Title: PIE Needs and Relevant Facilities at Cadarache
1PIE Needs and Relevant Facilities at Cadarache
- Coordinated and Presented by
- Alice Ying
With contributions from J. Furlan, V. Massaut,
Y. Poitevin, S. Reyes, A. Tesini, M. Youssef, and
WSG members
TBWG-16 Nov. 17 2005 Beijing, China
2Assumptions
- Parties believe that the post-irradiation
examination (PIE) of the test blanket module
(TBM) is an important part of the testing
program. - It has been recommended that an Annex be included
to the ITER Hot Cell for TBM PIE and be located
close to the ITER HCB or near ITER. - The TBWG has highlighted that such an enterprise
can be a collaborative effort between the parties
and encouraged a prior agreement and official
framework concerning the items of intellectual
property to be established.
3TBM PIE Scenarios (Revised)
Scenario
- TBM shipped back to the country of origin or
partner party after testing in ITER - Specimen Preparation PIE
- Specimen Preparation Only (PIE done at the host
country) - Specimen Preparation limited PIE at ITER site
(i.e., ceramic breeder pebble bed integrity)
- Have not reached a recommended reference scenario
to TBWG on TBWG 16 - However, most WSG task leaders favor option 4
and/or option 2
4Is it practically feasible to transport the
entire TBM back to the country of origin?
- Transfer to the country of origin transportation
provision will have to conform to the
international transport regulations. Casks
licensed to transport tritium (in bottles) exist
for small specimens, at least, so that it seems
to be possible either to extend their content to
the tritiated spices (in a primary container ?)
and to design a proper adapted cask.
5ONEDANT Transport Model for Dose Calculations
Goal to estimate thickness of steel and/or lead
needed to reduce the cask surface does rate to 2
micro-Sv/h
- Due to the time constraint, Gamma ray transport
calculations were performed only for the
dominating radioactive element of Mn54 found in
the ferritic steel (half life time 1 year)
PbLi was drained out of the TBM before
transportation. The model includes the W armor,
the FS structures and the SiC layers.
Figure shows the neutronics model for the case of
20 cm of lead shielding within a 2 cm of
steel The dose has been tallied in the first cm
of air around the case, we have used the highest
dose value in the air zone that is closer to the
FW (left side of the figure)
DCLL TBM structures
2 cm thick steel case
20 cm lead
6- Two shielding concepts investigated, one uses
only a steel case of various thicknesses around
the TBM - Another case assumes a 2 cm thick steel
container filled with lead shielding at
different thicknesses - In the case of steel, 40 cm are needed to reduce
the dose below 2 ?Sv/hr (mass of container
9 tonnes) - In the second case Pb thickness of 20 cm would
reduce the dose below the allowed limit (total
mass of steel case and Pb shielding 5 tonnes)
7TBM Cooling may not be an issue after 1 day after
shutdown (DCLL)
8Issues Concerning TBM Transports
- Transfer of TBM parts towards other facilities
should be submitted to constraints such as - use of casks approved to circulate on public road
networks (even from ITER to Cadarache centre), - specific TBM content (including Beryllium)
included in the approved content of these casks, - acceptance of possible tritium outgassing during
transportation, - capability of ITER to dock those casks.
9Outline
- Relevant PIE Facilities at Cadarache
- PIE Needs
- Review of Basic Operational Procedure/ Processes
Involved in PIE - Route to Reference Scenario Definition
- Schedule
- Operational Procedure
- PIE Categories
- Criteria?
- Burdens
10Relevant Facilities at Cadarache LECA-STAR
- This facility is dedicated to irradiated fission
fuel studies. It offers a large panel of means
and long experience related to preparation and
examination of experimental devices. That is to
say, roughly - numerous hot cells, including large ones (up to 9
m x 3 m), - heavy loads handling (up to 60 t in the facility
and 2 t in the hot cells), - adapted in-cell tools (fine visual inspection,
cutting (fine coarse), welding, scientific
equipments for structural examination, ) - a team of experienced experts.
