Title: CCW Plant Expansion


1
CCW Plant Expansion CCW Piping
Thomas F. Joos, PE Lead Civil/Structural
Engineer CFAC Review March 10-11, 2009
2
Outline
  • CCW Plant Expansion (WBS 1.05.03.04)
  • Construction Package Scope
  • Construction Package Schedule
  • Construction Package Management/Oversight
  • CCW Piping (WBS 1.05.03.05)
  • Construction Package Scope
  • Construction Package Schedule
  • Construction package Management/Oversignt

3
CCW Plant Expansion
  • Scope (WBS 1.05.03.04)
  • Five (5) bay expansion to the existing CCWF
    (B-0600),
  • Central Chilled Water (CCW) Plant expansion
    shared between NSLS-II and BNL
  • NSLS-II share is 3 bays two chillers-
  • Expansion of the CCW Pump House (B-0600A) by five
    (5) pump bays
  • Installation of two (2) 1,250-ton electric
    centrifugal chillers associated pumps
  • Addition of two (2) cooling tower cells (cooling
    tower basin construction for 5 cells)
  • Addition to existing electrical substation
  • Associated electrical, mechanical, HVAC
    infrastructure and site work.

4
CCW Plant Expansion
  • Construction Package Schedule Baseline CWE
  • Bid Package available (design pkg) 12/10/08 11/1
    9/08(A)
  • Bid Solicitation (IFB in DOE review) 1/29/09 3/1
    3/09
  • Bids Returned 3/3/09 4/26/09
  • Contract Award 4/28/09 5/29/09
  • Notice to Proceed (Construction
    Start) 6/4/09 7/06/09
  • Construction Complete (Beneficial
    Occupancy) 3/24/11 1/31/11
  • Operations (CCWF added capacity
    available) 3/24/11 2/28/11
  • Procurement process is lagging by 1 month but
    have 3 months float before CCW is needed

5
CCW Plant Expansion
  • Construction Package Management/Oversight
  • Design
  • Design by Giffels Partnership (consultant A/E)
  • Design management by BNL Energy Management
    Division (EMD)
  • Design review by NSLS-II
  • Procurement
  • Bid solicitation by BNL Procurement Property
    Management Division (PPM) with BNL Modernization
    Program Office (MPO) ()
  • Review by NSLS-II ()
  • Construction
  • Construction management/oversight by BNL MPO ()
  • Review by NSLS-II ()
  • - These activities performed in accordance with
    a CCW Expansion Project Management Plan to be
    issued by NSLS-II

6
CCW Plant Expansion
North
7
CCW Plant Expansion
North
3 Additional Bays 2 Chillers for NSLS-II
New
Existing
2 Additional Bays for BNL
B-600 Operating Floor Plan
8
CCW Piping
  • Scope (WBS 1.05.03.04)
  • New 24 diameter CCW Supply, 24 diameter CCW
    Return 3 diameter Compressed Air piping
  • New piping extends between the existing CCW/CA
    mains on Rochester Street to a point at the edge
    of the NSLS-II Ring Building Construction site
  • Total distance of approximately 1,100 feet
  • Includes all excavation/backfill, valves,
    appurtenances and connections to existing CCW and
    CA mains and site restoration.

9
CCW Piping
  • Construction Package Schedule Baseline CWE
  • Bid Package Ready 2/26/09 3/23/09
  • Bid Solicitation 4/20/09 4/17/09
  • Bids Returned 5/4/09 5/08/09
  • Contract Award 6/1/09 5/22/09
  • Notice to Proceed (Construction
    Start) 6/29/09 6/19/09
  • Construction Complete 12/31/09 12/18/09

10
CCW Piping
  • Construction Package Management/Oversight
  • Design
  • Design by Giffels Partnership (consultant A/E)
  • Design management by BNL Energy Management
    Division (EMD)
  • Design review by NSLS-II
  • Procurement
  • Bid solicitation by BNL/ NSLS-II PPM
  • Construction
  • Construction management/oversight by NSLS-II

11
CCW Piping
North
B-0452
Upton Gas Station
Existing CCW/CA Mains (Rochester Street)
CCW Piping Plan Part 1
12
CCW Piping
Existing Drainage Swale Culverts
North
Interface with Ring Building Piping
Intersection Rowland St. Groves Street