Title: Performance of Michigans Stabilized Base Projects
1Performance of Michigans Stabilized Base Projects
Andy Bennett, MDOT Will Hansen, UM Dave Smiley,
formerly MDOT
2Background
- Before 1984 MDOT used a dense-graded base design
without drainage systems. - Over time, poor base drainage led to premature
joint deterioration and faulting (roughness) at
joints and cracks from the movement of base fines
under high pore pressures (from heavy wheel
loads) directly under the pavement slab (JRCP)
3Background
- MDOT started experimenting in 1990 with recycled
aggregate for base coarse. The primary purpose of
the treatment was to coat the aggregate
particles, if crushed concrete from the old
pavement was used, to prevent any leaching
concrete residue from clogging the drainage layer
or the internal drainage system. A secondary
benefit was to provide stability to the aggregate
matrix, which was a gap-graded gradation (5G)
that was selected to enhance drainage.
4Special Provision for Stabilized Open Graded
Drainage Coarse
- Contractors had a choice of stabilizing with
asphalt cement, asphalt emulsion, or cement . - Cement content for stabilization called for
approximately 6 (190 lbs/CYD). - Asphalt stabilization option called for
sufficient stability and coating of the surface
particles (approximately 3). - Aggregate gradation 5G obtained only from crushed
concrete from the project.
5Stabilized Base Projects
- 13 projects were constructed with 4 stabilized
base between 1990 and 1995. - 2 projects were stabilized with cement and 11
projects with asphalt. - Asphalt emulsion was used on the majority of
projects because it was less expensive.
6Background MDOT Base Gradations
7 Construction Concrete
Crushing Operation
8Construction-Pug Mill Emulsion Coating (ATB)
9Stabilized Bases as Constructed
6 cement treated base
Asphalt emulsion treated base
10Construction- CTB Project Paving
112006 Field Investigation
12Excessive Joint Deflection Leading to Top-Down
Transverse Cracking
13Typical Distress Developmentfor JRCPs on
Treated versus Untreated Open-Graded Bases
14Performance Modeling Using Distress Index
15Performance Modeling Using Distress Index
16Comparison of Distress Between Treated and
Untreated Base Projects Constructed 1990-95
17Joint Deflection Treated vs Untreated Base
18Agg Test Road-27 ft JRCP 10.5 inch Concrete on 4
inch ATB
19Agg. Test Road-Section B
20Dowel-Bar Action
21SB US-23 Agg.Test Road-Section A Surface Profile
showing joint Settlement-Agg
22WB I-94, CS 82021, Belleville, 27 Ft JRCP 11
inch Concrete 4 inches CTB
23Cost Comparison of Open Graded Drainage Coarse
- I-94WB Wayne Co., 4 cement coated recycled 5G,
393,000 SYDs _at_ 2.35/SYD, constructed 1992 - I-96 Howell, 4 asphalt emulsion coated recycled
5G, 360,000 SYDs _at_ 1.35/SYD, constructed in
1991-1992 - I-75 Wayne Co., 4 asphalt emulsion coated
recycled 5G, 464,000 SYDs _at_ 1.90/SYD,
constructed in 1991 - I-69 Eaton Co., 5 3GM1 (not recycled concrete),
457,000 STDs _at_ 3.20/SYD (project 21823A)
346,000 SYDs _at_ 2.70/SYD (project 21824A)
307,000 SYDs _at_
2.69/SYD (project 21825A)
166,000 SYDs _at_ 2.69/SYD (project 21826A)
Projects constructed between
1991 and 1993
24Major Findings
- JRCP on Treated base (ATB/CTB) OGDC was found to
have improved joint stability (smaller joint
deflection) as compared to JRCP on untreated
base. Consequently, a reduction in top-down
transverse cracking developed during the
time-period studied (15 years) with no upward
trend in distress index. - Excessive joint deflection developed in JRCP on
untreated 3G (MDOT gradation) OGDC requiring
maintenance within 15 years.
25Findings contd
- Poor sub-surface drainage condition was
- found to promote permanent joint settlement in
some of the stabilized base projects.
26Findings contd
- In slag concrete dowel-bar looseness
develops as the coarse aggregate cannot maintain
joint load transfer through dowel-bar action.
Almost all joint load transfer through dowel-bar
action is lost within the time period studied.
This has promoted mid-slab transverse cracking as
seen from the Aggregate Test Road results.
27Recommendations
- Stabilized base-course can be expected to
- improve performance of jointed plain concrete
pavement (JPCP) for Michigan conditions of
traffic and wet-freeze climate.