Title: Okanogan Kelt Reconditioning Proposal


1
Okanogan Kelt Reconditioning(Proposal 29007)
Sponsored By Colville Confederated Tribes
Presented ByPaul WagnerGolder Associates, Inc.

2
Project NeedSpecifically called for in
Subbasin Summary
  • Objective 1 Maximize reproductive potential of
    steelhead in the Okanogan Subbasin.
  • Strategy 1. Explore feasibility of steelhead
    kelts reconditioning to allow repeat spawning."
  • Fish and Wildlife Needs
  • "Enhance survival of post-spawn (kelt) steelhead
    to maximize reproductive success."

3
NMFS Biological Opinion for Operation of the
Federal Columbia River Power System
  • RPA Action 109 - Theoretically, reconditioning
    and/or kelt downstream transportation could
    significantly increase the likelihood of a second
    spawning opportunity for many of these fish.
    Evaluations should be conducted to review
    available literature and develop pilot testing
    regarding reconditioning of kelts."

4
Limiting Factor Addressed
  • Downstream and upstream passage through 9
    mainstem Columbia River hydroelectric projects.

5
Relationship to other projects
  • BPA Project 200001700. Wild Kelt
    Reconditioning.
  • BPA Project 199604200. Restore Enhance
    Anadromous Fish Populations Habitat in Salmon
    Creek.
  • BPA Project 200000100. Improvement of
    Anadromous Fish Habitat and Passage in Omak
    Creek.
  • Omak Creek Habitat Restoration Projects funded by
    the National Fish and Wildlife Federation, the
    Salmon Recovery Funding Board (Project
    00-1683-D).

6
Relationship to other projects, continued
  • Salmon Creek Habitat Restoration Efforts.
  • Mid-Columbia Steelhead Radio Telemetry Studies.
  • Chelan and Douglas County Public Utility District
    Habitat Conservation Plan.
  • BPA Proposal 29042. Selective Fish Collection
    and Harvesting Gear.
  • BPA Proposal 29051. Develop Local Okanogan River
    Steelhead Brood Stock.

7
(No Transcript)
8
(No Transcript)
9
Objectives
  • Objective 1. Conduct Final Planning/Development
    of Kelt Reconditioning Program for the Okanogan
    River.
  • Objective 2. Collect Steelhead from Omak and
    Salmon Creeks.
  • Objective 3. Hold, Feed, and Recondition
    Steelhead Kelts at the Cassimer Bar Facility.
  • Objective 4. Monitor and Evaluate Reconditioning
    Success.

10
Objective 1. Conduct Final Planning/Development
of Kelt Reconditioning Program for the Okanogan
River.
  • Task 1a. Kelt Trapping/Release Final Planning and
    Permitting.
  • Task 1b. Kelt Reconditioning Facility
    Development.
  • Task 1c. Staff Training.

11
Objective 2. Collect Steelhead from Omak and
Salmon Creeks. Task 2a. Steelhead Trapping.
12
(No Transcript)
13
(No Transcript)
14
Objective 3. Hold, Feed, and Recondition
Steelhead Kelts at the Cassimer Bar Facility.
  • Task 3a. Kelt Holding/Reconditioning.

15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
Objective 4. Monitor and Evaluate
Reconditioning Success.
  • Task 4a. Mortality and Re-Maturation.
  • Task 4b. Homing Fidelity/Spawning Success.
  • Task 4c. Fecundity and Egg Viability Assessment.
  • Task 4d. Reporting and Project Administration.

19
Expected Results
  • Double natural steelhead production in Omak and
    Salmon creeks in 5 years.
  • - based upon 30 capture rate, 50
    reconditioning rate.
  • Assess homing fidelity.
  • -compliment ongoing efforts by CRITFC,YN, and
    others.
  • Assess egg viability and fecundity.
  • - add to the body of science related to
    steelhead kelt reconditioning.

20
Schedule
  • November 2002 - March 2003. Complete final
    planning, facility modifications, permitting,
    staff training (tasks 1a, 1b, 1c).
  • March 2003 - April 2003. Capture steelhead (task
    2a).
  • April 2003 - December 2003. Recondition kelts
    (task 3a).
  • December 2003 - April 2003. Monitoring and
    evaluation, reporting (tasks 4a, 4b, 4c, 4d).