CRP Regional Water Wastewater Servicing Project

Description:

CRP Regional Water / Wastewater Servicing Project. Sub-Regional Information Session ... Without conservation, Black Diamond, Turner Valley, High River, Okotoks, and ... – PowerPoint PPT presentation

Number of Views:18
Avg rating:3.0/5.0
Slides: 29
Provided by: bengri
Category:

less

Transcript and Presenter's Notes

Title: CRP Regional Water Wastewater Servicing Project


1
CRP Regional Water / Wastewater Servicing Project
  • Sub-Regional Information Session
  • Service Area C
  • Airdrie, AB
  • May 23, 2007

2
Overview of Presentation
  • Review of Drivers for Project
  • Review of Project Objectives
  • Growth Scenario Examined
  • Overview of Servicing Alternatives
  • TBL Analysis of Alternatives
  • Next Steps in Project

3
Project Drivers
  • Growth
  • Water and wastewater infrastructure under
    pressure from rapid growth in region
  • New development limited by availability of water
  • Questions regarding sustainability and
    environment protection in region
  • Growth in region proceeding without a regional
    plan

4
Project Drivers
  • Water Availability
  • South Saskatchewan River Basin Water Management
    Plan (SSRB WMP) proposes moratorium on new water
    licenses in Bow River Basin
  • Water resources available to communities will be
    limited to amount of existing licenses
  • Additional water will need to be obtained
    through
  • Water license transfers
  • Purchase of raw water
  • Purchase of treated water
  • Groundwater extraction (where applicable)

5
Project Drivers
  • Public Health Protection
  • Alberta Environment Waterworks Facility
    Assessments revealed that smallest systems at
    highest risk for compliance violations
  • Small systems have difficulty attracting and
    retaining qualified operators
  • Regional systems identified by Province as a
    means of addressing these concerns grant program
    in place

6
Study Objectives
  • Develop sustainable water and wastewater
    servicing solutions for Calgary Region
  • Develop technical servicing options
  • Infrastructure
  • Water management approaches
  • Evaluate alternatives using triple bottom line
    decision approach

7
Growth Scenario Examined
  • No Regional Land Use Plan in place
  • Future growth scenario examined based primarily
    on Calgary Regional Economic Forecast (CREF)
    Transportation Model
  • CREF data augmented by community planning
    documents
  • Individual developments and ASPs not considered

8
Land-Use Neutral Growth Scenario
  • We are comparing the relative merits of
    alternative servicing options for this single
    growth scenario
  • Our analysis does not include assessing the
    desirability or nature of the growth
  • Coordination needed with Regional Growth and
    Sustainability Framework

9
CREF Model
  • Covers all of CRP except Banff, Canmore, MD of
    Bighorn, Nanton, portions of Wheatland County

10
Servicing Zones
  • Growth in CREF zones summed and concentrated at
    Service Nodes

11
C 2030 Service Population
  • Airdrie 63,500
  • Crossfield 3,850
  • Rocky View North 4,075
  • Rocky View Central 29,823

12
Key Issues Water Availability
  • All new developments in MDs and Counties will
    need to obtain water license or external supply
  • Without conservation, Black Diamond, Turner
    Valley, High River, Okotoks, and Nanton will
    require additional water licenses
  • With 30 conservation, only Okotoks will require
    an additional licence for 30-yr horizon
  • Adequate license capacity available on a regional
    basis for 2075 demands

13
Analysis of Alternatives
  • Focus of study is to develop a sustainable
    servicing plan
  • Alternatives will be evaluated using Triple
    Bottom Line objectives

14
Triple Bottom Line Objectives
  • Environmental protect and preserve the local
    environment, minimize adverse impacts on water
    quality, minimize energy usage and conserve
    resources.
  • Social - protect public health, result in land
    use and growth patterns that enhance the quality
    of life for residents of the Calgary region.
  • Economic cost effective solutions that enhance
    the economic development of CRP member
    communities.

15
Draft Decision Framework
16
Area C Water Alternatives
  • Airdrie will continue with regional supply from
    Calgary
  • Crossfield will continue with regional supply
    from Anthony Henday system
  • Servicing options centered around water supply
    for future growth in MD of Rocky View

17
Area C Water Alternatives
  • Supply from Calgary
  • Supply from Rocky View Water Co-op WTP
  • Supply from Kneehill Regional System
  • Rocky View Central 29,823 people

18
Area C - Water
19
Area C - Water
20
Area C - Water
21
Area C1 Wastewater
  • Pipeline connecting Crossfield to Airdrie-Calgary
    line
  • Upgraded WWTP in Crossfield
  • (Airdrie continues with regional system from
    Calgary)

Crossfield 3,850 people Rocky View North
4,075 people
22
Area C1 - Wastewater
23
Area C1 Wastewater
24
Area C2 Wastewater
  • New pipeline connecting Rocky View Central to
    Calgary
  • Existing Rocky View pipeline and upgraded WWTP in
    Langdon
  • Rocky View Central 29,823 people

25
Area C2 - Wastewater
26
Area C2 - Wastewater
27
Next Steps
  • Communities to review TBL results
  • Which alternative best addresses individual needs
    and constraints?
  • Coordinate Servicing Study and Regional Growth
    and Sustainability Framework
  • Establish servicing partnerships
  • Begin preliminary engineering

28
Questions
David Pernitsky Project Manager CH2M HILL
(403) 237-9300 David.Pernitsky_at_ch2m.com Natalie
Guy Project Engineer Natalie.Guy_at_ch2m.com