Title: Combined Heat and Power Project
1Combined Heat and Power Project
- 2008-04-29 Final Report Presentation
- Lindsay Booth, Jon Bortles, Ben Horowitz, Brad
Queen
2How Much Does Cogeneration Help Reduce Emissions?
- 2004 Stanley Consultants study showed purchase
electricity as least cost option. Updates at
higher natural gas prices reinforced finding. - Reduction in cogeneration of electricity has
increased emissions - Campus expansion will increase emissions further
3Current plan is to build a new heat plant without
Cogen
1.361 cent/kWh difference 110,465,500 kWh
1,503,435 (most of cost difference) However,
carbon cost of 26/Tonne and 2 lbs/kWh generation
is ? 2.449 cents/kWh
Plant Relocation-short version.ppt
4UCB Goals / Priorities
- Safety
- Reliability (in part via redundancy)
- Minimize cost
- Reduce carbon emissions (per CAP for CU State)
- Electricity
- Heat
- Cooling
- Long term price and supply risk mitigation
- Space and access problems with power house
- Provide for growth in energy usage (incompatible
with 4)
5Things That Have Changed Since 2004 Analysis
- CUs adoption of the American College
University Presidents Climate Commitment (ACUPCC) - Colorado governors goals
- The probability of carbon cost (due to federal
cap trade or carbon tax legislation) has
increased dramatically. Xcel and the Electric
Power Research Institute are factoring it into
their planning and so should CU - Both natural gas and coal costs have become
volatile - More efficient replacement cogeneration equipment
should have been included in the Stanley
Consultant studies - Single turbine operation at higher capacity and
efficiency may lead to lower costs than the low
capacity factors and poor efficiency of the
Stanley study. However, there are design
limitations. - Xcels recent announcement of a smart grid
prototype in Boulder will lead to time of use
electricity rates and may change rules for
standby tariffs
6Questions
- Data on current system
- Whats the carbon cost of cogen and non-cogen
scenarios (taxes and offsets)? - Are there newer technologies that improve
efficiency? - Are there grants, financing, or ESCo options that
reduce costs of cogen? - Does carbon cost change the lowest cost result.
- How much of a gap will develop between carbon
neutrality plan and emissions growth/reductions
planned?
7Campus Demand
8Methodology
- New gross square feet on campus in the next 5
years 1,247,680. - This is a 13 increase over the 9,296,759 square
feet in the 2005 carbon inventory - Steps
- Multiply GSF by
- a) Campus averages for traditional buildings and
- b) LEED buildings (high/low error bars) averages
- Subtract the above total by of 20 of existing
buildings with planned retrofits - Compare to 2005 baseline for kWh, Klbs, and tons
chilled water - Convert above values to tons of CO2 (where
feasible)
9Assumptions
- Business as usual, purchase electricity from Xcel
and follow CIP - Omit Visual Arts
- -20 for LEED when data not available (building
standards at LEED silver/gold) - Average Wolf, Atlas, Koelbel kWh/GSF for the
low electricity factor - Emission factors provided by EPA, Xcel, Stanley
report - Geosciences and biotech high electricity value
is comparable to Cristol and Porter. - Used base year of 2005/2006
- All new buildings and retrofits will be additions
to the chilled water demand.
10Results Demand
11(No Transcript)
12(No Transcript)
13(No Transcript)
14Results NEW Emissions
15Keeping our Commitments?
- Not entirely from the demand side.
TonsCO2
16Planned Capacity Expansion
- Current Peak Demand
- 20 MW
- 160,000 lbs steam / hr
- 7,000 tons of cooling
- Current Peak Capacity
- 32 MW with both turbines
- 370,000 lbs steam / hr
- 3,300 tons of cooling (using steam)
- Planned Peak Capacity
- 400,000 lbs steam / hr
- 15,000 tons of cooling
- Current Power House
- 2 natural gas fired 16 MW turbine generators that
also produce 60,000 lbs per hour of steam each. - 2 gas fired boilers that produce 100,000 and
150,000 lbs per hour of steam - 3 absorption chillers with a total combined
capacity of 3,300 tons
17Cogeneration and Cost Models
18Energy Use and Losses with CHP
http//www.epa.gov/chp/documents/intro.pdf
19UCBs Cogeneration PlantCombustion Turbine with
Heat Recovery Steam Generator (HRSG)
2
3
3
2
1
1
4
4
4
Combustion Turbine http//www.energysolutionscente
r.org/DistGen/Tutorial/CombTurbine.htm
20Alt. 1 (Cogen) vs. Alt. 2A (Xcel) Breakeven Gas
Price (from Power Plant Relocation Proposal,
September 2006)
March 6, 2008 The spot price at the Henry Hub
increased 16 cents per million Btu (MMBtu) or 1.7
percent on the week, averaging 9.37 per
MMBtu http//tonto.eia.doe.gov/oog/info/ngw/ngupda
te.asp
Mitsubishi MF-111B Turbine manufacturers
reported heat rate 11024 Btu/kWh ( 2,778
kcal/kWh) for simple cycle only http//www.mhi.co.
jp/en/products/detail/mf-111.html CU
performance with steam augmentation is even
better 10250 Btu/kWh per power plant data sheet
/MMBtu
Reported in September 2006
Net heat rate with recovered heat will be even
further left on this curve
Turbine
(A measure of turbine operating efficiency)
21Turbine Efficiency Is Related to Output
22Electric Power Research Institute (EPRI) View of
the Future Comparative Costs of Generating
Options
Assuming sufficient RD and the successful
deployment of several low- and non-emitting
technologies, the market choices will among the
new alternatives to coal will depend in large
measure on tow key uncertainties the price of
natural gas and the cost of CO2 emissions
controls and/or market credits.