A half-port TBM weighs 2 t
11Relevant Facilities at Cadarache CHICADE
- This facility deals with chemical and
characterization studies of nuclear wastes. It
offers tools for destructive and non-destructive
survey and for radiochemical analyses. - Main basic equipments are various shielded
containments, a hot cell (so-called ALCESTE 7 m
x 6 m) and usual means to operate (heavy loads
handling, up to 15 t in the facility, depending
of the zone). - The facility, whose aim is different, has not
well adapted means nor experience to deal with
the requirements.
- Can this facility be used to accommodate any
unscheduled PIE? For example, can it be used as a
temporary storage until ITER HC becomes
available?
12Facilities at Cadarache Summary
- LECA-STAR has capacity to handle, dismantle and
sample large objects prior to performing
experimental tasks. Structural examination
equipments and know-how are available too but are
dedicated to irradiated fission fuel. - CHICADE offers hot surfaces and volumes but has
no experimental means well-adapted to the
requirements.
Need to know the sample size of the large objects
LECA-STAR Facility
13Action Items
- TBWG should take actions to finalize a reference
scenario (as well as an alternative if necessary) - Further study is scenario dependent, involving
the concerned units staffs in Cadarache. - WSG members to define Coarse cutting
specifications/requirements precision,
complexity, etc. - So that ITER can, in future, try to take TBM
requirements for a best compromise for a cutting
machine. - Or a cutting technique specific for the TBM.
14What is the most pressing issue?
- It should be noted that ITER site layout,
including the nuclear buildings, will be
finalized in 2006 so any TBM/PIE/HC relevant
issue which may impact the layout (HC and any
additional annex and relevant site services, in
particular) should be addressed soon by the TBWG.
- Per email message of Tesini to Ying dated Oct.
25, 2005
- Related immediate issue/action
- Establish PIE reference scenario including flow
path and associated operations - Recommend alternative option
15Scenario A
- Per email message of Tesini to Ying dated Oct.
25, 2005
16If TBMs transportation outside the ITER boundary
can be an issue
- With regard to PIE, possible component flow path
could be - a) TBM is removed from plug within the ITER HC,
packaged in suitable shielded container (safety,
Tritium, transport issues to be addressed) - b) TBM is delivered to LECI-PELECI facility
unless the on-site LECA-STAR can handle the TBM's
(for which Jackie's memo quotes 2 ton max
handling capacity). If possible (for size,
availability) usage of the LECA-STAR facility
appears preferable as it may help relax the TBM's
transportation issue (within the same site)
Concerning the heavy loads handling, just one
point to avoid confusion In the hot labs there
are generally two families of heavy loads
handling means those used to handle the casks
(outside the hot cells) able to lift several tens
of tons (60 t in LECA-STAR), and those dedicated
to handle things inside the hot cells (2 t in
LECA-STAR). (if it is possible to assume that
ITER site Cadarache centre belong to the same
site, avoiding transportation on the public
roads, constraints should still remain, but they
should be lighter on the cask's design and
licensing).
17- Concern
- It should be noted that ITER site layout,
including the nuclear buildings, will be
finalized in 2006 so any TBM/PIE/HC relevant
issue which may impact the layout (HC and any
additional annex and relevant site services, in
particular) should be addressed soon by the TBWG.
- Minimum Request to ITER HC Regarding the
capability of ITER HC to dock those casks - Space required for packaging six irradiated
half-port modules in suitable shielded containers
(safety,Tritium, transport issues to be
addressed) - Space and tools needed to accommodate above
operations - Tools
- Overhead crane and forklift/scissor jack with
rail for transferring TBM from port plug to
shielded container - Water cooling systems to remove decay heat (may
be necessary before one month after shutdown) - Space space for 6 shielded containers
18Scenario B
- per Furlans memo to Ying dated on Aug. 22, 2005
19If a half-port size TBMs transportation outside
the ITER boundary can be an issue
- Dismantle TBM previously in ITER hot cells,
producing medium size pieces. - The next step, needing accurate visual inspection
(corrosion cracks identification) and accurate
cutting methods, could be performed in a CEA hot
lab if not feasible in ITER. - This precise sampling of medium size specimens
could be performed in Cadarache (LECA-STAR or
CHICADE). Then the samples could be dispatched
from there to hot labs or to the Party if
requested, using small size casks.
