Title: National Capital Region


1
National Capital Region First Responder
Authentication Card Implementation Plan
Robert LeGrande, Program Director
Mark James, Program Manager

2
PKI identity smart card will provide the relying
party with machine-read information to determine
access privileges for granting access into, out
of, and within various areas as required
Goal Standardized Incident Identity Management
3
Multi-Jurisdictional Recognition(mobile identity
management)
INFORMATION FEED FEDERAL STATE LOCAL
PRIVATE
First Responder Validation Authority (Produced
and Synchronized Nightly)
  • PDA INFORMATION FORMAT
  • DATA
  • TEXT
  • IMAGE

4
Program Structure
DHS / Preparedness Directorate
Office of National Capital Region Coordination
(ONCRC)
Federal Smart Card Interagency Advisory Board
(IAB)
State Regional Coordination
Policy / Standards
Senior Policy Group (SPG)
CAOs
Emergency Managers
METRO CIOs
RWGI
Key
State/Local Liaison
Federal Liaison
NCR Credentialing
Direct Report
Coordination
5
Approved Implementation Plan
  • Phase I Baseline Dates- New Dates
  • Regional as-is and to be analysis 01/03/06
    - 02/28/06 3/15/06-5/15/06
  • Includes 19 Jurisdictions the states of Md and
    Va
  • Limited implementation for interface
    analysis 01/03/06 - 02/28/06 3/15/06-5/15/06
  • Mobile device and interoperability
    analysis 01/03/06 - 02/28/06 3/15/06-5/15/06
  • Provide recommendations and implementation plan
    06/01/06
  • Pentagon sponsored Winter Fox exercise Done
  • NCR sponsored pilot exercise planning 02/01/06
    - 03/14/06 5/15/06-6/15/06
  • Phase II Baseline Dates- New Dates
  • NCR sponsored pilot exercise 03/15/06 -
    03/30/06 - 7/06
  • Commence regional implementation 04/01/06 -
    07/30/06 6/1/06- 9/1/06
  • NCR sponsored exercises 04/03/06 - 04/27/06
    8/1/06- 10/1/06
  • FEMA sponsored Forward Challenge 06 06/19/06 -
    06/22/06
  • Phase III Baseline Dates- New Dates
  • Complete implementation of UASI 05
    Funding 07/30/06 - 09/30/08 9/1/06-11/1/06
  • NCR sponsored exercises 09/04/06 - 09/30/08-
    11/15/06-12/15/06