Performance of Michigans Stabilized Base Projects - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Performance of Michigans Stabilized Base Projects

Description:

MDOT started experimenting in 1990 with recycled aggregate ... any leaching concrete residue from clogging the drainage layer or the internal drainage system. ... – PowerPoint PPT presentation

Number of Views:30
Avg rating:3.0/5.0
Slides: 28
Provided by: andybe
Category:

less

Transcript and Presenter's Notes

Title: Performance of Michigans Stabilized Base Projects


1
Performance of Michigans Stabilized Base Projects
Andy Bennett, MDOT Will Hansen, UM Dave Smiley,
formerly MDOT
2
Background
  • Before 1984 MDOT used a dense-graded base design
    without drainage systems.
  • Over time, poor base drainage led to premature
    joint deterioration and faulting (roughness) at
    joints and cracks from the movement of base fines
    under high pore pressures (from heavy wheel
    loads) directly under the pavement slab (JRCP)

3
Background
  • MDOT started experimenting in 1990 with recycled
    aggregate for base coarse. The primary purpose of
    the treatment was to coat the aggregate
    particles, if crushed concrete from the old
    pavement was used, to prevent any leaching
    concrete residue from clogging the drainage layer
    or the internal drainage system. A secondary
    benefit was to provide stability to the aggregate
    matrix, which was a gap-graded gradation (5G)
    that was selected to enhance drainage.

4
Special Provision for Stabilized Open Graded
Drainage Coarse
  • Contractors had a choice of stabilizing with
    asphalt cement, asphalt emulsion, or cement .
  • Cement content for stabilization called for
    approximately 6 (190 lbs/CYD).
  • Asphalt stabilization option called for
    sufficient stability and coating of the surface
    particles (approximately 3).
  • Aggregate gradation 5G obtained only from crushed
    concrete from the project.

5
Stabilized Base Projects
  • 13 projects were constructed with 4 stabilized
    base between 1990 and 1995.
  • 2 projects were stabilized with cement and 11
    projects with asphalt.
  • Asphalt emulsion was used on the majority of
    projects because it was less expensive.

6
Background MDOT Base Gradations
7
Construction Concrete
Crushing Operation
8
Construction-Pug Mill Emulsion Coating (ATB)
9
Stabilized Bases as Constructed
6 cement treated base
Asphalt emulsion treated base
10
Construction- CTB Project Paving
11
2006 Field Investigation
12
Excessive Joint Deflection Leading to Top-Down
Transverse Cracking
13
Typical Distress Developmentfor JRCPs on
Treated versus Untreated Open-Graded Bases
14
Performance Modeling Using Distress Index
15
Performance Modeling Using Distress Index
16
Comparison of Distress Between Treated and
Untreated Base Projects Constructed 1990-95
17
Joint Deflection Treated vs Untreated Base
18
Agg Test Road-27 ft JRCP 10.5 inch Concrete on 4
inch ATB
19
Agg. Test Road-Section B
20
Dowel-Bar Action
21
SB US-23 Agg.Test Road-Section A Surface Profile
showing joint Settlement-Agg
22
WB I-94, CS 82021, Belleville, 27 Ft JRCP 11
inch Concrete 4 inches CTB
23
Cost Comparison of Open Graded Drainage Coarse
  • I-94WB Wayne Co., 4 cement coated recycled 5G,
    393,000 SYDs _at_ 2.35/SYD, constructed 1992
  • I-96 Howell, 4 asphalt emulsion coated recycled
    5G, 360,000 SYDs _at_ 1.35/SYD, constructed in
    1991-1992
  • I-75 Wayne Co., 4 asphalt emulsion coated
    recycled 5G, 464,000 SYDs _at_ 1.90/SYD,
    constructed in 1991
  • I-69 Eaton Co., 5 3GM1 (not recycled concrete),
    457,000 STDs _at_ 3.20/SYD (project 21823A)
    346,000 SYDs _at_ 2.70/SYD (project 21824A)
    307,000 SYDs _at_
    2.69/SYD (project 21825A)
    166,000 SYDs _at_ 2.69/SYD (project 21826A)
    Projects constructed between
    1991 and 1993

24
Major Findings
  • JRCP on Treated base (ATB/CTB) OGDC was found to
    have improved joint stability (smaller joint
    deflection) as compared to JRCP on untreated
    base. Consequently, a reduction in top-down
    transverse cracking developed during the
    time-period studied (15 years) with no upward
    trend in distress index.
  • Excessive joint deflection developed in JRCP on
    untreated 3G (MDOT gradation) OGDC requiring
    maintenance within 15 years.

25
Findings contd
  • Poor sub-surface drainage condition was
  • found to promote permanent joint settlement in
    some of the stabilized base projects.

26
Findings contd
  • In slag concrete dowel-bar looseness
    develops as the coarse aggregate cannot maintain
    joint load transfer through dowel-bar action.
    Almost all joint load transfer through dowel-bar
    action is lost within the time period studied.
    This has promoted mid-slab transverse cracking as
    seen from the Aggregate Test Road results.

27
Recommendations
  • Stabilized base-course can be expected to
  • improve performance of jointed plain concrete
    pavement (JPCP) for Michigan conditions of
    traffic and wet-freeze climate.
Write a Comment
User Comments (0)
About PowerShow.com