Title: PRNAV
1P-RNAV Safety Assessment Safety
Argument September 2007 Ed Smith DNV
2Background to Safety Studies
- Over last 5-10 years EUROCONTROL produced a
series of P-RNAV safety studies - Last safety assessment (FHA/ PSSA) was completed
in May 2004 and safety argument (v2.0) in March
2005 - These documents received a lot of peer review and
comment - As a result EUROCONTROL commissioned a project in
late 2006 to review, re-verify and re-validate
these documents - Also extended scope, primarily to cover Non-Radar
environment and below MRVA/ MSA - That project has produced draft updates of the
FHA/ PSSA and the safety argument
3Overall Approach
Safety Targets
Top Down Review Are targets robust? Does FHA/
PSSA process make sense etc.
Bottom Up Review Are SRs achievable? Are they
consistent with TGL10, TSO C129a etc.?
FHA/ PSSA
- Safety Requirements (SRs)
- FSRs
- SIRs
4Key Tasks
- WHAT
- Set single consistent TLS
- Review hazard identification
- Expand to cover non-radar and below MRVA/ MSA
- Update severity/ frequency analysis
- Validate quantification
- Link quantification to mitigations under
stakeholder control - Address GNSS stand-alone navigation (GA focus)
- HOW
- ANSP stakeholder steering group
- Safety workshop multidisciplinary
- Review against documentation (TGL 10, TSO C129a
etc) - Review against other safety projects (TLS
setting, RNAV approach safety assessment etc.) - Review of all available data sources (RNAV track
keeping studies, database integrity etc.)
5Draft FHA/ PSSA Main Outputs
- Under review by ANSP stakeholders
- Preliminary main outputs
- All Functional Safety Requirements reviewed and
updated to address stakeholder concerns - All Safety Integrity Requirements (SIRs) updated
to reflect latest data sources - SIRs linked to practical risk mitigations
- Together all the above clearly show what is
needed to meet safety criteria
6Draft Safety Argument Main Outputs
- Addresses risk under failure conditions and
fault-free conditions - As before uses Goal Structured Notation (GSN) to
lay out key arguments and evidence - Slimmed down format
- Updated based on FHA/ PSSA latest
- Shows more clearly what EUROCONTROL has
demonstrated concerning P-RNAV safety and what
stakeholders need to do at a local level - The review activities have indicated that the
revised safety requirements are practicable and
realistic - Fulfilment of the requirements and/or the
mitigations that support the safety requirements,
are all capable of direct verification by
stakeholders
7Draft Safety Argument Structure
Arg 1
P
-
RNAV in TA has
been specified to be
acceptably safe
Arg 1.8
Arg 1.1
Backing evidence is
The underlying concept
available to show that
is intrinsically safe
direct evidence is
trustworthy
Arg 1.2
Arg 1.7
The system design is
complete
All safety issues have been
resolved or actions
identified to resolve
Arg 1.3
Arg 1.6
The system design functions
correctly and coherently under
That which has been
all expected conditions
specified is realistic
Arg 1.5
Arg 1.4
All risks from internal
The system design is
system failure have been
robust against external
mitigated sufficiently
abnormalities
8Summary
- Latest P-RNAV safety assessment activities have
addressed all the issues raised by stakeholders
at TERA and other fora - This has led to significant update of the safety
requirements to bring them more into line with
TGL10 and other available guidance/ data sources - Once comments from the ANSP steering group on the
draft deliverables have been received, the safety
assessment and safety argument documents will be
finalised - These should then facilitate the production of
local safety assessments/ safety cases