Title: Capital Project Appraisal
1Capital Project Appraisal
24 February 2006
2Capital project appraisal in practicecareer
opportunities for actuarial skills!
- In 1998 the Association of Consulting Actuaries
(ACA) and the Confederation of British Industry
(CBI) surveyed large UK firms (turnover gt20m) in
regard to their approach to key capital
investment decisions. - The survey indicated a lack of rigour in the
decision process of many firms. - There is no reason to believe that there has
been much change since, or that practices in
Ireland are superior. - We will look at this surveys results first and
then devote the rest of the lecture to
considering recommended practice.
3Findings of survey by ACA CBIhow UK firms
approach key capital investment decisions
- Appraisal techniques are not rigorously
quantitative - 23 of firms did not use quantitative analysis
at all - Only 60 reviewed the value of decision criteria
regularly - management judgement had key role in setting a
projects target - Many firms, ignore cashflow methods - rely on
profit data - Many viewing cashflow judge only on payback (2 to
4 yrs!) - Hurdle rates are often set at higher level than
theory needs - Most dont decide solely on whether meets target
rate - Most projections ignore inflation
- Risk analysis often performed by people not best
placed - Limited attention is paid to inter-related risks
- Firms using high hurdle rates mostly in lower
risk sectors
4Capital project appraisalrecommended practice
- This is a key part of the planning risk
analysis stages - A capital project is described as up-front
expenditure on asset creation for subsequent
profit flows - intangible (e.g. patent) as well as tangible
asset - Approach being discussed follows methodology of
one stage of RAMP (Risk Analysis Management for
Projects) process
5RAMP life cycle of a projectprocess developed by
actuarial civil engineering professions
- Opportunity identification
- Detailed appraisal, leading to investment
submission - - the stage being discussed today
- Raising the necessary finance, design, contracts
etc - Asset creation
- Operation
- Close-down
see www.ramprisk.com
6Key stages in project appraisal
- Initial appraisal of identified opportunity
- core organisation criteria, strategic financial
- synergy with other projects, upside potential
- subjective dimension as well quantitative
- risk for sponsors, lenders, investors. Mitigation
- Detailed appraisal
- entails choice of risk discount rate
- risk identification, analysis, modelling,
mitigation - investment submission
7Detailed appraisal
- Project definition, scope and timescale
- must be clearly spelt out and agreed by all
- clear specification of
- success criteria
- to whom goals of the project apply
- responsibilities of people in project team and
management team - Evaluation of cashflows, including knock-on
- cap ex, running costs, revenues, termination cost
- rigour is vital - should document all assumptions
- first cut / NPV, IRR, (discounted) payback period
- then apply sensitivity analysis / scenario
testing - if satisfactory, then apply detailed risk analysis
8Risk discount rate
- Nominal rates for nominal cashflows
- Distinguish between
- specific (diversifiable / probabilistic) risk,
and - systematic (non-diversifiable / market) risk
- Increase discount rate for systematic risk
9Choosing risk discount rate
- Projects carrying normal degree of risk
- incremental after-tax cost of (debt equity)
capital - cost of equity risk free rate equity risk
margin - Projects above normal systematic risk
- ideally base on rates used by firms experienced
in such projects ? in practice a judgment call - Other considerations
- illusion of precision
10Dealing with specific risks
- Identification steps
- high level cull of clearly-high-risk projects
- brainstorming by project experts, senior internal
and external people with a long view - to identify project risks, likelihood,
interdependency, frequency severity, mitigation
options - desktop analysis building on this and research
- set out all identified risks in a Risk Register,
cross referencing interdependencies
11Risk types examples
- Political war, govt / policy change, new laws
taxes, trade restrictions, planning permits,
third party opposition - Natural force majeure, climate change
- Economic interest rate and exchange rate moves
- Financial cashflow estimates, capital cost,
assumptions, finance availability, sponsor
dissent - Crime fraud, crime
- Project ill-defined objectives, design flaws,
information withheld, timescale, leading-edge
technology, key personnel, contractor bankruptcy,
decommissioning - Business volumes revenue, running cost,
efficiency level, early obsolescence,
competition, safety hazards
12Analysis of identified risks
- Each risk could be classified by 4 measures
- frequency of occurrence or risk level
- degree of dependence on other, separate risks
- degree by which it can be mitigated or managed
- financial impact
- Expected cost of a given risk quantified in NPV
- Low probability, high severity risks scrutinised
- Distribution of NPVs for entire project modelled
- by scenario analysis or stochastic modelling
- (volume of assumptions limit stochastic model use)
13Example probability dist of NPVs
Expected NPV 154,600. Losses 35 of time
Max loss 391,000
14Risk mitigation
- Options and examples
- reduction
- reducing risk (probability or consequence)
modify design or build in safety margins - reducing uncertainty further research
- transfer fixed price contract, pay insurance
premium - avoidance redesign / abandon
- absorb or pool organise syndicate, joint
venture - Evaluation of each option to assess
- effect on frequency, consequence expected value
- feasibility cost of implementation
- if any secondary risks resulting ? resultant
mitigating actions - overall impact on the distribution of NPVs
- Mitigation should reduce downward volatility of
NPVs - if decreases expected NPV, need judgement call on
trade-off
15Example of trade-off judgement call
- Work with the example in the table in slide
number 13 - The contractor is prepared to bear the whole of
any extra costs / losses arising after year 1,
provided the contract price is increased by
80,000. This would arise in scenarios C E - Is it worth accepting the offer?
- See workings on next slide
16Example continuedeffect on distribution of NPVs
of paying contractor 80,000
Expected NPV 145,350. Losses 20 of time
Max loss 188,000
17The investment submission
- Reflect choice of best possible mix of mitigation
options - Show expected NPV probability distribution of
NPVs - Identify and analyse residual risks. Special
attention should be paid to remaining risks which
could have catastrophic impact (high severity) - Specify method of finance of the project
- Analyse effect on investors after inflation,
borrowing, tax
18The investment decision
- As well as probing the submission, decision
makers need to consider less concrete matters
outside the formal analysis, such as - possible bias or approximations
- lessons learned from previous experiences
- up-to-the minute developments that could impact
viability - doubts about feasibility or quality of
implementation - overall project credibility
- realism of estimated upside potential and
justification to proceed