Title: MLNG REJUVENATION
1 MLNG REJUVENATION AND MLNG/MLNG DUA REVAMP
PROJECT (MRR PROJECT) SUCCESSES, CHALLENGES AND
LESSONS LEARNT 23 MARCH 2004
Pau Kiew Huai
2PETRONAS LNG COMPLEX
PETRONAS LNG COMPLEX, BINTULU
KUALA LUMPUR
3PETRONAS LNG COMPLEX
- PETRONAS LNG COMPLEX has 3 LNG plants
-
Start-up Capacity - MLNG 1983 8.4
- MLNG DUA 1995 7.8
- MLNG TIGA 2003 6.8 Total 23MMTPA
4PETRONAS LNG COMPLEX
MRR Project for 1st 2nd plants only
5WHY REJUVENATION?
- MLNG have completed 20 years operation since
1983. - (Modules 1,23 Utilities Common
Facilities) - The rejuvenation project objectives are to-
- operate a further 20 years.
- sustain reliability of plant.
- retain integrity of facilities.
6WHY REVAMP?
- MLNG MLNG DUA future feed gas composition
contains higher CO2 content - To maintain current MLNG MLNG DUA production
capacity - Upgrade plant utilities to support revamped plant
requirement.
7REJUVENATION SCOPE
Painting and Insulation, 40 of rejuvenation
scope Repair and Replacement of Corroded Pipe
Lines, Steel Structures and Equipment.
8REJUVENATION SCOPE
Rejuvenate boilers deaerator Rejuvenate
boiler water polishers
9REJUVENATION SCOPE
replace chlorination unit
replace SCW pump impeller to bigger size
10REJUVENATION SCOPE
Replace all LNG tank heaters with flexible
conduit design Replace instrument junction boxes
11 REVAMP SCOPE
2, Dehydration unit revamp
1,Sulfinol Unit revamp
4, Acid Gas Incineration facilities
3, Liquefaction unit revamp
12EXECUTION STRATEGY
Project Stake Holders (Plant Management)
Project Owner's Team
Project EPCM Consultant (Consortium of JGC, KBR,
OGP)
Vendors, 3rd party services
Construction Contractors
13PROJECT EXECUTION STRATEGY
- Project Phases
- Phase 1 - scope definition site investigation
(1999 - 2000) - Phase 2 - engineering, procurement and
construction planning (2000 - 2001) - Phase 3 - construction (2001 - 2005)
14PROJECT SCHEDULE
2001
2002
2003
2004
2005
MLNG Rejuvenation/ Revamp
Module 1
Module 2
Module 3
MLNG Dua Revamp
Module 6
Module 4
Module 5
15PROJECT COST ESTIMATE
- Initial project cost estimate USD 306 million
- MLNG Rejuvenation USD 230 million
- MLNG Revamp USD 45 million
- MLNG Dua Revamp USD 31 million
- Latest cost projection USD 270million
16CONSTRUCTION
- HSE - strong emphasis
- Daily toolbox Total Safety
- Task Instruction meetings
- Near Miss Reporting
- Loss Prevention Inspection
- Award Scheme
- Red Lead Based Paint Removal Methods
17CONSTRUCTION
- Training
- 18,000 Man-sessions
- (HSE Skill training)
- 41 Different Courses
- - e.g. Safety
- Induction rigging
- lifting
18CONSTRUCTION
- Red lead based paint removal
- Training Personnel Issue PPE
- Blood testing (before, during and after job)
- enclosure of plant equipment
19CONSTRUCTION
- Heavy lifts
- C-1103 - 120 ton 30 m high in middle of the
Module - V5701B - 70 ton on high structure
20LESSON LEARNT
Managing 300,000m3 scaffolding demands lots of
supervision / attention
21LESSON LEARNT
Managing blasting in live plant demands strict
control and monitoring.
Furmanite clamp
22LESSON LEARNT
- Interface with Plant Operations
- Involve plant staff for engineering review
procurement evaluation - Daily discussion with Operation staff
- Hold regular "Look Ahead" meetings
23LESSONS LEARNT
Sound economical rejuvenation solution
- Rejuvenation engineering need-
- clear rejuvenation criteria
- up-to-date plant informations
- experienced plant inspectors /engineers
24LESSONS LEARNT
Improvement on next shutdown
Promote teambuilding, organise lesson
learnt workshops
25ACHIEVEMENTS
- HSE
- 7 million manhours
- without LTI to date
- Zero environmental
- infringement
- 18,000 man-sessions training conducted
26ACHIEVEMENTS
- Schedule
- all scheduled target dates and shutdown durations
met - project is robust
- and flexible to
- meet the frequent
- target date
- changes.
27ACHIEVEMENTS
- Quality
- Sustained current LNG production on revamped
modules - minimum flange leaks
- Cost
- On target,
- expect below budget
28AFTER
BEFORE
29Thank You