Capital Project Appraisal - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Capital Project Appraisal

Description:

There is no reason to believe that there has been much change ... Natural ~ force majeure, climate change. Economic ~ interest rate and exchange rate moves ... – PowerPoint PPT presentation

Number of Views:150
Avg rating:3.0/5.0
Slides: 19
Provided by: Patr127
Category:

less

Transcript and Presenter's Notes

Title: Capital Project Appraisal


1
Capital Project Appraisal
  • Pat Ryan

24 February 2006
2
Capital project appraisal in practicecareer
opportunities for actuarial skills!
  • In 1998 the Association of Consulting Actuaries
    (ACA) and the Confederation of British Industry
    (CBI) surveyed large UK firms (turnover gt20m) in
    regard to their approach to key capital
    investment decisions.
  • The survey indicated a lack of rigour in the
    decision process of many firms.
  • There is no reason to believe that there has
    been much change since, or that practices in
    Ireland are superior.
  • We will look at this surveys results first and
    then devote the rest of the lecture to
    considering recommended practice.

3
Findings of survey by ACA CBIhow UK firms
approach key capital investment decisions
  • Appraisal techniques are not rigorously
    quantitative
  • 23 of firms did not use quantitative analysis
    at all
  • Only 60 reviewed the value of decision criteria
    regularly
  • management judgement had key role in setting a
    projects target
  • Many firms, ignore cashflow methods - rely on
    profit data
  • Many viewing cashflow judge only on payback (2 to
    4 yrs!)
  • Hurdle rates are often set at higher level than
    theory needs
  • Most dont decide solely on whether meets target
    rate
  • Most projections ignore inflation
  • Risk analysis often performed by people not best
    placed
  • Limited attention is paid to inter-related risks
  • Firms using high hurdle rates mostly in lower
    risk sectors

4
Capital project appraisalrecommended practice
  • This is a key part of the planning risk
    analysis stages
  • A capital project is described as up-front
    expenditure on asset creation for subsequent
    profit flows
  • intangible (e.g. patent) as well as tangible
    asset
  • Approach being discussed follows methodology of
    one stage of RAMP (Risk Analysis Management for
    Projects) process

5
RAMP life cycle of a projectprocess developed by
actuarial civil engineering professions
  • Opportunity identification
  • Detailed appraisal, leading to investment
    submission
  • - the stage being discussed today
  • Raising the necessary finance, design, contracts
    etc
  • Asset creation
  • Operation
  • Close-down

see www.ramprisk.com
6
Key stages in project appraisal
  • Initial appraisal of identified opportunity
  • core organisation criteria, strategic financial
  • synergy with other projects, upside potential
  • subjective dimension as well quantitative
  • risk for sponsors, lenders, investors. Mitigation
  • Detailed appraisal
  • entails choice of risk discount rate
  • risk identification, analysis, modelling,
    mitigation
  • investment submission

7
Detailed appraisal
  • Project definition, scope and timescale
  • must be clearly spelt out and agreed by all
  • clear specification of
  • success criteria
  • to whom goals of the project apply
  • responsibilities of people in project team and
    management team
  • Evaluation of cashflows, including knock-on
  • cap ex, running costs, revenues, termination cost
  • rigour is vital - should document all assumptions
  • first cut / NPV, IRR, (discounted) payback period
  • then apply sensitivity analysis / scenario
    testing
  • if satisfactory, then apply detailed risk analysis

8
Risk discount rate
  • Nominal rates for nominal cashflows
  • Distinguish between
  • specific (diversifiable / probabilistic) risk,
    and
  • systematic (non-diversifiable / market) risk
  • Increase discount rate for systematic risk

9
Choosing risk discount rate
  • Projects carrying normal degree of risk
  • incremental after-tax cost of (debt equity)
    capital
  • cost of equity risk free rate equity risk
    margin
  • Projects above normal systematic risk
  • ideally base on rates used by firms experienced
    in such projects ? in practice a judgment call
  • Other considerations
  • illusion of precision

10
Dealing with specific risks
  • Identification steps
  • high level cull of clearly-high-risk projects
  • brainstorming by project experts, senior internal
    and external people with a long view
  • to identify project risks, likelihood,
    interdependency, frequency severity, mitigation
    options
  • desktop analysis building on this and research
  • set out all identified risks in a Risk Register,
    cross referencing interdependencies

11
Risk types examples
  • Political war, govt / policy change, new laws
    taxes, trade restrictions, planning permits,
    third party opposition
  • Natural force majeure, climate change
  • Economic interest rate and exchange rate moves
  • Financial cashflow estimates, capital cost,
    assumptions, finance availability, sponsor
    dissent
  • Crime fraud, crime
  • Project ill-defined objectives, design flaws,
    information withheld, timescale, leading-edge
    technology, key personnel, contractor bankruptcy,
    decommissioning
  • Business volumes revenue, running cost,
    efficiency level, early obsolescence,
    competition, safety hazards

12
Analysis of identified risks
  • Each risk could be classified by 4 measures
  • frequency of occurrence or risk level
  • degree of dependence on other, separate risks
  • degree by which it can be mitigated or managed
  • financial impact
  • Expected cost of a given risk quantified in NPV
  • Low probability, high severity risks scrutinised
  • Distribution of NPVs for entire project modelled
  • by scenario analysis or stochastic modelling
  • (volume of assumptions limit stochastic model use)

13
Example probability dist of NPVs
Expected NPV 154,600. Losses 35 of time
Max loss 391,000
14
Risk mitigation
  • Options and examples
  • reduction
  • reducing risk (probability or consequence)
    modify design or build in safety margins
  • reducing uncertainty further research
  • transfer fixed price contract, pay insurance
    premium
  • avoidance redesign / abandon
  • absorb or pool organise syndicate, joint
    venture
  • Evaluation of each option to assess
  • effect on frequency, consequence expected value
  • feasibility cost of implementation
  • if any secondary risks resulting ? resultant
    mitigating actions
  • overall impact on the distribution of NPVs
  • Mitigation should reduce downward volatility of
    NPVs
  • if decreases expected NPV, need judgement call on
    trade-off

15
Example of trade-off judgement call
  • Work with the example in the table in slide
    number 13
  • The contractor is prepared to bear the whole of
    any extra costs / losses arising after year 1,
    provided the contract price is increased by
    80,000. This would arise in scenarios C E
  • Is it worth accepting the offer?
  • See workings on next slide

16
Example continuedeffect on distribution of NPVs
of paying contractor 80,000
Expected NPV 145,350. Losses 20 of time
Max loss 188,000
17
The investment submission
  • Reflect choice of best possible mix of mitigation
    options
  • Show expected NPV probability distribution of
    NPVs
  • Identify and analyse residual risks. Special
    attention should be paid to remaining risks which
    could have catastrophic impact (high severity)
  • Specify method of finance of the project
  • Analyse effect on investors after inflation,
    borrowing, tax

18
The investment decision
  • As well as probing the submission, decision
    makers need to consider less concrete matters
    outside the formal analysis, such as
  • possible bias or approximations
  • lessons learned from previous experiences
  • up-to-the minute developments that could impact
    viability
  • doubts about feasibility or quality of
    implementation
  • overall project credibility
  • realism of estimated upside potential and
    justification to proceed
Write a Comment
User Comments (0)
About PowerShow.com