Title: Integrating Pavement and Maintenance Management Systems for Performance Based Contract
1Integrating Pavement and Maintenance Management
Systems for Performance Based Contract
Rotorua 2009
2Contents
- Process Design
- System Architecture
- Using System for ATP Development
- Conclusion
3Maintenance Planning Management
Business Process Defined in Asset Management Plan
4Levels of Planning
Strategic analysis is undertaken for entire road
network to define Long-term Maintenance Standard
Level of Service Not Project preparation is
carried out to compare and justify the benefits
and risk associated with implementing alternative
(often innovative) pavement treatment option.
Preparation of a 10-year Programme and annual
treatment program (ATP) is the most widely used
level of analysis.
Same dTIMS System is used although there is minor
difference in the Setup Used
5Contents
- Process Design
- System Architecture
- Using System for ATP Development
- Conclusion
6Software Modules
7AMIS Suits
- AMIS scheduler - to organise the inspections and
cyclic works programmes in accordance with
contract inspection frequencies and cyclic
programmed works - AMIS mobile - to collect spatially aware data in
the field - AMIS connect - to synchronise field data capture
with the central AMIS database - AMIS reporter - provides web based access to
customised reports
8AMIS Mobile Spatial Network
- Network maintenance hierarchy colour coded
- Non contract roads displayed for visible reference
9AMIS Mobile Network Inspection
10AMIS Mobile Network Inspection
11Exor Modules
- Public Enquiry Manager is used to log, track,
manage and resolve complaints and enquiries
related to the contract - Maintenance Manager manages workflow process of
the day-to-day routine maintenance tasks and
programmed activities performed on assets.
12Maintenance Manager
- Functions include
- Scheduled asset and network inspections
- Defects identification and treatment
recommendation - Assignment of relevant response time
- Estimation of level of efforts / bill of
quantities - Generation of Work Orders and records the
completion of each defect repaired - Progress monitoring of available budgets
13dTIMS CT
14AMIS - Reporter
15Dash Board
16Contents
- Process Design
- System Architecture
- Using System for ATP Development
- Conclusion
17Program Development Flow Process
18Data for ATP
- Provided by RTA (RAMS)
- Inventory (Annexure 19)
- Pavement condition (2007 Oct)
- Roughness, Rutting and Texture Depth
- Cracking
- Pavement strength (2007 Aug)
- Maintenance history (AMIS Database)
- Inspections
- Defects / Treatment History
- Visual condition assessment during field
validation process
19Data Processing / Review
- This process is undertaken annually
- To validate data provided by RTA for completeness
and consistency - Analysis of current and historical data for
calibration of assumed deterioration rates and
treatment resets - Reporting the pavement performance measures
20Trend Analysis
21Predictive Modelling
- Based on 100m lane sections
- Model Parameters Used
- Analysis parameters (e.g. condition data,
maintenance history, traffic volume) - Rate of condition deterioration
- Appropriate treatment types and unit rates
- Treatment triggers and condition resets
- Optimisation to achieve PPM values
- Analysis period to cover the term of contract
- Output
- List of candidate sites
- Forecasted PPM values
22dTIMS CT is used for Predictive Modelling
23PPM Forecast (AC_FLEX_3)
24PPM Cumulative Graph (AC_FLEX_3)
25Programmed Work
26Candidate Sites
- Generated using Models considering
- Latest available data (Inventory, Condition,
Pavement Strength etc.) - Maintenance history / issues
- Feedback from RTA (Preference sites)
- Previously committed sites (Excluded)
- Sites identified for special treatments (i.e.
skid resistance, bus lane surfacing)
27Field Verification(of Candidates Sites)
- Network drive through to validate
- Inventory and Condition data consistency
- dTIMS treatment appropriateness
- Timing of prioritisation
- Immediate intervention
- Shorter term intervention
- As per dTIMS selection
- Longer term intervention
- Indefinite deferral
28AMIS MOBILE is utilised in the field validation
process
29(No Transcript)
30Review and Consolidation
- Grouping of 100m sections into project length
block by Characteristic treatment and timing
Better to do at same time
- These blocks Committed in dTIMS to confirm PPM
values compliance
31GYPSY CAM was very useful for the consolidation
process
32Pavement Design
- Finalised flexible pavement sites
- Are investigated and classified according to
- Surface deficiencies (e.g. ravelling, rutting,
cracking) - Structural deficiencies (e.g. fatigue,
deformation, pumping) - Structurally deficient pavements are further
tested and designed using - Falling Weight Deflectometer (FWD) and validating
coring - EfromD3 and Circly 5.0
- AC Rigid (Asphalt surfacing on cement concrete
base) are inspected to decide if slab
stabilisation/replacement is required
33Annual Treatment Programme
34Job Scoping
- Job Walk Through to define
- Site constraints
- Traffic and traffic management
- Localised geometry, topography, geology
- Adjacent pavements
- Shear
- Constructability
- Layering
- Inter shift ramping
- Preceding works
- Work plans (shift by shift)
35Planning Board
- Preceding activities
- REF
- Traffic Control Plans
- Road Occupancy Licence
- Resident Notification
- Sequence of activities
- Interdependency
- Durations
36Records
- Accurate data collection of completed works
- Lot Packages for QA purposes
- Data managed and reported through AMIS
37AMIS - Data Management
Include information of pre-work, ancillary and
subsequent treatments
38Conclusions
- Fully integrated and configurable AMIS system
well customised to local conditions can help to
manage a performance based contract more
efficiently - The system design should be based on well defined
and comprehensive business process. - Economy and better performance can be achieved
with using various off-the-self software (best
available for specific purposes) together with
in-house developed software to fill the gaps - Both process and software system need ongoing
refinements to ensure the issues identified and
lesson learnt could be utilised. - Strong in-house team consisting of asset
management specialists, system analysts and
developers working side by side with operational
personnel could provide the best results
39Thank You