Title: SMOOTH GUTTER LINES
1Rocky Mountain Asphalt Conference and Equipment
Show February 19, 2009 Best Practices in Using
Slurry Systems Presented by Nathan
Niemann
2(No Transcript)
3ASPHALT
Pavement Preservation Is a must for
4Slurry SystemsMicro-SurfacingSlurry Seal
- Road Selection
- Pre-construction
- Construction
- Post-Construction
5Road Selection
- A bad road covered with a slurry system is just a
bad road with slurry on it. - Maintenance on any road boils down to keeping out
the water. - Right Road, Right Treatment, Right Time.
6(No Transcript)
7(No Transcript)
8Pre-Construction
- Materials
- Testing
- Mix Design
- Testing
- Stockpiling
- More Testing
- Calibration
9Materials Testing
- Emulsion
- Type of emulsion
- CQS-1HP,CSS-1HP
- CSS-1H, SS-1H
- CQS-1H, QS-1H
- Quality Asphalt
- Formulation
- Mineral Filler
- Lime, Cement
- Aluminum Sulfate
- Aggregate
- Gradation
- Sand Equivalent
- Soundness
- LA Abrasion
10Good Aggregate Source
11(No Transcript)
12Mix Design
13Hand mix to verify mix time.
14Soaking 1 hour or 6 day
15Wet track abrasion
16Looking for aggregate loss on wet track
17Wet cohesion tests set time and time to traffic
18(No Transcript)
19Loaded wheel test
20Lateral displacement and sand adhesion
21Schulze-Breuer
22(No Transcript)
23(No Transcript)
24Stockpiling
- Contamination
- Job Mix Formula
- More Testing
- Narrow band Gradations
- Target Gradations
25Tolerances for JMF
26Provide Adequate Area for Staging
27Calibration
- Calibrate Rock
- Calibrate Emulsion
28Calibration
29Calibrate Equipment
30Aggregate Gate
31Aggregate Gate Setting
32Aggregate Belt
33Counters Flow Meters
34Take the Time to Know
- Measure Twice Cut Once.
- You should know the mix will work before you ever
start.
35Construction
- Road Preparation
- Test piles Sections
- Equipment Maintenance
- Joints
- Hand Work
- What to do if you have a problem
- Documentation
36Road Preparation
- Crack Seal
- HMA Patching
- Weeding
- Paint removal
- Oil spot removal
- Sweeping
- Protect Utilities
37Crack Seal Prior To Maintenance
38Crack Seal
39Asphalt Patching
40 Not Acceptable Patching
41Asphalt Preparation
42Remove Weeds
43Remove Paint
44Grind Off Oil Spots
45Sweep Off All Loose Materials
46Dirt And Mud Removal
47Covering Manholes
48Not Acceptable
49Not Acceptable
50Placing
51Equipment
- Daily Cleaning
- Daily Maintenance
52(No Transcript)
53Mixing Chamber Pug Mill
54(No Transcript)
55Slurry Box With Augers
56Joints and Seams
- Square Transverse joints
- Use paper when needed
- Straight Seams
- Gutter Lines
57(No Transcript)
58Clean Gutter Lines
59Longitudinal joints
60Good Seams are not eye-catching
61Unsightly Lines
62Long Straight Lines
63(No Transcript)
64Hand Work
- Make it match
- Dont leave excess material
- Cover your tracks
65Good Seams
66Handwork With Squeegees
67Finishing Ends of Streets
68Good Texture
69What you should to do if you have problems.
- Very Hush-Hush trade Secret
- STOP Working
- Call Suppliers
- Run Tests (Again as needed)
- Identify the problem
- Implement the solution
70Oversize Rock in the Mix
71Drag Marks
72Documentation (What I Track)
- Keep track of where each load of emulsion went
- Keep track of application rates
- Keep track of patching needed
- Know remaining materials on hand
- Quantities under runs and over runs for ordering
enough materials - Dont Guess Know
73(No Transcript)
74Screener Weight Bin
75Post-Construction
- If it looks bad it is bad
- Clean up you messes
- Patch areas that need it
76Tire Damage
77Oops
78Questions?