Title: NDDOT Environmental Section
1NDDOTEnvironmental Section
- Changes in Material Clearance Procedures
Nicole Kunkel, Environmental Section Bob
Christensen, Cultural Resources Section
2(No Transcript)
3(No Transcript)
4(No Transcript)
5(No Transcript)
6Environmental and Cultural Resource
ClearanceWhy It's Important
7Why is Cultural ResourceClearance Required?
- Necessary for every project that is proposed.
- Section 106 of the National Historic Preservation
Act. - Section 4(f) of the 1966 U.S. Department of
Transportation Act.
8Preserve Historic Landmarks
9Preserve Historic Forts
10Preserve Historic Tribal Sites
11Why is EnvironmentalClearance Required?
- Necessary if there is a federal action.
- National Environmental Policy Act of 1969 (NEPA).
- Clean Water Act of 1972 (CWA).
- Executive Order 11990.
12Protection of Prairie Potholes
13Wildlife Habitat
14Waterfowl Habitat
15Balancing Development and the Environment
- We need roads so that we can travel and transport
goods throughout our state and to/from other
areas of the country. - Often, this means impacting the environment for
the sake of development. - The Environmental Section works to avoid or
minimize wetland impacts and to preserve the
benefits wetlands create through mitigation.
16(No Transcript)
17(No Transcript)
18Environmental Section tasks
- The Environmental Section covers a lot of
different jobs including, but not limited to - Wetland Delineations
- Wetland Mitigation and Monitoring
- Jurisdictional Requests
- Section 404, Floodplain, and Sovereign Lands
Permits - Material Source Clearance (more on this in a bit)
- PCR PSE reviews
- Tracking Environmental Commitments
- Driveway Permits
- Essentially, the Environmental Section is
involved throughout the entire life of a project.
19Environmental Section staff
- Sheri Lares, Section Leader slares_at_nd.gov
- Tom Huncovsky thuncovsky_at_nd.gov
- Steve Kessler skessler_at_nd.gov
- Mike Bingle-Davis madavis_at_nd.gov
- Nicole Kunkel nkunkel_at_nd.gov
- Dan Ackerman dackerman_at_nd.gov
20Cultural Resources Section Staff
- Bob Christensen, Section Leader rchriste_at_nd.gov
- Jeani Borchert jborcher_at_nd.gov
- Greg Wermers gwermers_at_nd.gov
- Valerie Barbie vbarbie_at_nd.gov
21Material SourcesNew Clearance Process
22Whats not changing?
- Material sources will still need to be cleared by
the Environmental and Cultural Resources
Sections. - Request forms will still be necessary for new and
expanding sites. - The Material Source Approval Request form will
still be located on the NDDOT website. - Certificates of Approval will continue to be
issued.
23New Process
- The new clearance process is now in effect in the
Environmental and Cultural Resource Sections - The website new material source form will be
accessible through the NDDOT homepage soon. - Several main improvements.
- Quick access to Certificates of Approval for
sites that are approved. - Sites are approved by legal location rather than
project. - Forms can be submitted directly to the
Environmental Section, rather than through the
Project Engineer. - Less paperwork faster turnaround times overall.
24Why the new process?
- Significant increase in submittal of Material
Source Approval Request forms in the past three
years - 2006 approximately 250 requests
- 2007 approximately 450 requests
- 2008 more than 1000 requests
- Concerns from stakeholders
- Every site required approval for each project it
was used for. - Length of time to approve sites.
- Please remember that Section 107.04 of the
Standard Spec. allows at least 30 calendar days
for approval of material source requests due to
additional USFWS / Cultural Resource clearance
for certain sites).
25Material Source Requests
- If a Certificate of Approval is not on the
website for the desired location, you will need
to submit a request form. - Sites that will be expanding beyond the area
shown in the Certificate of Approval will need to
be submitted for the full approval process. - Previously approved sites will be reissued a
Certificate of Approval at the beginning of each
calendar year if there are no conflicts.
26Applicant
- Check website for Cert. of Approval
Site Not Approved
Site Previously Approved
- Submit Material Source Approval Request Form
- Print Cert. of Approval
- Submit to Project Engineer for inclusion in the
project record
Environmental Clearance
Cultural Resources Clearance
Approved
Not Approved
- Certificate of Approval
- Receive notification that the Cert. of Approval
is on the website - Print Certificate of Approval
- Submit to Project Engineer for inclusion in the
project record
- Denial Memorandum
- Applicant is notified that a different material
source area must be selected
27Differences in the Process for Different
Applicants
- This step in the process takes place once the
website has been checked and the site is not yet
approved - Contractors Submit request form to Environmental
Section. - Materials and Research Coordinate with USFWS to
avoid Section 4(f) properties. Record the site
with GPS unit and enter information into GIS
database after testing has occurred. Submit
request form to Environmental Section. - Right of Way Coordinate with Environmental
Section to avoid Section 4(f) properties. Submit
request form to Environmental Section.
28Form Submittal Changes
- As previously stated, if a Certificate of
Approval is on the website for the desired
location (and the site will not be expanding),
then a new request form will not be required. - The Request Form for new and expanding sites
should be filled out electronically and submitted
with a clear map via email to the
materialsource_at_nd.gov inbox. - Forms can still be filled out, printed, and
mailed to the Environmental Section with a map
however, they will take longer to approve due to
the added mailing time.
29Blank Form
Example
30Example Maps
31Avoidance Areas and Easements
- Avoidance Areas highlight any locations within a
site that cannot be impacted. - Include easement and non-easement wetlands and
cultural resource areas. - When the material source location is under USFWS
easement, the approval process takes longer. - The Environmental Section must coordinate with a
representative from the USFWS Wetlands Management
District (WMD) that the site is located in. - After meeting at the site, the USFWS WMD
representative must send a letter of approval to
the Environmental Section.
32Certificates of Approval
- Certificates of Approval will be available on the
NDDOT website. - http//www.dot.nd.gov/dotnet2/materialsource/certi
ficatesofapproval.aspx - A Certificate of Approval will still be required
for every material source site that will be used
for a project. - The Design Project Engineer or Construction
Project Engineer will place the Certificate of
Approval in the project record.
33(No Transcript)
34(No Transcript)
35(No Transcript)
36(No Transcript)
37Certificate of Approval Renewal
- All sites (except borrow) will be reviewed for
renewal every winter. - Borrow sites will be renewed every year for 3
years to ensure that they will be available for
their specific project. - USFWS needs to review material source sites
annually to ensure that there will be no impact
to their interests. - The Threatened and Endangered Species List is
updated every 90 days, so the NDDOT negotiated to
review sites once a year instead of every 3
months.
38Reminders
- Double-check for accuracy when filling out
Request Forms. Incorrect township, section, and
range is the most common error. - Use maps that clearly show the legal location and
the area that the site will encompass. - Certificates of Approval are required for the
material placed at stockpile locations, as well
as the stockpile locations themselves. - Feel free to send any questions to the NDDOT
Material Source email inbox materialsource_at_nd.gov
39Special Thanks
- Bob Christensen, Cultural Resources Section
- Tom Huncovsky, Environmental Section
- Greg Wermers, Cultural Resources Section
- And everyone who has put time and effort into
making this project happen.
40http//www.dot.nd.gov/dotnet2/materialsource/ cert
ificatesofapproval.aspx