this will be tested in the Winter using
the SVX4 test strings installed this Fall.
13 Conclusions
- We are planning to use this Falls shutdown to
prepare for and simplify Layer 0 installation
next summer - We believe that we can further reduce the
detector radius to insure that there will be
sufficient clearance for installation. - We have a conceptual design for the installation
procedure and associated fixturing. - Hardware commissioning should be straightforward
given shared downstream electronics and
experience with SVX4 strings installed this Fall.
14Cables in Dense Region