Title: Market Operations Standing Committee Meeting
1Market Evolution Program
- Market Operations Standing Committee Meeting
- April 23, 2003
2Overview
- Consultation
- Initiative Status
3Overview
- Day Ahead Market
- Multi-Interval Optimization
- Short Term Resource Adequacy
- Long Term Resource Adequacy
- Wholesale/Retail Integration
- Environmental Tracking
- Locational Marginal Pricing
4(No Transcript)
5(No Transcript)
6Working Groups/Consultation
Working Groups
IMO
Stakeholders
7Working Groups
- Working Groups were formed after an initial
fact-finding period for initiatives that were
mature enough to benefit - Multi-Interval Optimization
- Day Ahead Market
- Long Term Resource Adequacy
- Advisory process to help IMO make informed
recommendations, particularly with respect to
stakeholder perspective on issues
8Next Steps
- Stakeholder workshops planned for May/June on the
Long Term Resource Adequacy and Day Ahead Market
initiatives - Dates announced by the end of this week
- Format
- Face - to - Face
- Webcast
- Each consists of an educational component and an
opportunity for questions/input - Presentations will be made available in
PowerPoint and as a Media Player file with audio
9Locational Marginal Pricing
- Nodal pricing behaviour since market opening is
being assessed - Expect decision in the next few weeks on priority
of continuing this work
Environmental Information Tracking
- RFP for system prepared based on draft
regulations - Early stages of assessing training and education
needs of consumers/participants
10Day Ahead Market
11Day Ahead Market
- DAM discussion paper
- Examined and ruled-out simple DAM for summer 2003
- Formed DAM Working Group following Feb 18 MAC
- Developed DAM Objectives and Key Principles
- Prepared Feasibility Study - Mar 28 IMO Board
accepted DAM direction and approved commencement
of design phase - Staged approach - high level design to be
completed by July at which time an assessment
will be made whether to proceed further
12Day Ahead Market
- Assessment of high level design
- How well it addresses some of the problems
evident in current market design and operation - Appropriate linkages to long term resource
adequacy initiative - Broad stakeholder consensus on the benefits of
implementing the proposed design - Appropriate cost recovery mechanism
- Working Group is engaged in identifying design
issues and potential solutions - Stakeholder workshops planned for early June on
proposed high level design
13Day Ahead Market
- DAM Working Group
- Principles and Objectives
- DAM and impact on Market Participant Classes
- Reviewed other DAM Options
- Working Group consensus to proceed with SMD-style
DAM - Commencing discussions of high-level design
features
14Day Ahead Market Design
- User Requirements
- WHAT the DAM will look like - complete September
2003 - Split into high level design and detailed design
- High level design - present to MAC June 11, IMO
Board July 3 - Detailed design
- Significant portion of participant-facing
elements - System Requirements
- HOW the DAM will work - complete November 2003
- Fewer participant-facing elements
15Multi-Interval Optimization
16Multi-Interval Optimization - What have we done?
- Feb 18 MAC Breakout sessions
- Working Group
- Formed with representation from generators and
loads - Meets either via conference call or face-to-face
sessions on a weekly basis - Focussed on three key issues
- Optimization Function
- Optimization Time Period
- Dispatch Advisories (How,What,When)
17Multi-Interval Optimization Objectives
- Improved Operational Reliability
- Resources will automatically be scheduled in
advance to allow ramp rate capability to be
utilized to solve future reliability concerns - Operational Stability
- Reduced Unit Cycling - The number of start/stop
sequences for resources will be reduced relative
to current operation - Improved Compliance - Non-compliance with
dispatch instructions will be reduced - Improved Market Transparency
- IMO manual intervention in the dispatch solution
will be reduced - Improve Market Efficiencies
- Constraint payments caused by limited ramp
capability will be reduced compared to present
dispatch
18Two Proposals
19Issues/Recommendation
- Issues
- ABB Solution
- Calculation time
- Potential hardware upgrade costs
- IMO Solution
- Solution may not always be optimal
- Recommendation
- Implement IMO solution
- IMO Board approved design stage funds
- Will go back in July for build phase funding
20Next Steps
21Resource Adequacy
22Short Term Resource Adequacy
- Options reviewed, recommended mechanisms being
implemented - Emergency Demand Response
- Hour Ahead Dispatchable Load
- Replacement Energy
23Long Term Resource Adequacy
- Discussion paper
- Working Group formed
- Performing feasibility assessment with
recommendation targeted for July, design to be
completed by year end - Six options currently under investigation
- LECG consultants engaged
- Working Group is engaged in identifying issues
and potential solutions - Stakeholder workshops planned for early to
mid-May on draft feasibility assessment
24Long Term Resource Adequacy
- LTRA Working Group
- Objectives
- Evaluation Criteria
- Draft Feasibility Study
25Wholesale/Retail Integration
26What is a Wholesale/Retail Issue?
- No formal definition, but generally these issues
all display four common characteristics
- Both the wholesale and retail markets are
affected - It is in the long-term interest of both markets
to resolve them - No single governing/regulatory authority has full
rule-making powers or responsibility over the
issue - They are generally complicated by the fact that
they span the wholesale/retail market boundary -
particularly in areas such as issue ownership,
computer systems, business processes and
financial risk management activities
27Wholesale/Retail Integration
- Issue Areas
- Financial Stresses across the market boundary
- Opening the door to future demand response
products that retail customers can participate in
while providing a reliability benefit - Ensuring that the wholesale/retail market
boundary keeps pace with emerging technologies
such as retail-level metering and microgeneration - Developments
- Wholesale/Retail Integration discussion paper
soliciting stakeholder feedback to be released
shortly - Upcoming Pilot Projects
28Wholesale/Retail Integration
- The Approach
- Avoid overlap with topics being addressed in
existing stakeholder forums - Use of Pilot Projects to look ahead to future
logistical challenges - Ensure that future solutions do not conflict with
the evolving role of various market participants
and retail entities - Ensure alignment with other MEP initiatives