Title: 805%20MHz%20Pillbox%20Cavity
1805 MHz Pillbox Cavity
(IIT, Chicago, IL, Feb. 7th, 2002)
- Derun Li
- Center for Beam Physics
- Lawrence Berkeley National Laboratory
2Collaborators
- J. Corlett, A. Ladran, R. MacGill, R. Rimmer,
- J. Wallig, M. Zisman
- Lawrence Berkeley National Laboratory
- Berkeley, CA 94720
- D. Summers, M. Reep
- University of Mississippi, Oxford, MS
- A. Moretti, A. Rowe, Z.B. Qian, V. Wu
- Fermi National Accelerator Laboratory
- Batavia, IL
3Introduction Review
- Development of the 805 MHz Pillbox cavity
- High shunt impedance and high acceleration
gradient at order of 30 MV/m - Allow for testing of Be windows with different
thickness, coatings and as well as other windows - Study RF cavity operation issues under the
influence of strong magnetic fields at both the
solenoid and gradient modes - The cavity design and status
- The 805 MHz pillbox cavity design should allow
for testing of different windows ? demountable
windows to cover the beam irises (we have five Be
windows, four Cu windows ...)
4Cavity Design status
Coupler
Waveguide window
Thermo-couples or view ports
Be (or Cu) windows
Three more view ports on the equator
Pillbox cavity
5Cavity Design Parameters
- Frequency 805 MHz
- Shunt Impedance
- 38 M?/m (Z0) 32 M?/m (ZT2) Z V0,T2/P
- Quality factor Q0 18,800
- Coupling Constant
- ?c 1.0 at critical coupling ltEgt 30 MV/m
requires 2 MW peak power, 350 watts average, 52
watts on windows (Cu, 66 watts for Be) at duty
factor of 1.8x10-4 (12 FNAL19 us pulse length
and 15 Hz repetition rate).
6Manufacturing of the cavity
- The cavity was fabricated at University of
Mississippi, brazed at Alpha Braze Comp.
7Cavity and coupler tuning
- The cavity was ready for final tuning for the
frequency and coupling in June, 2001. - (June 24-27, 2001 in University of Mississippi)
- Before tuning f 803.198 MHz, ?c 0.12
- After tuning f 805.486 MHz, Qext 12,800
- After final brazing
- Measurements done in November 14, 2001 at LBNL
before shipping to Lab G at Fermilab
f 804.946 MHz, ?c 1.3, Q0 15, 000
8Cavity Tuning (continued)
Michael and Daniel assembling the cavity
Cavity halves, coupler and Cu windows
9Cavity Tuning (Continued)
- Frequency tuning (shortening the gap)
- Coupler tuning (widening coupling slot and
shortening the transition waveguide)
Coupling slot
10Coupler Tuning (continued)
- The couple slot angle
- was widened from
- 400 to 500 (two cuts)
- in order to get close
- to critical coupling.
- Measurements of
- the coupling agree
- well with time domain
- MAFIA simulations
11Vacuum issues
- After final brazing at Alpha-Braze Comp.
- Vacuum leaking was detected at the coupler.
- Cu coating on the big transition waveguide was
stripped and re-coated at LBNL.
12Modification to coupler
O-Ring Grove
13Vacuum issues (continued)
- Old flanges were removed, and welded with new
ones - UHV cleaning, RGA scan
- Test setup at LBNL
14Vacuum issues (continued)
- After many failures, an O-ring at the transition
of the coupler guard vacuum were employed - Cold and hot N2 gas was used to flush and bake
the system - Before shipping to Lab G at Fermilab
- Leak tight with base pressure (after a few days
baking) 3x10-8 Torr and a clean RGA scan - Shipped to Fermilab under pressured N2 gas.
- Lesson learned
DONT MACHINE A BRAZED JOINT ? IT MAY LEAK !
15Diagnostics
- Three view ports on the equator of the cavity
- Three RF probes (adjusted to about -52 dB gain
from the standard waveguide port) available for
E M field measurement - An optic bore-scope can be used to inspect the
windows and inner surface of the cavity ( need
lighting and TV/VCR for viewing and recording) - Maximum six thermo-couples can be attached to
monitor temperature distribution on windows - Two compartments behind the cavity can be used to
measure window deflection by frequency shift
16Diagnostics (continued)
- Equipment available
- at Lab G
- x-ray, dark current
- spectrum, forward
- reflected RF power
- and arc detector
- Lab G layout ?
17 Be windows
- Pre-stress study of the Be windows
- Received two more Be windows (10,20 mills)
- Two new copper windows with coatings
- Halogen lamp heating measurements on two failed
Be windows - Accelerometer measurements
- Acoustic measurements
- FEA (ANSYS code) modeling
- Magnetic and E M forces on windows
18 Be windows (continued)
Acoustic Measurement
Setup for accelerometer measurement
19Current Status
- Cavity with Cu windows is now at Lab G
- Leak tight at pressure of 2x10-7 Torr (1/22/02)
- Braces are being made at Fermilab
- Leak checking is underway
- Waiting for vacuum parts to be made for final
assembling of the vacuum and waveguide system - LBNL personnel (with test plan) will be at Lab G
in Fermilab before turning on the RF power
20Test Plan
- A complete microwave measurement
- Resonant frequency
- Coupling constant
- Q factor
- Verify calibration of the RF probes
- Final assembling of the vacuum/waveguide systems
- Bake with N2 flow at 100 oC for two days
preferably with RGA scans
21Test Plan (continued)
- Continue baking at vacuum for two days
- RF conditioning slowly starting at low power
- Push for high gradient
- 2.5 MW peak power ? 34 MV/m accelerating gradient
and 500 watts at 1.8x10-4 duty factor - Turn on superconducting magnet in solenoid mode
to repeat above studies - Replace two Cu windows with the ones with TiN
coatings
22Test Plan (continued)
- Should we test Be windows? NO!
- EHS issues need to be addressed first
- may contaminate the vacuum system
- Future test plan depends on the upcoming test
results and inputs from MUCOOL collaboration.