100
100
IGCC w/o CSS
90
90
80
80
NGCC_at_12/MMBtu
70
70
Wholesale Levelized Cost of Electricity, /MWh
NGCC_at_6/MMBtu
60
60
50
50
26/metric ton CO2
40
40
Coal w/o CSS
30
30
0
10
20
30
40
50
Cost of CO2, /metric ton
Source Original chart prepared by EPRI,
Generation Options in a Carbon Constrained World
2005, NYMEX NG Futures Jan 2006
23Electricity Rates / New CHP Technologies
24Electricity Rates
Primary Standby Tariff (PST) Demand
charges Energy charges The Electrical Commodities
Adjustment Standby charges (per kW)
Primary General Tariff (PG) Demand charges (per
kW) Energy charges (per kWh) The Electrical
Commodities Adjustment (per kWh) (fuel
volatility)
25CHP Technologies that Match UCB Needs
x
x
x
x
x
x
x
x
x
x
http//www.epa.gov/chp/documents/intro.pdf
26New Technologies Gas Turbines
- Type of turbine in the current plant
- Technology has gradually improved since the plant
was built - Available in sizes from 500 kW to 250 MW
- Time overhaul ranges from 25,000 to 50,000 hours
27Gas Turbines Efficiency
- Efficiency has been improving with time, so newer
machines are more efficient than older ones of
the same size and type - Can reach overall CHP system efficiencies of 70
to 80
28Gas Turbines Emissions
- One of the cleanest means of generating
electricity from fossil fuel - Natural Gas is the primary fuel turbines are run
on - Emit substantially less carbon dioxide per kWh
than any other fossil technology in commercial
use
29Gas Turbines Capital Cost
- Purchasing new efficient technology can be more
cost effective then refurbishing current turbines
30Comparable CHP Projects andEnergy Service
Companies
31Grabbing the Low Hanging Fruit
- UCB capable of internally replicating the
services of an ESCo? - ? Energy efficiency overhaul energy cost
savings via conservation - 15-40 increased energy efficiency (X
million/year) - Savings earmarked and used to fund capital
improvement projects (co-gen) - Oberlin report the establishment of an
internal energy market - The Deliverables What NORESCO brings to the
table - Not your typical ESCo - So much more than
conservation - The co-gen masters CEO/President Neil
Petchers - ? Advantages of ESCos assumes all upfront
project costs shifting the financial risk - ? The guarantee (and the incentive) they wont
get paid until they walk the talk - ? Tremendous pressure to succeed to get it
right and do a good job - Does this same pressure exist internally at UCB?
32Acknowledging Competing Interests
- Reconciling the Aforementioned Pressures
- Internal factions at UCB pressured to deliver
same results as an ESCo? Not yet. - First getting our own house in order
dismantling silos, getting aligned with the big
picture - Pressures on facilities/internal personnel
reliability, cost effectiveness but what about
the big picture (ACUPCC, Governors goals,
Capital Improvement Plan/Flagship 2030)? - Can contracting with NORESCO aid in this
process?
33Contracting with NORESCO Controlling the
Outcome A Dynamic Working Relationship
- Recognizing Party Lines Maintaining Ownership
- CNWG facilities internal party, NORESCO
external - Recommendation approach NORESCO armed with a
plan and a vision - This is what we want, this is how we want to
do it, this is how you (NORESCO) can help - A hands-on relationship with NORESCO must be
driven by involvement working in concert - Internal forces guiding NORESCOs external
co-gen expertise the opportunity to bring to - fruition the implementation of a major piece of
the carbon neutrality puzzle - If were serious about carbon neutrality we
have to get aggressive with this stuff To
that end, NORESCO can help.
34Results, Conclusions, and Recommendations
35Conclusions
- Assuming 26/Tonne carbon regulation costs added
to purchased power price - Assuming the sale of emission reductions to
Colorado Carbon Fund at 20/Tonne - Up to a natural gas commodity price of
10.08/MMBtu, refurbishment of one existing
turbine to extend it service life may result in a
net monetary savings to the university and an
annual reduction of 36,385 tonnes of CO2
emissions. - For natural gas prices between 10.08/MMBtu and
11.55/MMBtu a reduction of 22,836 tonnes CO2 can
be achieved via capitalizing a new 5MW turbine. - Recent spot prices for natural gas have re
reached 10.50/MMBtu but EIA projections of
industrial prices point to a return of recent
averages between 7-8 soon and fluctuations
within that range until 2022.
36Lower Heat Rates (Higher Efficiency) Necessary
37/kWh Comparison Between Generated and Purchase
Power
Capital costs and standby utility charges included
38Recommendations
- Acceleration in establishing milestones for
reductions in energy use and emissions as
necessitated buy ACUPCC obligations and voluntary
participation in the governors goals. - Formalize projections of demand growth due to
Capital Improvement Plan - Policy formalized regarding fuel price risks
(with or without cogen this is a significant
concern). - Commission of a more detailed professional
analysis incorporating the latest and most
efficient cogeneration technologies properly
configured to UCBs utility demand cycle. - With the advent of Xcels smart grid in Boulder ,
UCB should investigate reevaluating how it
connects to the grid and how the rate structure
effects generation on campus.
39Thanks to
- Utility Services for help with CHP and utility
rate data - The Office of Campus Resource Conservation for
help with building performance data - Environmental Center staff for on one hand
telling us how complex this issue is and on the
other hand pushing for results