Selfmonitoring programme for a Swedish power plant - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Selfmonitoring programme for a Swedish power plant

Description:

... of nitrogen oxides, sulphur dioxide, dust, oxygen, and carbon monoxide ... Continuous monitoring of nitrogen oxides, oxygen, and carbon monoxide ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 13
Provided by: hansrolan
Category:

less

Transcript and Presenter's Notes

Title: Selfmonitoring programme for a Swedish power plant


1
Self-monitoring programme for a Swedish power
plant
  • Hans-Roland Lindgren
  • Director Swedish EPA

1
2
Monitoring programme - Linköping power plant
  • Recipient monitoring (air, water)
  • External inspections (boiler, CFC-inst. etc.)
  • Reporting
  • Annexes (drawings of
    boilers, emission points, treatment plants and
    coal storage area)
  • General information
  • Description of the plant and its emissions
  • Permit conditions
  • Environmental monitoring
  • Process monitoring (instructions and recording)

2
Hans-Roland Lindgren
3
The plant and its emissions
  • Waste and hazardous waste disposal
  • Noise
  • Fuels (amounts, types and storage)
  • Chemicals (urea for NOx reduction, boiler and
    water treatment chemicals)
  • Location
  • Coal-, oil-, wood boilers and turbines
  • Air emission sources and its control
  • Description of water system and water treatment

Hans-Roland Lindgren
3
4
Air emission monitoring of coal boiler
  • Continuous monitoring of nitrogen oxides, sulphur
    dioxide, dust, oxygen, and carbon monoxide
  • Once a year as part of external inspections are
    dinitrogen oxide, ammonia and phthalates
    monitored
  • Lead, cadmium and zinc once a month on a
    collective sample and during inspections

Hans-Roland Lindgren
4
5
Air emission monitoring of oil boiler
  • Continuous monitoring of nitrogen oxides, oxygen,
    and carbon monoxide
  • Once a year as part of external inspections are
    dinitrogen oxide, ammonia and dust monitored
  • Sulphur is monitored in oil at every delivery

Hans-Roland Lindgren
5
6
Monitoring of condensate from wood boiler
  • Continuous monitoring of ammonium nitrate, pH and
    water flow
  • Twice a year and in addition as part of external
    inspections are suspended solids measured

Hans-Roland Lindgren
6
7
Monitoring of water from ash handling, cooling
and oil storage
  • Suspended solids, pH and total sulphur is
    monitored in water from ash separator once a year
  • Flow (continuously) and total extractable organic
    compounds during water pumping from oil storage
    by spot samples
  • Daily average flow of cooling water during
    periods of power generation (May-Sept.)

Hans-Roland Lindgren
7
8
Process monitoring
  • Recording of operational parameters
  • Recording of calibrations and maintenance
  • Recording of disturbances in the production of
    importance for the environment
  • Instructions for operation and maintenance of
    boilers
  • Instructions for operation and maintenance of air
    emission control equipment
  • Instructions for calibration of monitoring
    equipment

Hans-Roland Lindgren
8
9
Environment quality monitoring
  • Joint ambient air quality monitoring through the
    Association for Air Quality in the County to
    which the company contributes
  • Water recipient quality monitoring through Motala
    Ström Water Association

Hans-Roland Lindgren
9
10
External inspections
  • Measurement of combustion and air emission
    parameters on all boilers and spot samples on all
    waste waters
  • Report on all inspected objects. Results,
    evaluation, defects and planned changes
  • Inspection of installations and records. Changes
    in production etc. which influence emissions are
    recorded
  • Monitoring of noise is made
  • Inspection and calibration of monitoring equipment

Hans-Roland Lindgren
10
11
Reporting
  • Regular reporting every three months not later
    the 2 months of the end of the period
  • Reporting on inspections within 2 months after
    inspection
  • Reporting on disturbances and accidents
    immediately
  • Yearly reporting within 2 months after end of
    year

11
Hans-Roland Lindgren
12
Yearly reporting
  • Monitoring results and emissions, accuracy of
    installed monitoring equipment
  • Comments on permit conditions and possible
    actions
  • CFC-reporting
  • Signature
  • General information
  • Description of operations
  • Permits and permit conditions
  • Environmental report
  • Production time and conditions

12