2006 Fracture Critical Inspection by URS finds 3 cracked plates ... Snoopers, heater, etc. Begin bridge closure. Remove existing damaged plate. Remove bolts ... – PowerPoint PPT presentation

Number of Views:26
Avg rating:3.0/5.0
Slides: 33
Provided by: MPl7
Category:

less

Transcript and Presenter's Notes

Title: CombsHehl Bridge I275 Project


1
Combs-Hehl Bridge (I-275) Project
  • Splice Plate Retrofit

2
(No Transcript)
3
Timeline
  • 2006 Fracture Critical Inspection by URS finds 3
    cracked plates
  • 2007 KYTC staff finds cracks growing
  • Construction contract let to replace 3 cracked
    plates

4
Combs-Hehl Bridge (I-275) Original Project
Overview
  • FE02 019 0275 B00040
  • Campbell County
  • I-275 Westbound from Ohio to Kentucky over the
    Ohio River
  • Original Bid 193,256.01
  • Intech Contracting
  • 6 lane Interstate
  • ADT 83,500
  • Contract time Spec. Comp. Date June 15, 2008
  • Bridge Closure allowed 9 pm Saturday to 9 am
    Sunday morning (i.e. only 12 hours to do the job)

5
Combs-Hehl Bridge (I-275) Splice Plate Retrofit
  • Bridge Closure
  • Coordination and public information
  • Lane closures, detour traffic
  • Replace Splice Plates
  • Gather correct materials
  • Mobilization
  • Replace plates
  • Cleanup

6
Traffic Control
  • Close down I-275 Westbound from Ohio
  • Communication with involved entities
  • ODOT
  • City of Cincinnati
  • Extensive signage and coordination
  • ARTIMIS
  • Public information campaign
  • Detour SB I-71 to I-471

7
(No Transcript)
8
Splice Plate Replacement
  • Acquire matched plate
  • Field measure bolt holes and dimensions
  • Fabricate plate to match
  • Mobilize on bridge
  • Snoopers, heater, etc
  • Begin bridge closure
  • Remove existing damaged plate
  • Remove bolts
  • Mag Particle Test main steel members
  • Inspect condition of steel between plates

9
  • ..\My Documents\Combs Hehl Presentation\good
    pics\IM005850.JPG

10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
Splice Plate Replacement
  • Heat new plate
  • Had to be 250 degrees above the temperature of
    existing steel
  • Place new plate
  • Clean existing steel surfaces
  • Manipulate 300 degree, 500 lb steel plate

16
(No Transcript)
17
(No Transcript)
18
Splice Plate Replacement
  • Cleanup
  • Demobilize
  • Re-open bridge to traffic by 900am
  • Remove lane closures
  • Return to paint exposed steel

19
Timeline
  • 6-1-08 Original Contract completed
  • 72.00 over budget for extra police at
    intersection
  • 6-2008 Plates sent to IMR Laboratory for testing
  • Concluded that plates were improperly tempered
    and therefore extremely brittle
  • 10-2008 Burgess and Niple commences next biennial
    fracture critical inspection
  • BN find cracked ½ plate on EB bridge
  • Traffic reduced to one lane on each structure-
    after much discussion, coordination between FHWA,
    KYTC, ODOT later WB reopened
  • KYTC removes EB truck traffic ( 3 ton limit) to
    reduce loading
  • Lane closure used for hardness testing by UK Ted
    Hopwood
  • Emergency repair contract designed to replace 4
    plates on EB bridge

20
(No Transcript)
21
(No Transcript)
22
Change Order
  • 4 additional plates to be replaced, on eastbound
    bridge
  • Close down I-275 at I-471
  • All traffic control in Kentucky
  • Remobilize equipment
  • Crane
  • Manlifts

23
Traffic Control
  • Close down eastbound I-275 _at_ I-471
  • 3 lanes on I-275
  • 2 lanes, onramp from SB I-471
  • 1 lane, onramp from NB US 27 connector
  • Time limitations
  • Total bridge closure, 2 nights over 1 weekend
  • 9pm to 9am, Friday and Saturday nights

24
Splice Plate Replacement
  • 4 plates, U16 member
  • 80 ft above bridge deck
  • 10 degrees F, windy
  • Remove and replace opposite splice plates before
    touching adjacent plates
  • Work commenced over 02/11/08 through 02/13/08
  • Bridge re-opened to traffic at 800 am on 02/13/08

25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
Conclusion
  • 10 more non-critical plates need to be replaced
  • Through much coordinated effort and open dialogue
    with the public and the press we can confidently
    provide a safe highway and adequate mobility
    while also taking all necessary precautions.
  • The following is not our bridge!

30
(No Transcript)
31
(No Transcript)
32
Questions ?
Write a Comment
User Comments (0)
About PowerShow.com