Title: Military Base Standard Offer Program
1Military Base Standard Offer Program
2Background
- SB 652, enacted during the last legislative
session, resulted in changes to Public Utility
Regulatory Act (PURA). - SB 652 was a comprehensive bill to improve the
prospects for maintaining military bases in
Texas. By increasing energy efficiency and
reducing energy costs, bases have a better chance
of remaining open. - The legislation targets electric utilities that
are located in areas that are outside of ERCOT.
3Background
- PUCT approved rules for this Program on March 4.
- Applicable facilities in EPE service area are Ft.
Bliss and ADAC. - The goal is to reduce aggregate electricity
consumption (kWh) at these facilities by 5
before 1/1/2005. - Goal is 7,370,000 kWh
- Incentive levels are higher than other standard
offer programs being implemented by utilities
under SB 7 (electric utility restructuring bill). - EPE is making 1.3 million in incentive funds
available to achieve this goal.
4Whats a Standard Offer Program?
- Any energy efficiency measure meeting PUCT
requirements can qualify. Not measure-specific. - EPE pays incentives based on the kW and kWh
savings. Not tied in to measure costs. - Measure eligibility
- Retrofit or new construction measures
- Permanently-installed measures only
- Most renewable measures are allowed
- Installed equipment must exceed minimum
efficiency standards, if applicable.
5Project Opportunities
- HVAC
- Lighting
- Motor retrofits
- Variable frequency drives
- Controls
- Process improvements
- Fuel-switching from electric
- Renewable energy projects, including wind and PV
6Ineligible Measures
- Measures with life less than 10 years
- Removable measures (generally includes plug
loads) - Cogeneration or self generation (except
renewables) - Fuel switching to electric
- Measures that rely on changes in behavior and
require no capital investment - Projects that eliminate an existing function, or
relocate existing operations outside the EPE
service area.
7EPEs Role as Program Administrator
- Oversee that programs follow rules and template
guidelines - Review, approve or reject program applications
- Verify and inspect that measures meet intended
purpose - Administer incentive dollars
- Provide outreach to project sponsors
8The Role of the Project Sponsor
- Develops a energy efficiency project that meets
the requirements of the Program and Ft. Bliss. - Executes an agreement with EPE to deliver a
specific quantity of kW and kWh. - Negotiates with Ft. Bliss to implement the
proposed energy efficiency project. - Implements the project within the required
timeframe. - Documents the installation and resultant energy
savings. - Receives incentive payment from EPE.
9Examples of Project Sponsors
- Fort Bliss acting as its own project sponsor
- Third-Party Project Sponsors
- A/C Dealers
- Insulation Contractors
- Energy Efficiency Service Providers
- Renewable Energy Project Developers
- AE Firms
- Lighting Contractors
- Electrical Contractors
10Third-Party Project Sponsor Requirements
- Third-Party Project Sponsors must have
- Adequate insurance
- All appropriate licenses
- References
- Evidence of technical and managerial capabilities
and experience - Evidence of financial capability
11Comparison with Other SOPs
- Military Bases SOP
- Goal is kWh, not kW
- Better for motor drive and other high-load factor
projects - No limit on lighting projects
- Higher payments
- Expedited project approval and payments.
- Ft. Bliss can act as its own project sponsor.
- Other SOP
- Emphasis is peak demand.
- Reduced payments for high load factor projects
- May require a deposit.
- Most projects are lighting only.
- Most project sponsors are third-party ESCOs.
12Standard Incentive Payment
- Demand payment 278.29 per kW of peak demand
savings - Energy payment 0.095 per kWh of annual energy
savings - All incentives are paid directly to project
sponsor.
13Hard-to-Reach
- Projects that benefit hard-to-reach customers,
such as certain personnel living in military
housing units, may be eligible for the HTR
incentive payments of 556.58/kW and 0.19/kWh. - EPE estimates that the majority of family housing
for E-1 through E-3 grades would qualify as
hard-to-reach households, and that many
additional units for grades E-4 through E-6 are
also hard-to-reach, with over 1,000 potential
hard-to-reach units.
