Title: Partners in Bridge and Asset Management


1
Partners in Bridge and Asset Management

Richard Lee Floyd, PE Bridge Inspection / BMS
Engineer
2
Nationwide Bridge Construction Trend
3
South Carolina Bridge Construction Trend
4
Some Basic Bridge Statistics
As of August 1, 2002
  • 9,106 Bridges (8,255 state owned)
  • 1,259 Structurally Deficient Bridges (995 state
    owned)
  • 840 Functionally Obsolete Bridges (794 state
    owned)
  • 499 Load Restricted Bridges (209 state owned)
  • 32 Closed Bridges (18 state owned)

5
Bridge Life Cycle Before BMS
Maintenance/Operations
Programming Process Using Sufficiency Ratings
Pre-Construction
Construction
6
The Bridge Programming Process Using BMS..
7
Sufficiency Ratings
Sufficiency Ratings for Direct
Prioritization
8
Bridge Management and Programming _at_ SCDOT
  • SCDOT Bridge Management System
  • NBI Data (Early 1970s)
  • BMS Data (Fall 1993)
  • SCDOT Strategic Plan
  • Engineering Directive M-33 PC-30
  • (4/1/1999 and revised 7/1/2000)

9
Bridge Life Cycle After BMS
Maintenance/Operations
Programming Process Using BMS
Pre-Construction
Construction
10
Bridge Data QA/QC Process
11
Bridge and Programming Process
12
Bridge Programming Process
  • Step 1 Monetary Parameters and Special
    Considerations
  • Step 2 Preliminary Bridge Projects Lists from
    BMS (Review of Input and
    Output)


  • Step 3 Bridge Projects Lists from BMS
  • Step 4 Bridge Projects Lists from Districts
  • Step 5 Analysis of Lists from Steps 3 and 4


    (Bridge
    Projects Review Team)
  • Step 6 Preliminary Bridge Projects Programming
    List
  • Step 7 Final Bridge Projects Programming List

    (Approval from State Highway
    Engineer)

13
Goals of Improved Project Prioritization
  • Getting the most benefit for the

!
14
Some Bridge Programming Statistics
As of December 31, 2001
  • BMS Programming Rate 89 (Goal 75)
  • Average BMS Ranking 187
  • Average ADT 3,660
  • Average Bypass Length 6 miles

15
Results of 10 Year Needs Study(Grace and Pearman
not included)
16
20 Year Needs Study and Analysis
17
Results of 20 Year Needs Study and
Analysis(Grace and Pearman not included)
1,750,000,000
18
Structurally Deficient Bridge Deck Area Trends
19
Bridge Management
Asset Management
20
Asset Management
More Critically Important Than
Ever!
GASB Statement 34
For More Information Director of
Maintenance Intranet Site and also in the
Bridge Maintenance Section
21
Bridge Asset Security
22
Purpose
  • Basic bridge components
  • Definitions and symbols
  • Bridge behavior schematics and critical locations
  • Additional bridge details and critical locations
  • Locations of example bridges
  • Provide explanations
  • SCDOT contacts
  • Answer questions

23
Questions and Maybe Some Answers
???