Title: Session 8 Bridge Geotechnical Reports
1 Session 8 BridgeGeotechnical Reports
2 3 - OGE
- ORGANIZATIONAL BACKGROUND
4(No Transcript)
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9 PDP Major ProjectStep 7Type Study
Foundation Recommendations
10Preferred Verification Study
- Design Topics
- Survey
- Geometrics
- Geotech
- Pavements (DESIGN)
- Drainage
- Structure Type Study
- Maintenance of Traffic
- (Cont.)
- Geotech
- Complete Subsurface Investigation
- Including recommendations
- Pavements
- Request pavement design
- Subsurface drainage requirements
Step 7 major
11Preferred Verification Study
- Design Topics
- Survey
- Geometrics
- Geotech
- Pavements
- Drainage
- Structure Type Study
- Maintenance of Traffic
- (Cont.)
- Structure Type Study
- Hydraulic study and scour
- Structure Types
- Clearances
- Maintenance of Traffic
- Permitted Lane Closures Exceptions Committee
Step 7
12Preferred Verification Study
- Design Topics (cont.)
- Traffic Control
- Other
- Right of Way
- Environmental
- Sheets
- Cost Estimates
- Reviews
- Traffic Control
- Signal Warrants
- Other
- Airway/Highway Clearance Analysis
- Retaining Wall Justification (two parts)
- Pedestrian Overpass Justification
- Noise Wall Justification
Step 7
13- BDM 201.2
- STRUCTURE TYPE STUDY SUBMISSION REQUIREMENTS
- A. Profile for each bridge alternative Section
201.2.1 - Preliminary Structure Site Plan Section 201.2.2
- (preferred bridge alternative)
- C. Hydraulic Report Section 201.2.3
- D. Narrative of Bridge Alternatives Section
201.2.4 - E. Cost Analysis Section 201.2.5
- F. Foundation Recommendation Section
201.2.6 - G. Preliminary Maintenance of Traffic
Plan Section 201.2.7
14- 201.2.6 FOUNDATION RECOMMENDATION
- The Structure Type Study shall include a
Foundation Recommendation - that consists of
- A. General foundation type (i.e. Drilled
Shafts, Friction Piles, Bearing Piles or Spread
Footings) - Embankments ,MSE
- B. Typed boring logs
- C. Laboratory test results as follows
- 1. Soil Water content, particle size
analysis, liquid limit, plastic limit - 2. Rock RQD
- For the scour evaluation, Section 203.3(D),
provide D50 values from the - particle size analysis.
- When unique subsurface conditions arise, include
a brief narrative in the - Foundation Recommendation for justification to
obtain extra soils borings.
15- 201.2.6 FOUNDATION RECOMMENDATION
- The Structure Type Study shall include a
Foundation Recommendation that consists of - A. General foundation type (i.e. Drilled
Shafts, Friction Piles, Bearing Piles or Spread
Footings) - B. Typed boring logs
- C. Laboratory test results as follows
- 1. Soil Water content, particle size
analysis, liquid limit, plastic limit - 2. Rock RQD
16Rock Quality DesignationRQDHow related to
Scour50
17- 202.2.2 FINAL MAINTENANCE OF TRAFFIC PLAN
-
- In addition to the Preliminary Maintenance of
Traffic Plan requirements of Section 201.2.7, the
Final Maintenance of Traffic Plan should include
the following information - A. Plan views and preliminary working drawings
to ensure constructability - B. Temporary barrier anchorage details and
requirements - Location and type of temporary shoring
- (See Section 208)
- D. Location of structural members that require
strengthening - E. Temporary structure design information (See
Section 500) - Additional notes and/or details necessary
18BDM 208 TEMPORARY SHORING Whenever shoring
is required to support a roadway where traffic is
being maintained and the height of the retained
earth will be over eight foot , the Design Agency
shall be required to provide a temporary shoring
design with details provided in the plans and
feasibility studied during the Structure Type
Study. For projects involving Railroads, the
requirements will be different as each railroad
company has their own specific requirements. The
Design Agency is responsible for contacting the
responsible railroad and obtaining the specific
requirements for design and construction.
19EXAMPLE DELIVERABLE
- FOUNDATION RECOMMENDATION
20(No Transcript)
21(No Transcript)
22(No Transcript)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26PLANNING BY PROJECT MANAGER
- GETTING BORINGS HAS TO BE AN EARLY ACTIVITY IN
STEP 7
27GOPHER
COLLECT DATA
28EXISTING INFORMATION
- WHO TO CONTACT
- GET BORINGS FROM OTHER PROJECTS
- GET PILE DRIVING RECORDS
- ODNR
29WHAT DO WE DO WITH THE EXISTING GEOTECHNICAL
INFORMATION?
30HOW MANY BORINGS
- TAKE AN APPROPRIATE NUMBER SO THAT THE DESIGNER
HAS REASONABLE CONFIDENCE IN THE OVERALL
GEOTECNICAL DESIGN - WHAT ARE THE TYPICAL REQUIREMENTS FOR A BRIDGE
31 32GEOTECHNICAL RECIPE
33GUIDELINES
REQUIREMENTS
34Depth of Borings and Number of Borings Be
rational when doing this
- 2.2.3.1 Bridges
- Borings for bridges in soil shall penetrate
through soft or loose strata and 30 feet into
hard or dense soils requiring not less than 30
blows per foot -
- Borings in soil shall be carried to a depth of
not less than 30 feet below the proposed bearing
elevation of the footing. - Where bedrock occurs above the proposed footing
elevation, sound bedrock shall be cored to a
depth of 5 feet below the proposed footing
elevation. - Where bedrock is encountered 20 feet or less
below the foundation bearing elevation, sound
bedrock shall be cored to a depth of 10 feet. - Where bedrock is in excess of 20 feet below the
footing elevation, sound bedrock shall be cored
to a depth of 5 feet.