20Further details on the capabilities of facilities
near Cadarache
- Handling of materials containing tritium in the
facilities the question is to know the amount of
tritium which could be released (in the vent
system). Up to now the facilities are allowed to
make controlled releases, provided they remain
lower than a maximum yearly activity limit. If
needed a demand to increase the limits may be
made (probably in the frame of the whole site). - Measure of residual tritium my knowledge is
there are no adequate existing equipments in the
Cadarache hot cells up to now (but it seems to be
possible to design specific equipments). - Additional
- Tests in CEA Saclay in the LECI lab the whole
panel of physical, chemical, mechanical
examinations testing of irradiated samples is
available, so it is for the samples preparation
(examples machining of tensile strength samples,
EBM samples ...). -
21Approximate weights of various TBM (preliminary)
HH DD Earlier DT Low duty cycle DT High duty cycle DT
Port 2 Water-cooled ceramic breeder TBM 1990 kg
Port 16 He-cooled ceramic breeder TBM 1905 kg
Port 18 DCLL 1100 kg (after PbLi drained)
22In Tesinis view, even coarse cutting in ITER HC
is nearly impossible
Facilities at Cadarache with upgrade to handle
tritium
ITER HC
23Disassembly and coarse sectioning cell
- Shielded, tritium proof containing cell
- Being able to operate on ½ port test blanket
modules - A remotely operated screw driver, laser beam
cutter, precision saw, vise, and manipulator will
be utilized for cutting open TBMs to remove
sub-assemblies and specimen packets - Need collectors for receiving pebbles
24Concerns of using relevant facilities at Cadarache
- Of course a peer review should be made in order
to check the feasibility of the requested
operations in the various facilities, in
particular concerning safety (activity and
shielding, tritium and other species content,
Beryllium, ). - If Tritium measurements were required a specific
feasibility should have to be launched, although
LECI had to deal with in the framework of a past
programme. - An other point to check is the remaining life
time of the facilities (or parts of them) with
regard of the TBM programme schedule.
25There are benefits of performing PIE near ITER
site
- PIE such as tritium reconstruction, tritium
recovery from ceramic breeder and beryllium
pebble beds - PIE on ceramic breeder pebble bed packing state
and integrity
26Performing PIE at the partys site is also
desirable
- It is in the interest of the material community
to study the irradiation effect even at the low
doses - Most likely, full PIE hot cell facilities are
available in the Party
27- 1 - As correctly observed by Yves, it should be
demonstrated that even the TBM's initial, coarse
cutting operations can be satisfactorily carried
out inside the ITER Hot Cell. - 2 - Even if this is possible, we should carefully
consider the relative influence of the TBM's
coarse cutting and ITER Hot Cell operations on
the overall TBM experimental programme - a) the ITER HC is temporarily available but there
is no TBM's to cut - b) TBM's are ready for cutting but the ITER HC is
busy with higher priority operations - 3 - The above TBM/HC requirements/availability
situation will worsen if the TBM's are coming
into the ITER HC a) frequently and/or b) in high
number. This situation is directly linked with
the overall TBM's experimental programme and
should be carefully considered by the TBWG
28- (1) Is it possible to handle structural and
breeder materials which contain tritium (within
the facilities in Cadarache)? If not, what kind
of facility modification is needed to do that in
the hot cell in Cadarache?(2) Is it possible
to measure the residual tritium in breeder and
multiplier pebbles (within the facilities in
Cadarache)? (3) Is it possible to transfer
breeder and multiplier materials, which contain
tritium, to the country of origin? (related to
smaller, more manageable specimens) Is there any
authorized appropriate cask available? Can we
assume no tritium leak during transportation?(4)
What kind of test piece can be made in CEA
Saclay? What kind of tests can be performed?
29- Visual inspection and metrology associated with
deformation measurement of the whole TBM, as well
as TBM dismantling producing medium size pieces
is performed in ITER hot cells.The next step,
needing accurate visual inspection (corrosion
cracks identification) and accurate cutting
methods, could be performed in a CEA hot lab if
not feasible in ITER. This precise sampling of
medium size specimens could also be performed in
Cadarache (LECA-STAR or CHICADE).Then the
samples could be dispatched from there to hot
labs LECI-PELECI in Saclay for mechanical tests
and metallographic examinations or to the Party
if requested, using small size casks.