Military Base Standard Offer Program - PowerPoint PPT Presentation

About This Presentation
Title:

Military Base Standard Offer Program

Description:

... the deemed savings table for central air conditioners, the total kW savings is ... 3-ton 13 SEER central A/C unit: $282 - $887 (7,500) 10-ton rooftop A/C ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 28
Provided by: pau80
Category:

less

Transcript and Presenter's Notes

Title: Military Base Standard Offer Program


1
Military Base Standard Offer Program
  • El Paso Electric

2
Background
  • SB 652, enacted during the last legislative
    session, resulted in changes to Public Utility
    Regulatory Act (PURA).
  • SB 652 was a comprehensive bill to improve the
    prospects for maintaining military bases in
    Texas. By increasing energy efficiency and
    reducing energy costs, bases have a better chance
    of remaining open.
  • The legislation targets electric utilities that
    are located in areas that are outside of ERCOT.

3
Background
  • PUCT approved rules for this Program on March 4.
  • Applicable facilities in EPE service area are Ft.
    Bliss and ADAC.
  • The goal is to reduce aggregate electricity
    consumption (kWh) at these facilities by 5
    before 1/1/2005.
  • Goal is 7,370,000 kWh
  • Incentive levels are higher than other standard
    offer programs being implemented by utilities
    under SB 7 (electric utility restructuring bill).
  • EPE is making 1.3 million in incentive funds
    available to achieve this goal.

4
Whats a Standard Offer Program?
  • Any energy efficiency measure meeting PUCT
    requirements can qualify. Not measure-specific.
  • EPE pays incentives based on the kW and kWh
    savings. Not tied in to measure costs.
  • Measure eligibility
  • Retrofit or new construction measures
  • Permanently-installed measures only
  • Most renewable measures are allowed
  • Installed equipment must exceed minimum
    efficiency standards, if applicable.

5
Project Opportunities
  • HVAC
  • Lighting
  • Motor retrofits
  • Variable frequency drives
  • Controls
  • Process improvements
  • Fuel-switching from electric
  • Renewable energy projects, including wind and PV

6
Ineligible Measures
  • Measures with life less than 10 years
  • Removable measures (generally includes plug
    loads)
  • Cogeneration or self generation (except
    renewables)
  • Fuel switching to electric
  • Measures that rely on changes in behavior and
    require no capital investment
  • Projects that eliminate an existing function, or
    relocate existing operations outside the EPE
    service area.

7
EPEs Role as Program Administrator
  • Oversee that programs follow rules and template
    guidelines
  • Review, approve or reject program applications
  • Verify and inspect that measures meet intended
    purpose
  • Administer incentive dollars
  • Provide outreach to project sponsors

8
The Role of the Project Sponsor
  • Develops a energy efficiency project that meets
    the requirements of the Program and Ft. Bliss.
  • Executes an agreement with EPE to deliver a
    specific quantity of kW and kWh.
  • Negotiates with Ft. Bliss to implement the
    proposed energy efficiency project.
  • Implements the project within the required
    timeframe.
  • Documents the installation and resultant energy
    savings.
  • Receives incentive payment from EPE.

9
Examples of Project Sponsors
  • Fort Bliss acting as its own project sponsor
  • Third-Party Project Sponsors
  • A/C Dealers
  • Insulation Contractors
  • Energy Efficiency Service Providers
  • Renewable Energy Project Developers
  • AE Firms
  • Lighting Contractors
  • Electrical Contractors

10
Third-Party Project Sponsor Requirements
  • Third-Party Project Sponsors must have
  • Adequate insurance
  • All appropriate licenses
  • References
  • Evidence of technical and managerial capabilities
    and experience
  • Evidence of financial capability

11
Comparison with Other SOPs
  • Military Bases SOP
  • Goal is kWh, not kW
  • Better for motor drive and other high-load factor
    projects
  • No limit on lighting projects
  • Higher payments
  • Expedited project approval and payments.
  • Ft. Bliss can act as its own project sponsor.
  • Other SOP
  • Emphasis is peak demand.
  • Reduced payments for high load factor projects
  • May require a deposit.
  • Most projects are lighting only.
  • Most project sponsors are third-party ESCOs.

12
Standard Incentive Payment
  • Demand payment 278.29 per kW of peak demand
    savings
  • Energy payment 0.095 per kWh of annual energy
    savings
  • All incentives are paid directly to project
    sponsor.

13
Hard-to-Reach
  • Projects that benefit hard-to-reach customers,
    such as certain personnel living in military
    housing units, may be eligible for the HTR
    incentive payments of 556.58/kW and 0.19/kWh.
  • EPE estimates that the majority of family housing
    for E-1 through E-3 grades would qualify as
    hard-to-reach households, and that many
    additional units for grades E-4 through E-6 are
    also hard-to-reach, with over 1,000 potential
    hard-to-reach units.