14Incentive Payments
- Certain projects are eligible for a eligible for
a 20 adder, since El Paso is in an EPA
non-attainment area. - Previous energy efficiency projects implemented
under SB 5 have qualified for the higher payment. - Projects that would not have been implemented
without the adder are eligible. - With the adder
- Standard incentive payments are 333.95 per kW
and 0.114 per kWh. - HTR payments are 667.90 per kW and 0.224 per
kWh
15Incentive Payment Example 1
- A local HVAC dealer installs 30 high-efficiency
AC units, varying in size from 2.5 to 5 tons, and
in SEER rating, from 13.0 to 16.0. Using the
deemed savings table for central air
conditioners, the total kW savings is 24.9, and
the annual kWh savings is 42,750. The incentive
payment is calculated as follows - (24.9 x 278.29) (42,750 x 0.095) 10,991
- (24.9 x 333.95) (42,750 x 0.114) 13,189
with 20 environmental adder - (24.9 x 668.38) (42,750 x 0.228) 26,390 if
installed on HTR-eligible units with 20 env.
adder
16Incentive Payment Estimates
- The following are estimates only and not based on
actual metered or measured data from Ft. Bliss - 4-lamp T-12 fixture retrofit 38 (approximately
33,000 required to reach goal) - Energy Star residential refrig. retrofit
115-275 (approximately 8,500 required to reach
goal) - 3-ton 13 SEER central A/C unit 282 - 887
(7,500) - 10-ton rooftop A/C unit 800 (1,750)
- VSD for 250 hp water pump 30,000-35,000 (30)
- 1 mW wind turbine 400,000 - 450,000 (3-3.5)
- The value of the energy savings is not included
in the above estimate.
17Definition of Peak Demand Savings
- The maximum average load reduction occurring
during any one-hour period between 1 PM and 7 PM
MDT weekdays, from May 1 through September 30
(holidays excluded).
18Energy Savings MV Options
- Deemed Savings Option
- Deemed savings are pre-determined savings values
for most of the common energy efficiency
measures. These kW and kWh values have been
approved by the PUCT. - Incentive payments for all measures shown
previously are based on deemed savings. - Project Sponsor accepts deemed savings values for
measures installed and receives 100 of incentive
payment after submitting an installation report.
19Energy Savings MV Options
- Project Sponsors may choose to not accept deemed
savings estimates, and to perform measurement and
verification (MV) activities. - For measured savings, actual kW and kWh
measurements are required to determine incentive
payments. - Project Sponsors must submit a measurement and
verification (MV) plan with project application. - Certain measures do not have a deemed savings
values.
20Program Steps
- Project Application
- Initial Application
- Final Application
- Pre-installation inspection / metering
- Installation report
- Post-installation inspection
- Installation payment
- Energy savings measurement and verification (MV)
- Savings report
- Final incentive payment
21Initial Application for Third-Party Project
Sponsors
- IA includes sponsor qualifications
- Identifies intended measures (20 kW savings
minimum) - Estimates kW/kWh savings and incentive payments
- EPE reviews the IA for sponsor and project
eligibility. - Approximately 14-day review period
- Upon approval, EPE reserves funds for the
project. - Letter of intent from Ft. Bliss
- The letter should include a summary description
of the project and indication of Ft. Bliss level
of interest in implementing the proposed project,
should the project sponsors application be
approved. Not required for Ft. Bliss.
22Final Application for Third-Party Project Sponsors
- Detailed project description
- Savings calculations and incentive estimates
- Equipment surveys (use standard forms)
- Proposed MV plan
- Finalized work plan for completing the project
within the required timeframes - Due within 30 days of initial application
acceptance - Agreement with Ft. Bliss not required with final
application, but must be submitted within 30 days
after project go-ahead. Not required for Ft.
Bliss.
23Installation Report
- Updated project implementation information
- The demolished and actual installed retrofit
equipment inventories, including equipment
counts, equipment efficiencies, and equipment
nameplate data. - Updates to occupancy or equipment or occupancy
schedules - Updated engineering calculations estimating
energy and demand savings - Final MV plan details
24Savings Report and Final Payment
- If the project sponsor is using simple of full
MV, the project sponsor should submit a savings
report after all MV activities are complete.
This report should document the actual demand and
energy savings measured for the projects. - Total project payment due less installation
payment will be made after invoicing by project
sponsor. - If deemed savings are used exclusively, the
project sponsor doesnt need to submit a savings
report.
25Program Timeline
26www.epelectricefficiency.com
- Program Web site has
- Latest program announcements
- Latest version of program manual for download
- Support files
- Deemed savings
- Installation standards
- Lighting spreadsheets
- Helper applications
- Information on available funding
- Program contacts and links
27Contact Information
- Mr. John Armstrong - Program Manager
- Phone - 915.543.5809
- Email - jarmstro_at_epelectric.com
-