35SPECIFICATIONS FOR SUBSURFACE INVESTIGATIONS
36The Rod Machine
37FOR MAJOR PROJECTS PROJECT MANAGERSSHOULD
CONSIDER REQUIRING A PROPOSED GEOTECHNICAL
TESTING AND BORING PLAN
38Cost of Geotechnical Work 10Cost of a
boringsStructure5000Roadway 500
39Depending on the schedule you may want to
begin working on the type study with field hand
scribbled logs
40(No Transcript)
41- BDM 201.2.6
- FOUNDATION RECOMMENDATION
- For the scour evaluation, Section 203.3(D),
provide D50 values from the particle size
analysis. - When unique subsurface conditions arise, include
a brief narrative in the Foundation
Recommendation for justification to obtain extra
soils borings ( WALL JUSTIFICATION STUDY).
42Bedrock Contours
43MSE WALLSTYPE STUDYEVALUATION REPORT
- BEARING PRESSURE
- SETTLEMENT
- GLOBAL STABILITY
- INTERNAL STABILITY / STRAP LENGTHS
44(No Transcript)
45(No Transcript)
46(No Transcript)
47(No Transcript)
48(No Transcript)
49(No Transcript)
50(No Transcript)
51(No Transcript)
52(No Transcript)
53- 204.4 ABUTMENTS SUPPORTED ON MSE WALLS
- When conditions are appropriate, the designer may
consider stub type abutments with piling or
spread footings supported on MSE walls. The
Foundation Report for this type of abutment shall
include allowable bearing pressures, settlement
and bearing capacity calculations and all
construction constraints that may be required
such as soil improvement methods. Consult the
Office of Structural Engineering for additional
design recommendations.
54PILES OR NO PILES
55(No Transcript)
56(No Transcript)
57RAILROAD OVERPASS
58CODOT, Pueblo County
59GEOTECHNICAL WORK
- Communication and coordination between the
Geotechnical Engineer and the Design Engineer - Meetings
- Information exchange-Progress Reports
60The Geotechnical ProcessEarly Activity in Step 7
- Research
- Plan
- Drill, field work
- Record
- Test
- Coordinate with Designer
- Report containing the geotechnical conditions and
design recommendations
61Step 8 - Stage 1 Detailed Design LD 1403.7
- Design Topics
- Survey
- Geometric
- Drainage
- Right of Way
- Traffic Control
- Environmental
- Structures
- Preliminary Structure Design Report (Previously
TSL)
62 PDP Major ProjectStep 8Preliminary Design
ReportStage 1 Foundation Report
63- 202.2 BRIDGE PRELIMINARY DESIGN
- REPORT SUBMISSION REQUIREMENTS
- Final Structure Site Plan Section 202.2.1
- Final Maintenance of Traffic Plan Section 202.2.2
- Foundation Report Section 202.2.3
- D. Supplemental Site Plan for Railway
Crossings Section 202.2.4
64- 202.2.3 FOUNDATION REPORT
- The Bridge Preliminary Design Report shall
include a Foundation Report in - accordance with the ODOT Specifications for
Subsurface Investigations. - The Foundation Report shall include
- A. Investigational Findings
- B. Analyses and Recommendations
- C. Boring Logs and Undisturbed Test Data
- Where the scour evaluation has been identified a
potential problem, the - probable scour depths, calculated in accordance
with Section 203.3(D), - should be considered in the design of the
substructures the location of the - bottom of footings the minimum tip elevations
for piles and drilled shafts - and the frictional capacity of piles and drilled
shafts. - Specific design considerations for each
foundation type are presented in
65(No Transcript)
66- 5.2 STRUCTURE FOUNDATION
- INVESTIGATION
- The report of the subsurface investigation for
bridges, culverts, retaining walls, or other
structures shall be presented as - plan drawings in the form of a
- Structure Foundation Investigation.
67- 5.2.1 Form of Presentation
- 5.2.2 Front Sheet
- 5.2.2.1 Legend
- 5.2.2.2 Supplemental Information
- 5.2.3 Plan and Profile
- 5.2.3.1 Plan View
- 5.2.3.2 Profile View
- 5.2.4 Typed Boring Logs
- 5.2.4.1 Heading
- 5.2.4.2 Boring Information
- 5.2.5 Presentation of Undisturbed Test Results
685.3 REPORT OF FINDINGS AND RECOMMENDATIONS
- A report of the investigation's findings along
with analyses and recommendations shall be
presented in a written text or letter format. The
report shall be included in the appropriate
preliminary design submissions as stated in the
Location and Design Manual and the Bridge Design
Manual.
695.3.2.2 Structures
Foundation or pile type, treatment of the
foundation, allowable bearing of spread footings,
design of piles and their estimated length,
footing elevations, construction sequence,
instrumentation, field controls and any other
design factors affecting the project shall be
noted. Non-specific recommendations are not
acceptable.
705.3.2.2 Structures Recommendations related to
the design and construction of structures shall
include foundation recommendations and any
remedial measures necessary to complete the
project. All available subsurface information,
new and/or previously performed, shall be
considered in making recommendations.
71- 5.3.2.2 Structures
- A statement of the parameters used in the
analysis of the foundation design, such as those
related to bearing capacity and settlement, shall
be presented. - The method of analysis and diagram of the
section analyzed shall be shown. - Each pier and each abutment shall be
individually considered. - Consideration shall be given to the effect of
approach embankment loadings on the piers and
abutments.
72THE END