14
Incentive Payments
  • Certain projects are eligible for a eligible for
    a 20 adder, since El Paso is in an EPA
    non-attainment area.
  • Previous energy efficiency projects implemented
    under SB 5 have qualified for the higher payment.
  • Projects that would not have been implemented
    without the adder are eligible.
  • With the adder
  • Standard incentive payments are 333.95 per kW
    and 0.114 per kWh.
  • HTR payments are 667.90 per kW and 0.224 per
    kWh

15
Incentive Payment Example 1
  • A local HVAC dealer installs 30 high-efficiency
    AC units, varying in size from 2.5 to 5 tons, and
    in SEER rating, from 13.0 to 16.0. Using the
    deemed savings table for central air
    conditioners, the total kW savings is 24.9, and
    the annual kWh savings is 42,750. The incentive
    payment is calculated as follows
  • (24.9 x 278.29) (42,750 x 0.095) 10,991
  • (24.9 x 333.95) (42,750 x 0.114) 13,189
    with 20 environmental adder
  • (24.9 x 668.38) (42,750 x 0.228) 26,390 if
    installed on HTR-eligible units with 20 env.
    adder

16
Incentive Payment Estimates
  • The following are estimates only and not based on
    actual metered or measured data from Ft. Bliss
  • 4-lamp T-12 fixture retrofit 38 (approximately
    33,000 required to reach goal)
  • Energy Star residential refrig. retrofit
    115-275 (approximately 8,500 required to reach
    goal)
  • 3-ton 13 SEER central A/C unit 282 - 887
    (7,500)
  • 10-ton rooftop A/C unit 800 (1,750)
  • VSD for 250 hp water pump 30,000-35,000 (30)
  • 1 mW wind turbine 400,000 - 450,000 (3-3.5)
  • The value of the energy savings is not included
    in the above estimate.

17
Definition of Peak Demand Savings
  • The maximum average load reduction occurring
    during any one-hour period between 1 PM and 7 PM
    MDT weekdays, from May 1 through September 30
    (holidays excluded).

18
Energy Savings MV Options
  • Deemed Savings Option
  • Deemed savings are pre-determined savings values
    for most of the common energy efficiency
    measures. These kW and kWh values have been
    approved by the PUCT.
  • Incentive payments for all measures shown
    previously are based on deemed savings.
  • Project Sponsor accepts deemed savings values for
    measures installed and receives 100 of incentive
    payment after submitting an installation report.

19
Energy Savings MV Options
  • Project Sponsors may choose to not accept deemed
    savings estimates, and to perform measurement and
    verification (MV) activities.
  • For measured savings, actual kW and kWh
    measurements are required to determine incentive
    payments.
  • Project Sponsors must submit a measurement and
    verification (MV) plan with project application.
  • Certain measures do not have a deemed savings
    values.

20
Program Steps
  • Project Application
  • Initial Application
  • Final Application
  • Pre-installation inspection / metering
  • Installation report
  • Post-installation inspection
  • Installation payment
  • Energy savings measurement and verification (MV)
  • Savings report
  • Final incentive payment

21
Initial Application for Third-Party Project
Sponsors
  • IA includes sponsor qualifications
  • Identifies intended measures (20 kW savings
    minimum)
  • Estimates kW/kWh savings and incentive payments
  • EPE reviews the IA for sponsor and project
    eligibility.
  • Approximately 14-day review period
  • Upon approval, EPE reserves funds for the
    project.
  • Letter of intent from Ft. Bliss
  • The letter should include a summary description
    of the project and indication of Ft. Bliss level
    of interest in implementing the proposed project,
    should the project sponsors application be
    approved. Not required for Ft. Bliss.

22
Final Application for Third-Party Project Sponsors
  • Detailed project description
  • Savings calculations and incentive estimates
  • Equipment surveys (use standard forms)
  • Proposed MV plan
  • Finalized work plan for completing the project
    within the required timeframes
  • Due within 30 days of initial application
    acceptance
  • Agreement with Ft. Bliss not required with final
    application, but must be submitted within 30 days
    after project go-ahead. Not required for Ft.
    Bliss.

23
Installation Report
  • Updated project implementation information
  • The demolished and actual installed retrofit
    equipment inventories, including equipment
    counts, equipment efficiencies, and equipment
    nameplate data.
  • Updates to occupancy or equipment or occupancy
    schedules
  • Updated engineering calculations estimating
    energy and demand savings
  • Final MV plan details

24
Savings Report and Final Payment
  • If the project sponsor is using simple of full
    MV, the project sponsor should submit a savings
    report after all MV activities are complete.
    This report should document the actual demand and
    energy savings measured for the projects.
  • Total project payment due less installation
    payment will be made after invoicing by project
    sponsor.
  • If deemed savings are used exclusively, the
    project sponsor doesnt need to submit a savings
    report.

25
Program Timeline
26
www.epelectricefficiency.com
  • Program Web site has
  • Latest program announcements
  • Latest version of program manual for download
  • Support files
  • Deemed savings
  • Installation standards
  • Lighting spreadsheets
  • Helper applications
  • Information on available funding
  • Program contacts and links

27
Contact Information
  • Mr. John Armstrong - Program Manager
  • Phone - 915.543.5809
  • Email - jarmstro_at_epelectric.com
Write a Comment
User Comments (0)
About PowerShow.com