Layer 0 Installation and Commissioning - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Layer 0 Installation and Commissioning

Description:

Weiner Power Supply. VESDA/Cooling interlock chassis. Cathedral. Mini Fuse Panel ... Add monitoring of Weiner power supplies. STT changes for additional inputs ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 15
Provided by: ronaldl150
Category:

less

Transcript and Presenter's Notes

Title: Layer 0 Installation and Commissioning


1
Layer 0 Installation and Commissioning
This talk will cover plans for pre-installation
work in the 2004 shutdown, final installation in
2005, and post-installation hardware
commissioning
  • We want to maximize physics from the experiment
    minimal down time and efficient use of shutdowns
  • The Fall 2004 shutdown is expected to be rather
    long (gt13 weeks) but manpower may be limited.
    The 2005 shutdown may be shorter.
  • We wish to refurbish and reinstall the H disks so
    that we have close to 100 functionality in the
    remaining device. This could be done in 2004 but
    will be difficult in 2005
  • We want to be sure that layer 0 can be installed
    safely and easily

2
Fall 2004 Plans
  • We plan to install and operate a 4-hybrid SVX4
    string during the 2004 shutdown. This will allow
    us to test a mixed SVX2/4 readout system with the
    associated controls and download software. It
    will also test our grounding isolation scheme
    with new adapter cards
  • Test operating the cooling system at lower
    temperature
  • Reroute H disk cabling consistent with L0 scheme
  • We are also considering removing and refurbishing
    the H disks. This depends mainly on personnel
    availability. If we do this we can also
  • Photograph H-disk and support cylinder regions
  • Survey installation clearances

3
Fall 2004 SVX4 String Infrastructure
  • Moving counting house
  • Weiner Power Supply
  • VESDA/Cooling interlock chassis
  • Cathedral
  • Mini Fuse Panel
  • Calorimeter Gap (Horseshoe)
  • Adapter Card

Need to move 3 H disk cables 16C1 ? 10C1 16C2
? 24C2 17C2 ? 18C1
4
H Disk Refurbishment
This would involve removing the 4 disks,
producing two 100 disks and 2 poorer disks,
and reinstallation. The goal is to avoid effort
in the (shorter) 2005 shutdown.
  • Mechanical work in the gap
  • H-disk removal requires that the beryllium pipe
    be disconnected from the EC pipe at one end.
  • In addition, a piping section would need to be
    removed outside the EC to allow the EC pipe to be
    moved 39 outward (the same 39 by which the EC
    is opened).
  • No beam pipe cutting will be necessary.

EC
5
H Disk Refurbishment
  • Detector work would be done at SiDet
  • Estimate 12 weeks (including end effects), 1.5
    techs
  • Part of this decision will be based on
    availability of visas for the Moscow State group
    (3 people for 2-3 months) they are not likely
    to be available next summer.
  • Fixtures for H disk alignment and assembly are
    available in Lab A
  • Decision can be made in late August based on
    manpower and schedule

6
Installation Clearance
Run 2a beam pipe and silicon
L0 and Run 2b beam pipe
7
Installation Clearance
  • We continue to work to maximize the installation
    clearance

Run2a flange
minimum clearance
8
Installation Clearance
  • We can gain enough clearance to match the Run2a
    flange by
  • Removing mesh spacers between analog cables in
    area of maximum radius slight increase in
    capacitance
  • Tests show that this does not affect signal/noise
  • Only needs to be done in the outer (B) layer
  • Removing spacers between digital jumper cables
  • Using ½ oz copper and thinner adhesive for the
    digital cables
  • If H disks are removed we will use the
    opportunity to survey z0 aperture

9
Installation plan
  • Remove H disks
  • Layer 0 slides through the North End Calorimeter
    pipe
  • Is carried by a cradle (not shown) which spans
    the EC-CC gap
  • Left end engages the current beryllium beam pipe
    which serves to guide L0 through the SMT

10
Installation Conceptual Design
Layer 0
Run2a pipe
cradle
11
Cabling and Connections
  • We are making a mock up of the SMT support end
    region to understand space, connections and
    cabling

junction cards connected in horizontal position
then rotated 90 degrees
Digital cables in installation position
D0SMT Support
12
Online Software
  • Online layer 0 occupies existing H wedge
    electronics slots so much of the existing control
    interface can be used
  • Data format should be identical to SVX2
  • Change database and download GUI to accommodate
    extra SVX4 bits
  • Add monitoring of Weiner power supplies
  • STT changes for additional inputs
  • L3 tracking to accommodate additional silicon
    layer
  • Much of this will be tested in the Winter using
    the SVX4 test strings installed this Fall.

13
Conclusions
  • We are planning to use this Falls shutdown to
    prepare for and simplify Layer 0 installation
    next summer
  • We believe that we can further reduce the
    detector radius to insure that there will be
    sufficient clearance for installation.
  • We have a conceptual design for the installation
    procedure and associated fixturing.
  • Hardware commissioning should be straightforward
    given shared downstream electronics and
    experience with SVX4 strings installed this Fall.

14
Cables in Dense Region
Write a Comment
User Comments (0)
About PowerShow.com