1057 SMTF Meeting at FNAL - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

1057 SMTF Meeting at FNAL

Description:

Pier/Barry/Gerry encouraged SMTF to change from a multi-funded, multi-interest ... Nov 14: Run modulator into a load (Dave Anderson from SNS will be here) ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 19
Provided by: Star109
Category:
Tags: fnal | smtf | barry | dave | meeting

less

Transcript and Presenter's Notes

Title: 1057 SMTF Meeting at FNAL


1
10/5-7 SMTF Meeting at FNAL
  • SMTF organization
  • Pier/Barry/Gerry encouraged SMTF to change from a
    multi-funded, multi-interest regional
    collaboration to a global group working on ILC
    cavity issues (perhaps merge with TTC so fewer
    meetings).
  • ILC at FNAL 60 people, 40 FTEs, 75 engineers.
  • Three working groups on cavities/cryomodules
  • EP / handling cleaning / materials
  • Very productive sessions with worlds experts.
    Allen Rowe and Christian Boffo (FNAL) and Mike
    Kelly (ANL) are leading this effort locally.
  • Reached 52 MV/m in single cells at KEK with
    modest cleanliness.
  • Cyromodule design / costs / schedule
  • John Weisend and Tom Peterson made list of pros
    and cons for various layout options. Would take
    about 3 years to produce next generation
    cyromodule.
  • CW plans and cryomodule beam tests
  • Little CW attendance, beam tests emphasize low
    emittance studies.

2
(No Transcript)
3
(No Transcript)
4
  • FNAL/Cornell/JLab plans in FY06
  • Using four recently acquired Accel cavities,
    perfect BCP at Cornell and then EP at JLab
    funded at 1 M.
  • Run Capture Cavity 2 at Meson Building probably
    install in A0 afterwards.
  • FNAL/ANL BCP process 4-8 cavities from AES and
    FNAL at ANL and vertical test at Cornell or JLab.
    May want to e-beam weld some cavities at SLAC.
  • Begin construction of cryomodule at FNAL using 8
    dressed cavities and cryomodule parts from DESY
    (in exchange for 3.9 GHz cavities, which will not
    be completed in FY06). Test initially in Meson
    building (not enough shielding for several
    cryomodules).
  • Begin design of a fourth generation cyromodule
    for ILC.
  • With limited funds, will not move A0, build new
    gun/modulator/WG, install cryogenics in New Muon,
    build a vertical test stand nor build a second
    horizontal test stand. Open to SLAC building new
    rf gun.

5
  • FY05 accomplishments
  • Close to having 4K capability in Meson Building.
  • Installed and tested DESY LLRF electronics at A0
    will use with Capture Cavity 2 (considered a PD
    project as well).
  • Most of parts ordered for the first horizontal
    test stand.
  • Ordered a clean room.
  • ANL BCP facility has all parts.
  • Americanized DESY cryomodule drawings.
  • Building two 5 ms pulse modulators (SLAC
    providing switches).
  • Sent 5 people to TTF for beam/llrf studies.
  • Other
  • Accelerator / cryomodules at New Muon building
    will be called ILCTA.
  • Meson building facility yet to be named
    (eventually PDTF).
  • Proton Driver project no CD0 approval yet,
    working on cavity development as well.
  • Nobu thought KEK would go global after Phase I
    of their STF program if other labs do.

6
SLAC RD
  • L-band Test Facility
  • Electrical safety review of modulator this week.
  • Klystron installed and magnet tested, llrf system
    well along, waveguide arriving, structure window
    being designed, and structure fabrication
    starting.
  • Have plan to upgrade modulator to be able to run
    klystron (will work with LANL on this).
  • Schedule
  • Nov 14 Run modulator into a load (Dave Anderson
    from SNS will be here).
  • Dec/Jan Upgrade modulator for higher current and
    test into load study arc response.
  • Jan Run klystron without rf.
  • Feb Run rf into a load test 10 m of
    pressurized waveguide and new window up to 4-5
    MW.
  • March Power a 5 cell L-band cavity in NLCTA.

7
L-Band Test Facility at NLCTA
  • Recently acquired a 10 MW HVCM Modulator from
    SNS.
  • Buying a 5 MW TH2104C tube from Thales (1 year
    delivery).
  • In meantime use a SDI-Legacy tube from Titan
    (TH2104U).
  • All major LLRF and waveguide components on order.

SNS Modulator Being Assembled at NLCTA
Thales 2104U Klystron
8
Klystron WGLayout
The klystron will be installed in the unused half
of the Eight-Pack Modulator tank and waveguide
will be run into the NLCTA beam
enclosure. Expect first power in March 2006.
9
  • Coupler Program
  • Brian working on specifics of a parts testing
    plan to examine effect of bellows, windows,
    coatings and bake temperature on processing
    speed.
  • Jose looking at layout of test area in ESB
    propose to put a switch at klystron output.
    Coupler area would be used for initial klystron
    tests.
  • SLAC has capability and equipment (high purity
    water, clean rooms, TiN coating facility) to
    assemble and process couplers for FNAL cavities,
    but so do other labs.
  • Orsay for DESY TTF and XFEL couplers
  • JLab (would convert 1.5 GHz test stand)
  • FNAL (currently building setup for 3.9 GHz
    cavities).
  • CPI (could at least assemble couplers)
  • Will try to formulate global coupler plan at TTC
    meeting in December (first couplers needed in
    FY07).

10
Test Facility Program in 2006
  • Use 5 MW source for coupler and normal-conducting
    cavity tests.
  • Propose to add a second L-band station using ILC
    prototypes.
  • Based on progress, use Marx Generator, DTI Direct
    Switch or buy a baseline modulator from PPT.
  • Either buy are borrow a CPI or Toshiba 10 MW
    klystron from DESY.

11
Coupler Processing Studies
One concern is that the surface field variations
in the bellows and near the windows may lead to
excessive mulitpacting.
Coupler Surface Field
To understand processing limitations, plan in
FY06 to process coupler components individually.
In particular, determine if bellows or the
windows are the source of the long processing
time.
Brian Rusnak
12
Instrumented Coupler Test Stand at Orsay
13
  • SC Quad and RF BPM
  • Reviewed quad cryostat design with DESY (Heiner
    Brueck) and CIEMAT (Fernado Toral) last Friday.
  • Current Plan
  • Magnet tests nearly complete at DESY will ship
    magnet to SLAC afterward. Will also send lead
    package.
  • Will not use CIEMAT He Vessel designed for 2K
    operation (no He vapor) with a cold bore. Need to
    increase He around inner bore and force flow.
  • Widen connection to He reservoir and connect to
    bottom of tank to provide He bath.
  • Review new design with FNAL experts at end of
    month.
  • Parts ordered for He supply system at Magnet Test
    Lab.
  • Aim for first cooldown in March.
  • S-band RF BPM design complete (Zenghai / Gordon)
    and a triplet is currently being fabricated.
  • Scheduled for test at ESA at end of February.
  • Readout electronics being provided at ESA

14
ILC Linac SC Quad/BPM Evaluation
S-Band BPM Design (36 mm ID, 126 mm OD)
Cos(2F) SC Quad ( 0.7 m long)
He Vessel
SC Coils
Iron Yoke Block
Al Cylinder
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com