Title: MLNG REJUVENATION


1
MLNG REJUVENATION AND MLNG/MLNG DUA REVAMP
PROJECT (MRR PROJECT) SUCCESSES, CHALLENGES AND
LESSONS LEARNT 23 MARCH 2004
Pau Kiew Huai
2
PETRONAS LNG COMPLEX
PETRONAS LNG COMPLEX, BINTULU
KUALA LUMPUR
3
PETRONAS LNG COMPLEX
  • PETRONAS LNG COMPLEX has 3 LNG plants

  • Start-up Capacity
  • MLNG 1983 8.4
  • MLNG DUA 1995 7.8
  • MLNG TIGA 2003 6.8 Total 23MMTPA

4
PETRONAS LNG COMPLEX
MRR Project for 1st 2nd plants only
5
WHY REJUVENATION?
  • MLNG have completed 20 years operation since
    1983.
  • (Modules 1,23 Utilities Common
    Facilities)
  • The rejuvenation project objectives are to-
  • operate a further 20 years.
  • sustain reliability of plant.
  • retain integrity of facilities.

6
WHY REVAMP?
  • MLNG MLNG DUA future feed gas composition
    contains higher CO2 content
  • To maintain current MLNG MLNG DUA production
    capacity
  • Upgrade plant utilities to support revamped plant
    requirement.

7
REJUVENATION SCOPE
Painting and Insulation, 40 of rejuvenation
scope Repair and Replacement of Corroded Pipe
Lines, Steel Structures and Equipment.
8
REJUVENATION SCOPE
Rejuvenate boilers deaerator Rejuvenate
boiler water polishers
9
REJUVENATION SCOPE
replace chlorination unit
replace SCW pump impeller to bigger size
10
REJUVENATION SCOPE
Replace all LNG tank heaters with flexible
conduit design Replace instrument junction boxes
11
REVAMP SCOPE
2, Dehydration unit revamp
1,Sulfinol Unit revamp
4, Acid Gas Incineration facilities
3, Liquefaction unit revamp
12
EXECUTION STRATEGY
Project Stake Holders (Plant Management)
Project Owner's Team
Project EPCM Consultant (Consortium of JGC, KBR,
OGP)
Vendors, 3rd party services
Construction Contractors
13
PROJECT EXECUTION STRATEGY
  • Project Phases
  • Phase 1 - scope definition site investigation
    (1999 - 2000)
  • Phase 2 - engineering, procurement and
    construction planning (2000 - 2001)
  • Phase 3 - construction (2001 - 2005)

14
PROJECT SCHEDULE
2001
2002
2003
2004
2005
MLNG Rejuvenation/ Revamp
Module 1
Module 2
Module 3
MLNG Dua Revamp
Module 6
Module 4
Module 5
15
PROJECT COST ESTIMATE
  • Initial project cost estimate USD 306 million
  • MLNG Rejuvenation USD 230 million
  • MLNG Revamp USD 45 million
  • MLNG Dua Revamp USD 31 million
  • Latest cost projection USD 270million

16
CONSTRUCTION
  • HSE - strong emphasis
  • Daily toolbox Total Safety
  • Task Instruction meetings
  • Near Miss Reporting
  • Loss Prevention Inspection
  • Award Scheme
  • Red Lead Based Paint Removal Methods

17
CONSTRUCTION
  • Training
  • 18,000 Man-sessions
  • (HSE Skill training)
  • 41 Different Courses
  • - e.g. Safety
  • Induction rigging
  • lifting

18
CONSTRUCTION
  • Red lead based paint removal
  • Training Personnel Issue PPE
  • Blood testing (before, during and after job)
  • enclosure of plant equipment

19
CONSTRUCTION
  • Heavy lifts
  • C-1103 - 120 ton 30 m high in middle of the
    Module
  • V5701B - 70 ton on high structure

20
LESSON LEARNT
Managing 300,000m3 scaffolding demands lots of
supervision / attention
21
LESSON LEARNT
Managing blasting in live plant demands strict
control and monitoring.
Furmanite clamp
22
LESSON LEARNT
  • Interface with Plant Operations
  • Involve plant staff for engineering review
    procurement evaluation
  • Daily discussion with Operation staff
  • Hold regular "Look Ahead" meetings

23
LESSONS LEARNT
Sound economical rejuvenation solution
  • Rejuvenation engineering need-
  • clear rejuvenation criteria
  • up-to-date plant informations
  • experienced plant inspectors /engineers

24
LESSONS LEARNT
Improvement on next shutdown
Promote teambuilding, organise lesson
learnt workshops
25
ACHIEVEMENTS
  • HSE
  • 7 million manhours
  • without LTI to date
  • Zero environmental
  • infringement
  • 18,000 man-sessions training conducted

26
ACHIEVEMENTS
  • Schedule
  • all scheduled target dates and shutdown durations
    met
  • project is robust
  • and flexible to
  • meet the frequent
  • target date
  • changes.

27
ACHIEVEMENTS
  • Quality
  • Sustained current LNG production on revamped
    modules
  • minimum flange leaks
  • Cost
  • On target,
  • expect below budget

28